|
---|
Category:E-Mail
MONTHYEARML24303A3142024-10-25025 October 2024 Notification of Shearon Harris Nuclear Power Plant FEI and Information Request IR 05000261/20240042024-10-0303 October 2024 Document Request for Robinson Nuclear Plant - Radiation Protection Inspection - Inspection Report 05000261/2024004 ML24227A9572024-08-14014 August 2024 LRA - Requests for Additional Information - Set 1 (Email to Applicant) ML24187A0262024-07-0303 July 2024 NRR E-mail Capture - Change in Review Schedule - Harris Risk-Informed Process for Evaluations Exemption (L-2024-LLE-0004) ML24179A1292024-06-24024 June 2024 Acceptance Review for LAR to Revise TS to Adopt TSTF-234-A, Revision 1 ML24164A0052024-06-11011 June 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes February 15, 2024, Relief Request RA-23-0300 for Robinson ML24113A2522024-04-22022 April 2024 NRR E-mail Capture - Audit Plan - Shearon Harris Nuclear Power Plant, Unit 1 - RIPE Exemption 10 CFR 50.55a(h)(2) (L-2024-LLE-0004) ML24101A0522024-04-10010 April 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - ITS Alignments LAR (L-2023-LLA-0078) ML24101A0542024-04-10010 April 2024 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0244 - Extend CT for Accumulators - CLIIP (L-2024-LLA-0032) ML24079A3062024-03-19019 March 2024 NRR E-mail Capture - Acceptance Review Results for Robinson - Proposed Relief Request RA-23-0300 ML24145A1732024-02-26026 February 2024 002 Radiation Safety Baseline Inspection Information Request ML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML24002A7382024-01-0202 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes August 20, 2023, License Amendment Request for Robinson, Unit 2 ML23262B4502023-09-19019 September 2023 NRR E-mail Capture - H. B. Robinson Steam Electric Plant, Unit 2 - Acceptance of License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures Based on Leak-Before-Break Methodology ML23220A2342023-08-0808 August 2023 NRR E-mail Capture - Robinson, Unit 2 - Acceptance Review Results for Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule ML23177A1992023-06-26026 June 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-23-0005 - LAR to Align Certain TSs with ISTS (L-2023-LLA-0078) ML23172A0132023-06-20020 June 2023 Duke Fleet - Correction to June 2, 2023, Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23153A1892023-06-0202 June 2023 Duke Fleet - Request for Additional Information Proposed License Amendment Request to Revise Restrictive Surveillance Requirement Frequencies ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23131A4192023-05-10010 May 2023 003 Radiation Safety Baseline Inspection Information Request ML23124A1212023-05-0404 May 2023 Acceptance of Requested Licensing Action Duke Fleet Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23082A0432023-03-23023 March 2023 002 Radiation Safety Baseline Inspection Information Request Final ML23073A2282023-03-13013 March 2023 Duke Fleet- Adoption of TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements - Acceptance Review ML23065A0942023-03-0606 March 2023 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-22-0081 - LAR to Address Administrative Changes to the Operating License and Technical Specifications (L-2023-LLA-0020) ML23058A0562023-02-27027 February 2023 Acceptance of Amendment to Revise Surveillance Frequencies for RCS Pressure Isolation Valve Operational Leakage Testing and Reactor Trip System Instrumentation ML23048A1512023-02-16016 February 2023 Acceptance Review - Proposed Alternative for Steam Generator Welds (L-2023-LLR-0003) ML23011A0152023-01-11011 January 2023 NRR E-mail Capture - Request for Additional Information to Dukes Request for Robinson to Add Feedwater Isolation Function to TS 3.3.2 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML22285A1552022-10-12012 October 2022 NRR E-mail Capture - H. B. Robinson, Unit 2 - Acceptance of License Amendment Request Regarding the Addition of Feedwater Isolation Function to TS 3.3.2 and Removal of Obsolete Content from TS 2.1.1.1 and TS 5.6.5.b ML22237A1632022-08-25025 August 2022 004 Radiation Safety Baseline Inspection Information Request ML22222A1082022-08-10010 August 2022 NRR E-mail Capture - Request for Additional Information