From: Hood, Tanya To: Kim.Maza@duke-energy.com Cc: Earp Jr., Dennis; Vaughan, Jordan L; Zaremba, Arthur H.; Mahoney, Michael

Subject:

Shearon Harris Nuclear Power Plant - Request for Additional Information Regarding License Amendment Request to Adopt TSTF-505, Revision 2 (EPID L-2019-LLA-0218)

Date: Tuesday, September 29, 2020 4:43:00 PM Attachments: Shearon Harris - RAI _TSTF 505.pdf

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 - REQUEST FOR ADDITIONAL INFORMATION REGARDING LICENSE AMENDMENT REQUEST TO REVISE TECHNICAL SPECIFICATIONS TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE (TSTF) TRAVELER TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF [RISK-INFORMED TSTF] INITIATIVE 4B (EPID L-2019-LLA-0218)

Ms. Maza, By letter dated October 7, 2019, Duke Energy Progress LLC (the licensee), submitted a license amendment request (LAR) to amend the Technical Specifications (TSs) for the Shearon Harris Nuclear Power Plant, Unit 1 (Harris). The proposed amendment would modify TSs requirements to permit the use of risk-informed completion times in accordance with the technical specifications task force (TSTF) traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF [risk-informed TSTF] Initiative 4b.

The U.S. Nuclear Regulatory Commission staff has reviewed the licensees submittal and determined that additional information is required in order to complete the review. The requested additional information is attached. The draft questions were sent to Mr. Dennis Earp of your staff to ensure that they were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. A clarification call was held on September 29, 2020. Based on insight from the discussion it was determined that the response will be provided by November 13, 2020.

If you have any questions, please contact me at (301) 4151387 or Tanya.Hood@nrc.gov.

Tanya E. Hood Project Manager Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 11555 Rockville Pike Rockville, Maryland 20852-2738 301-415-1387 Tanya.Hood@nrc.gov