Rev 1 to Technical Dept Procedure TDP-6, NPRDS Failure Reporting.
ML17055B537
Person / Time
Site: Nine Mile Point Constellation icon.png
Issue date: 12/09/1985
From: Rich Smith, Spadafore J, Tomlinson E
NIAGARA MOHAWK POWER CORP.
To:
Shared Package
ML17055B512 List:
References
TDP-6, NUDOCS 8604280284
Download: ML17055B537 (8)


Text

Enclosure 812 NINE MILE POINT NUCLEAR STATION TECHNICAL DEPARTMENT PROCEDURE PROCEDURE NO. TDP-6 NUCLEAR PLANT RELIABILITY DATA SYSTEM (NPRDS) FAILURE REPORTING DATE AND INITIALS APPROVALS SIGNATURES NPRDS Coordinator E. S. Tomlinson Supervisor-Reactor Re G. Smith Super Qnt echnical Services J. R. 'I'ere II ~ /~l Summar of Pa es Revision 1 (Effective 12/9/85 )

PAGES DATE 1-3 December 1985 NIAGARA MOHAWK POWER CORPORATION THIS PROCEDURE NOT TO BE USED AFTER DECKER 1989 SUBJECT TO PERIODIC REVIEW.

8b04280~ 8b04i5 84+"'050004ip PDR ADOCH" PDR P

V f

PDP-6 NUCLEAR PLANT RELIABILITY DATA SYSTEM (NPRDS) FAILURE REPORTING 1.0 PURPOSE This procedure outline's the steps necessary to ensure that all reportable equipment failures are identified and processed in accordance with the INPO NPRDS Reporting Procedures Manual.

2 ' REFERENCES OI-21 "Work Tracking System" NPRDS Reporting Procedures Manual Rev. 10 AP.5.0 3.0 RESPONSIBILITIES 3.1 Planning Clerk - The unit planning clerk will be responsible for ensuring that the NPRDS Coordinat'or receives all Work Requests (WR's) for review.

3 ~2 Unit Supervisor Reactor Analyst The Unit Supervisor will assign a technician to functionally report to the NPRDS Coordinator on a weekly basis.

3.3 General Office Clerk - The general office clerk will supply the NPRDS Coordinator with all operation department occurrence reports (OR's).

3.4 Reactor Analyst Technician << The technician will screen all WR's in accordance with INPO's NPRDS Reporting Procedures Manual. The technician will also review Occurrence Reports and the monthly operating reports to confirm that all reportable failures were found. The technician will also support the NPRDS Coordinator in his efforts by performing various assigned duties.

3.5 NPRDS Coordinator - The NPRDS Coordinator is responsible for maintaining the NPRDS failure reporting system such that failures are reported in a complete and timely manner. The coordinator shall supervise and assign the designated technician's work on a daily basis. The coordinator will review 'and sign all failure reports. As a check the coordinator will review the monthly operating report and

,LER's and confirm that all applicable failures were reported.

3 ' Document Control Clerk - The document control clerk will be responsible for entering the failure data into the INPO computer data base.

TDP-6 -1 December 1985

4.0 Procedure 4.1 The technician receives the WR's and Occurrence Reports from the NPRDS Coordinator.

4.2 Work requests shall be screened to identify reportable failures.

4.2.1 WR's shall first be sorted by system. If the component is it not part of one of the systems listed on attachment 81 is not reportable.

4.2.2 The remaining WR's shall be reviewed in accordance with guidelines given in the Reporting Procedures Manual. A listing of components in the current data base is available for reference. It should be noted that a component may be reportable upon failure and not listed in the base. All questions regarding a failure's reportability shall be directed to the NPRDS coordinator.

4.3 All WR's which are not reportable failures are stamped NOT APPLICABLE and initialled as reviewed.

4 ~4 The technician then fills out a failure report for each applicable failure and marks the box on the WR labeled NPRD with the appropriate NPRDS system code and his initials.

He shall also attach a photocopy of the WR to the failure report. The technician should consult with the NPRDS Coordinator for any questionable concerns.

4.5 The completed WR's shall be returned to the planning clerk in the same numerical order in which they were received.

4.6 The technician shall submit the completed failure reports to the NPRDS coordinator for review and approval.

4.7 After approval the reports are entered into the INPO data base by the document control clerk.

4.8 To verify complete reporting the technician will review the Occurrence Reports and Monthly Operating Reports.

4.9 As a check the NPRDS coordinator will review LER's and the Monthly Operating Reports.

TDP"6 -2 December 1985

Attachment 81 Reactor Vessel Reactor Recirculation Reactor Instrumentation Main Steam Shutdown Cooling Containment Spray Core Spray Emergency Condenser Feedwater - HPCI Condensate - Condensate Storage and Transfer Liquid Poison Control Rod Drive Drywell Coolers

,Service Water, Diesel Generator Cooling Water, Containment Spray Raw Water Reactor Building Closed Loop Cooling Emergency Ventilation Containment Vent and Purge Isolation Valves and Control Circuits Penetrations - Hatches Torus Monitoring and Vacuum Relief Main Steam Line Rad Monitors and Ventilation Rad Monitors Diesel Generator and Auxiliaries Electrical Distribution (All circuit breakers)

MG Sets - RPS Buses DC Power RPS Instrumentation neutron Monitoring TDP-6 -3 December 1985