Regarding Dukes Request to Remove 4.160 Kv Bus 2 from Surveillance Requirement 3.8.1.16 ML22146A3652022-05-25025 May 2022 Acceptance of Requested Licensing Action License Amendment Request for Application to Revise Surveillance Requirement 3.8.1.16 ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 ML22108A0182022-04-15015 April 2022 NRR E-mail Capture - Accepted for Review - Duke Energy Relief Request for Harris Nuclear Plant Inservice Testing Program Plan - Fourth Ten-Year Interval to Extend Type C Test to 75 Months ML22083A0702022-03-24024 March 2022 NRR E-mail Capture - Catawba Nuclear Station, Units 1 and 2, Shearon Harris Nuclear Power Plant, Unit 1, and McGuire Nuclear Station, Units 1 and 2 - Acceptance Review for TSTF-569 LAR ML22083A0282022-03-23023 March 2022 Email Snsb Safety Evaluation for Harris LAR to Revise Reactor Protection System TS ML22080A0042022-03-18018 March 2022 Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML22038A1572022-02-0707 February 2022 NRR E-mail Capture - Duke Energy Fleet - Acceptance of License Amendment Request Regarding Adoption of TSTF-541, Revision 2 ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22012A3662022-01-12012 January 2022 Acceptance of Requested Licensing Action License Amendment Re2uest for Application to Revise Technical Specification to Adopt TSTF-577, Revised Frequencies for Steam Generating Tube Inspections ML22005A0872022-01-0505 January 2022 Acceptance of Requested Licensing Action Correction to Non-Conservative Technical Specifications Figure 3.4.3-2, Pressure/Temperature Limit Cooldown Curves ML21361A0122021-12-23023 December 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Relocate Emergency Operations Facility ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21321A3782021-11-16016 November 2021 NRR E-mail Capture - Energy Harbor Fleet, Beaver Valley Units 1 and 2 and DAVIS-BESSEL Unit 1 - Acceptance of License Amendment Request Adoption of TSTF-554 EPID-L-2021-LLA-0193 ML21295A2992021-10-22022 October 2021 Document Request for Robinson Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021004 ML21288A0802021-10-15015 October 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1 - RA-21-0213 - Remove Limitations to Perform Certain SRs During Shutdown (L-2021-LLA-0167) ML21286A6612021-10-13013 October 2021 Acceptance for Review of Proposed Alternative ISI-05-017 for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections ML21295A0372021-10-0505 October 2021 NRR E-mail Capture - Accepted for Review - Duke Energy Fleet License Amendment Request to Adopt TSTF-577 Revised Frequencies for Steam Generator Tube Inspections ML21252A0112021-08-30030 August 2021 NRR E-mail Capture - Acceptance Review - Shearon Harris Nuclear Power Plant, Unit 1- RA-21-0191 - Revised TS Related to Reactor Trip System Instrumentation (L-2021-LLA-0149) 2024-08-14
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24212A3412024-07-31031 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24164A0052024-06-11011 June 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes February 15, 2024, Relief Request RA-23-0300 for Robinson ML24101A0522024-04-10010 April 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - ITS Alignments LAR (L-2023-LLA-0078) ML24058A2462024-03-18018 March 2024 – Supplemental Information Needed for Using the Risk-Informed Process for Evaluations for the Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) ML24025A1592024-01-25025 January 2024 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 - Request for Additional Information - Rvi AMP and Inspection Plan (L-2023-LLL-0016) ML24002A7382024-01-0202 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Dukes August 20, 2023, License Amendment Request for Robinson, Unit 2 ML23235A0552023-08-23023 August 2023 – Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) ML23151A3482023-05-30030 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML23142A2732023-05-22022 May 2023 Duke Fleet - Request for Additional Information Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) ML23082A0432023-03-23023 March 2023 002 Radiation Safety Baseline Inspection Information Request Final ML23047A4512023-02-21021 February 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000261/2023402 ML23020A1252023-01-23023 January 2023 Notification of Target Set Inspection and Request for Information (NRC Inspection Report 05000400/2023403) ML23011A0152023-01-11011 January 2023 NRR E-mail Capture - Request for Additional Information to Dukes Request for Robinson to Add Feedwater Isolation Function to TS 3.3.2 and Remove Obsolete Content from TSs 2.1.1.1 and 5.6.5.b ML22222A1082022-08-10010 August 2022 NRR E-mail Capture - Request for Additional Information Regarding Dukes Request to Remove 4.160 Kv Bus 2 from Surveillance Requirement 3.8.1.16 ML22115A1412022-04-25025 April 2022 NRR E-mail Capture - Duke Common EOF Relocation - Request for Addition Information ML22112A1482022-04-22022 April 2022 Correction_H. B. Robinson Steam Electric Plant, Unit 2 - Request for Additional Information Regarding Supplemental Response to Generic Letter 2004-02 ML22080A0042022-03-18018 March 2022 Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections ML21354A8612021-12-15015 December 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet Request RA-19-0352 - Alternative for RPV Closure Stud Exams (L-2020-LLR-0156) ML21258A3652021-09-15015 September 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000400/2021011) and Request for Information (RFI) ML21172A2432021-06-21021 June 2021 NRR E-mail Capture - Request for Additional Information - Harris RA-20-0252 - LAR to Remove Extraneous Requirements from OL and TS (L-2021-LLA-0027) ML21036A1142021-02-0505 February 2021 NRR E-mail Capture - Request for Additional Information - Harris - Relief Request RA-20-0312 - SW Pinhole Leak (L-2020-LLR-0143) ML21049A2632021-02-0404 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Energy Fleet License Amendment Request to Revise Emergency Plan ML21032A0492021-02-0101 February 2021 NRR E-mail Capture - Request for Additional Information - Duke Fleet RA-20-0263 - Use of Later ASME B&Pv, XI for Repair - Replacement (L-2020-LLR-0124) ML20353A1312020-12-18018 December 2020 2021 Hbr 50.59 Info Request ML20323A4072020-11-18018 November 2020 NRR E-mail Capture - Request for Additional Information - Brunswick License Exemption Request from 10CFR73 Annual Force on Force Exercise Requirements (EPIC L-2020-LLE-0180) ML20297A3072020-10-13013 October 2020 NRR E-mail Capture - Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - RCS Flowrate Reduction/Lbloca LAR ML20274A0462020-09-29029 September 2020 Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 ML20247J3822020-09-0303 September 2020 Request for Additional Information - Shearon Harris Nuclear Power Plant, Unit 1 - Revise TS Related to Accident Monitoring and RFO Instrumentation ML20191A2122020-07-0909 July 2020 012 FPTI Notification Letter ML20063L4562020-02-0404 February 2020 NRR E-mail Capture - RAI - Robinson Relief Req Rx Vessel Cold Leg Nozzle Dissimilar Meter Butt Weld Inspection Interval EPID L-2019-LLR-0072 ML20022A1942020-01-22022 January 2020 Emergency Preparedness Program Inspection Request for Information ML19365A0462019-12-18018 December 2019 Audit Documents Needed for the Robinson SPRA Review ML19331A4002019-11-27027 November 2019 Request for Additional Information Regarding Licensing Action to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type ML19288A2942019-10-15015 October 2019 NRR E-mail Capture - RAIs for Robinson Revision to RPV Surveillance Program Withdrawal Schedule ML19283A0372019-09-26026 September 2019 Draft Requests for Additional Information for H.B. Robinson LAR to Revise TS 3.8.2, AC Sources - Shutdown, SR 3.8.2.1 ML19288A2462019-09-26026 September 2019 Request for Additional Information Regarding Change to Surveillance Requirement 3.8.2.1 H.B. Robinson Unit No. 2 ML19204A2682019-07-23023 July 2019 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for the Escw System TS AOT Extension and Removal of an Expired Note in TS Risk Informed LAR (L-2019-LLA-0025) ML19136A2712019-05-28028 May 2019 Supplemental Information Needed for Acceptance of Requested Licensing Action Regarding License Amendment Request to Modify the Departure from Nucleate Boiling Ratio Safety Limit to Address Transition to New Fuel Type ML19060A0912019-03-18018 March 2019 Request for Additional Information Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML19072A0292019-03-13013 March 2019 50.69 LAR RAIs ML19011A1372019-01-10010 January 2019 NRR E-mail Capture - Duke Energy Fleet RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML19007A3422018-12-21021 December 2018 NRR E-mail Capture - Duke Energy Fleet Draft RAIs - Relief Request 18-GO-001 - Proposed Alternative for Depth Sizing Qualification Examination of Welds (L-2018-LLR-0117) ML18337A1272018-11-28028 November 2018 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information Regarding the Rts/Esfas Trip Setpoints Modification LAR ML18332A4392018-11-28028 November 2018 NRR E-mail Capture - Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information for EAL Scheme Changes ML18291A6442018-10-17017 October 2018 NRR E-mail Capture - Robinson RAIs - Duke Energy 10 CFR 50.46 Annual Report ML18288A0192018-10-12012 October 2018 NRR E-mail Capture - Robinson RAIs - LAR to Allow Implementation of the Provisions 10 CFR 50.69 (EPID L 2018-LLA-0095) and LAR to Adopt TSTF-425 ML18264A0282018-10-0909 October 2018 RAI Regarding License Amendment Request to Adopt 10 CFR 50.69, Risk Informed Categorization Aad Treatment of Structures, Systems and Components for Nuclear Power Reactors ML18274A2632018-09-28028 September 2018 NRR E-mail Capture - Robinson Draft RAIs - LAR to Allow Implementation of the Provisions 10 CFR 50.69 (EPID L 2018-LLA-0095) and LAR to Adopt TSTF-425 ML18211A6042018-07-30030 July 2018 NRR E-mail Capture - Robinson Supplemental RAI - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L-2017-LLA-0308) ML18206B0612018-07-25025 July 2018 NRR E-mail Capture - Draft Robinson Supplemental RAI - LAR to Revise TS to Add a 2nd Qualified Offsite Power Circuit and Revise UFSAR to Operate LTCs in Automatic Mode (CAC No. MG0276; L 2017-LLA-0308) 2024-07-31
[Table view] |
Text
NRR-DMPSPEm Resource From: Galvin, Dennis Sent: Monday, December 11, 2017 2:04 PM To: Arthur.Zaremba@duke-energy.com Cc: Joshua.Duc@duke-energy.com
Subject:
Harris and Robinson Supplemental RAI - LAR to adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012)
Attachments: HNP-RNP LAR DPC-NE-3008-3009 Sup RAI APHB 2017-12-11 L-2017-LLA-0012.pdf
SUBJECT:
DUKE ENERGY PROGRESS, LLC, FOR SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1, AND H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 SUPPLEMENTAL REQUEST FOR ADDITIONAL INFORMATION REGARDING APPLICATION TO ADOPT DPC-NE-3008-P, REVISION 0, THERMAL-HYDRAULIC MODELS FOR TRANSIENT ANALYSIS, AND DPC-NE-3009-P, REVISION 0, FSAR /UFSAR CHAPTER 15 TRANSIENT ANALYSIS METHODOLOGY. (CAC NOS. MF8439 AND MF8440; EPID L-2016-LLA-0012)
Mr. Zaremba, By letter dated October 3, 2016, Duke Energy Progress, LLC (Duke Energy or the licensee) submitted a license amendment request (LAR) for Shearon Harris Nuclear Power Plant, Unit 1 (Harris) and H. B. Robinson Steam Electric Plant, Unit No. 2 (Robinson). The proposed amendment requested review, approval, and adoption into the Harris and Robinson Technical Specifications of DPC-NE-3008-P, Revision 0, "Thermal-Hydraulic Models for Transient Analysis," and DPC-NE-3009-P, Revision 0, "FSAR I UFSAR Chapter 15 Transient Analysis Methodology." The LAR supersedes a November 19, 2015, submittal in its entirety, which had submitted DPC-NE-3008-P for review without DPC-NE-3009-P. These methodologies will be used to support the performance of (1) thermal-hydraulic calculations and (2) updated FSAR Chapter 15 transient analysis as part of the reload design analysis for Harris and Robinson. By letter dated September 8, 2017, the U.S. Nuclear Regulatory Commission (NRC) staff issued requests for additional information (RAIs) related to DPC-NE-3009-P. Duke Energy responded on October 9 and 30, 2017.
The NRC staff has reviewed the licensees responses in the October 30, 2017, submittal regarding human actions. The NRC staff has determined that additional information is needed to complete its review regarding the response to NRC-RAI-30 associated with Robinson. The enclosed RAl was e-mailed to the licensee in draft form on December 4, 2017. An RAI clarification call was held on December 11, 2017 and the licensee agreed to provide responses to the RAl by January 10, 2018. The NRC staff agreed with this date.
If you have any questions, please contact me at (301) 415-6256 or Dennis.Galvin@nrc.gov.
Respectfully, Dennis Galvin Project Manager U.S Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Operating Reactor Licensing Licensing Project Branch 2-2 301-415-6256 1
Hearing Identifier: NRR_DMPS Email Number: 38 Mail Envelope Properties (Dennis.Galvin@nrc.gov20171211140300)
Subject:
Harris and Robinson Supplemental RAI - LAR to adopt DPC-NE-3009-P, Revision 0, Thermal-Hydraulic Models for Transient Analysis, (L-2016-LLA-0012)
Sent Date: 12/11/2017 2:03:42 PM Received Date: 12/11/2017 2:03:00 PM From: Galvin, Dennis Created By: Dennis.Galvin@nrc.gov Recipients:
"Joshua.Duc@duke-energy.com" <Joshua.Duc@duke-energy.com>
Tracking Status: None "Arthur.Zaremba@duke-energy.com" <Arthur.Zaremba@duke-energy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2386 12/11/2017 2:03:00 PM HNP-RNP LAR DPC-NE-3008-3009 Sup RAI APHB 2017-12-11 L-2017-LLA-0012.pdf 103991 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
REQUEST FOR ADDITIONAL INFORMATION LICENSE AMENDMENT REQUEST TO ADOPT DPC-NE-3008-P, REVISION 0, THERMAL-HYDRAULIC MODELS FOR TRANSIENT ANALYSIS, AND DPC-NE-3009-P, REVISION 0, FSAR / UFSAR CHAPTER 15 TRANSIENT ANALYSIS METHODOLOGY DUKE ENERGY PROGRESS, LLC SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NOS. 50-400 AND 50-261 By letter dated October 3, 2016, Duke Energy Progress, LLC (Duke Energy or the licensee) submitted a license amendment request (LAR) for Shearon Harris Nuclear Power Plant, Unit 1 (Harris) and H. B. Robinson Steam Electric Plant, Unit No. 2 (Robinson) (Reference 1). The proposed amendment requested review, approval, and adoption into the Harris and Robinson Technical Specifications of DPC-NE-3008-P, Revision 0, "Thermal-Hydraulic Models for Transient Analysis," and DPC-NE-3009-P, Revision 0, "FSAR I UFSAR Chapter 15 Transient Analysis Methodology." The LAR supersedes a November 19, 2015, submittal (Reference 2) in its entirety, which had submitted DPC-NE-3008-P for review without DPC-NE-3009-P. These methodologies will be used to support the performance of (1) thermal-hydraulic calculations and (2) updated FSAR Chapter 15 transient analysis as part of the reload design analysis for Harris and Robinson. By letter dated September 8, 2017 (Reference 3), the U.S. Nuclear Regulatory Commission (NRC) staff issued requests for additional information (RAIs) related to DPC-NE-3009-P. Duke Energy responded on October 9 and 30, 2017 (References 4 and 5).
The NRC staff has reviewed the licensees responses in the October 30, 2017, submittal regarding human actions. The NRC staff has determined that additional information is needed to complete its review regarding the response to NRC-RAI-30 associated with Robinson.
NRC-RAI 30.1 Section 15.2.8 of the Robinson UFSAR states that the feedwater system pipe break event is bounded by the steam system piping failure event. At Robinson, the steam generator (SG) design is such that the main feedwater line break is not expected to result in loss of significant liquid inventory from the SGs, and thus is expected to be a cooldown event that is bounded by the main steam line break.
The response to NRC-RAI-30 states that the existing steam system piping failure analysis credits an operator manual action to isolate auxiliary feedwater (AFW) flow to a faulted SG within 10 minutes. The response states that this action will be credited in any new feedwater system pipe break analysis, should a new analysis be required.
The NRC staff reviewed the credited human actions against the criteria in NUREG-0800, Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants:
LWR [Light Water Reactor] Edition (SRP) Section 18, Human Factors Engineering,
(Reference 6) and NUREG-1764, Guidance for the Review of Changes to Human Actions, (Reference 7).
Please provide the following:
- 1. DPC-NE-3009, Section 5.2.5, states that the credited operator actions for the feedwater system pipe break event are to terminate pumped safety injection and cycle AFW flow.
By contrast, the response to NRC-RAI-30 implies that for Robinson the implicitly credited action is to terminate AFW flow to a faulted SG within 10 minutes (operator actions to terminate pumped safety injection for Robinson are judged unnecessary in the RAI response because the analyzed shutoff pressure of the high-head pumped safety injection is below the reactor coolant system pressure). Please clarify which operator action will be assumed in future Robinson plant analyses, and confirm that cycling AFW flow would be considered a new operator action for Robinson (to be evaluated in accordance with the requirements of 10 CFR 50.59 as stated in the RAI response).
- 2. The RAI response states that the Robinson feedwater system pipe break event is bounded by the steam system piping failure event as a primary system cooldown transient, and thus the credited operator action for the steam system piping failure event is implicitly credited for the feedwater system pipe break event. Clarify whether the future analysis scope, which credits operator manual action to isolate AFW flow to a faulted SG within 10 minutes, includes events other than cooldown events such as, but not limited to, overheating or overpressurization events. If so, please provide details of these events.
- 3. The RAI response states that the operator action and the timing of the action are validated by procedure for the steam system piping failure event. Please provide the rationale (e.g. event timeline operator action validation, event timeline comparisons, etc.) that supports crediting the operator manual action to isolate AFW flow to a faulted SG within 10 minutes (currently credited in the steam system piping failure event) in future feedwater system pipe break event analyses. Please include any areas where feedwater break and main steam break analyses may differ. The rationale should address any other events identified in item 2 above, unless the operator action would be treated as a new operator action for Robinson (to be evaluated in accordance with the requirements of 10 CFR 50.59 as stated in the RAI response).
References
- 1. J. Elnitsky, Duke Energy Progress, LLC, letter to U.S. Nuclear Regulatory Commission, Supplemental Information for License Amendment Request Regarding Methodology Report DPC-NE-3008-P, October 3, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16278A082 (proprietary) and ML16278A080 (non-proprietary)).
- 2. R. Repko, Duke Energy Progress, LLC, letter to U.S. Nuclear Regulatory Commission, Application to Revise Technical Specifications to Adopt Methodology Report DPC-NE-3008-P, Revision 0, "Thermal-Hydraulic Models for Transient Analysis, November 19, 2015 (ADAMS Accession No. ML15323A352 (proprietary) and ML15323A351 (non-proprietary)).
- 3. Galvin, D. J., U.S. Nuclear Regulatory Commission, letter to K Henderson, Duke Energy Progress, LLC, Duke Energy Progress, LLC, for Shearon Harris Nuclear Power Plant, Unit
1, and H. B. Robinson Steam Electric Plant, Unit No. 2 - Request for Additional Information Regarding Application to Adopt DPC-NE-3008-P, Revision 0, "Thermal-Hydraulic Models for Transient Analysis," and DPC-NE-3009-P, Revision 0, "FSAR I UFSAR Chapter 15 Transient Analysis Methodology" (CAC Nos. MF8439 and MF8440), September 8, 2017 (ADAMS Accession Nos. ML17226A263 (proprietary) and ML17226A264 (non-proprietary)).
- 4. J. Donahue, Duke Energy Progress, LLC, letter to U.S. Nuclear Regulatory Commission, Response to Request for Additional Information Regarding Application to Revise Technical Specifications for Methodology Report DPC-NE-3009, Revision 0, October 9, 2017 (ADAMS Accession Nos. ML17282A024 (proprietary) and ML17282A023 (non-proprietary))
- 5. J. Donahue, Duke Energy Progress, LLC, letter to U.S. Nuclear Regulatory Commission, Response to Request for Additional Information (RAI) Regarding Application to Revise Technical Specifications for Methodology Report DPC-NE-3009, Revision 0 (Part 2),
October 30, 2017 (ADAMS Accession Nos. ML17303B205 (proprietary) and ML17303B209 (non-proprietary))
- 6. U.S. Nuclear Regulatory Commission, NUREG-0800, Standard Review Plan, Section 18, Human Factors Engineering, Revision 3, December 2016 (ADAMS Accession No. ML16125A114)
- 7. U.S. Nuclear Regulatory Commission, NUREG-1764, Guidance for the Review of Changes to Human Actions, Revision 1, September 2007 (ADAMS Accession No. ML072640413)