Semantic search

Jump to navigation Jump to search
 Issue dateTitleTopic
ML18041A07327 July 1999Rev 1 to NMP2-ISI-006, Second Ten Year Interval Inservice Insp Program Plan for Nine Mile Point Nuclear Power Station Unit 2.Safe Shutdown
Weld Overlay
Hydrostatic
Nondestructive Examination
VT-2
Liquid penetrant
Dissimilar Metal Weld
Scaffolding
Backfit
ML17059B2914 September 1996NMP Nine Mile Point Nuclear Station Unit 2,Pump & Valve First Ten-Yr Inservice Testing Program Plan.
ML17059B02215 February 1995Rev 0 to UT-NMP-311V0, Procedure for Manual Ultrasonic Exam of Nozzles Inner Radius & Bore.Nondestructive Examination
ML17059B02010 February 1995Rev 0 to UT-NMP-703V0, Procedure for Geris 2000 Ultrasonic Exam of RPV Nozzle Inner Radius & Bore Regions.Non-Destructive Examination
Nondestructive Examination
ML17059B02110 February 1995Rev 0 to UT-NMP-309V0, Procedure for Manual Ultrasonic Exam of Planar Flaw Sizing for Nozzle Inner Radius & Bore Regions.
ML17059A88818 January 1995Rev 0 to Field Disposition Instruction 0245-90800, Shroud.
ML17059A5669 November 1994Rev 2 to Emergency Plan Maint Procedure EPMP-EPP-08, Maint, Testing & Operation of Oswego County Prompt Notification Sys.Health Physics Network
ML17059A4246 July 1994Rev 14 to Nine Mile Point Nuclear Station Unit 1 Odcm.Grab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
ML18040A29417 December 1993Rev 13 to Nine Mile Point Nuclear Station Unit 1 Odcm.Grab sample
Offsite Dose Calculation Manual
ML17059A09725 October 1993Rev 4 to NMP2-IST-001,NMP,Nine Mile Point Nuclear Station, Unit 2,Pump & Valve First Ten-Yr Inservice Testing Program Plan.Stroke time
Hydrostatic
Squib
Cold shutdown justification
ML20056G66925 February 1993Rev 8 to OdcmGrab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
Process Control Program
ML17056C29730 June 1992NMPNS - Unit 2 Odcm.Grab sample
Annual Radioactive Effluent Release Report
ML17056B98426 June 1992Rev 9 to Nine Mile Point Nuclear Station Unit 1 Odcm.Grab sample
Annual Radiological Environmental Operating Report
ML18038A4851 October 1991Rev 3 to First 10-Yr ISI Program Plan. W/910930 Ltr
ML17058A9562 May 1991Rev 5 to Administrative Procedure AP-3.7.1, Unit 2 Radwaste Process Control Program.Process Control Program
ML18038A3531 May 1991Rev 3 to NMP2-IST-001, Niagara Mohawk Power Corp,Nine Mile Point Nuclear Station Unit 2 - Pump & Valve First Ten Year Inservice Testing Program Plan. W/910501 LtrSafe Shutdown
Stroke time
Squib
Power-Operated Valves
ML20070U3621 April 1991Cover Page to Rev 1 to Issue 2 to Nuclear Security Training & Qualification Plan
ML17058A9546 March 1991Rev 4 to Administrative Procedure AP-3.7.1, Unit 2 Radwaste Process Control Program.Process Control Program
ML18038A32730 June 1990Rev 3 to Nine Mile Point Requalification Program Action Plan.
ML17056B98315 June 1990Rev 8 to Nine Mile Point Nuclear Station Unit 1 Odcm.
ML17056A9673 April 1990Rev 8 to Odcm.
ML18038A32428 February 1990Rev 5 to Odcm.
ML17056A96627 February 1990Rev 7 to Odcm.
ML18038A29212 September 1989Rev 3 to Administrative Procedure AP-3.7.1, Unit 2 Radwaste Process Control Program.Process Control Program
ML17055E5582 March 1989Rev 1 to Restart Action Plan.Fire Barrier
Nondestructive Examination
Scram Discharge Volume
Exemption Request
ML19325C17414 February 1989Rev 1 to AP-3.7.1, Process Control Program.Process Control Program
Annual Radiological Effluent Release Report
ML17055E47716 January 1989Second 10-Yr Interval Inservice Testing Program.Safe Shutdown
Reactor Vessel Water Level
High Radiation Area
Stroke time
Squib
Scram Discharge Volume
Excess Flow Check Valve
Cold shutdown justification
Exemption Request
Power Operated Valves
ML18038A42331 May 1988Rev 6 to Offsite Dose Calculation Manual. W/Two Oversize FiguresGrab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
ML17056A96523 February 1988Rev 6 to Odcm.Grab sample
ML20059F8755 February 1988Rev 4 to Odcm
ML20236G81631 July 1987Revised Preservice Insp Plan for Nuclear Piping Sys & Reactor Pressure Vessel
ML20236G81131 July 1987Revised Preservice Insp Plan for Nuclear Piping Sys & Component SupportsIncorporated by reference
ML18038A27221 May 1987Rev 3 to Offsite Dose Calculation Manual.Grab sample
Offsite Dose Calculation Manual
ML18038A24913 April 1987Revised Emergency Procedures,Consisting of Rev 5 to Emergency Action Procedure EAP-1, Activation & Direction of Emergency Plan, & Rev 9 to Emergency Plan Implementing Procedure EPP-20, Emergency Notification. W/870413 LtrSafe Shutdown
Grab sample
Earthquake
Siren
Overexposure
Overdose
ML20205S23131 March 1987Rev 0 to Pump & Valve Inservice Testing ProgramSafe Shutdown
Reactor Vessel Water Level
Stroke time
Hydrostatic
Squib
Scram Discharge Volume
Power Operated Valves
ML18038A42227 February 1987Rev 4 to Offsite Dose Calculation Manual. W/Two Oversize FiguresGrab sample
Offsite Dose Calculation Manual
Annual Radiological Environmental Operating Report
ML20211P45013 December 1986Rev 0 to Preoperational Test Procedure N2-POT-1-2, Msivs
ML17055D18219 August 1986Rev 0 to Administrative Procedure AP-3.7.1, Process Control Program.Process Control Program
ML18038A16731 May 1986Rev 1 to Offsite Dose Calculation Manual. W/One Oversize EnclGrab sample
Offsite Dose Calculation Manual
ML17055B53311 April 1986Rev 1 to Technical Dept Procedure TDP-5, Administration of Operational Engineering Assessment Items.
ML17055B5431 April 1986Rev 0 to Maint Instruction Procedure S-MI-GEN-002, Maint Instructions for Writing Procedures.Fire Barrier
Squib
ML17055B53020 March 1986Rev 0 to Site Administrative Procedure AP-6.1, Procedure for Mod & Addition.
ML17055B54414 March 1986Rev 1 to Nuclear Training Procedure NTP-11, Licensed Operator Retraining.Fuel cladding
ML17055B54214 March 1986Rev 1 to Nuclear Training Procedure NTP-10, Training of Licensed Operator Candidates.Fuel cladding
Power change
ML17055B51710 March 1986Rev 4 to Administrative Procedure AP-2.0, Production & Control of Procedures.Fire Protection Program
ML17055B54110 March 1986Rev 3 to Vol IV to SWEC Pp 94, Review of Changes & Effect on Environ/Mechanical/Seismic/Hydrodynamic Qualification of Equipment.
ML17055B5462 March 1986Rev 2 to Maint Instruction Procedure MI-4.0, Maint Instructions for Review & Implementation of Technical Requirements in Maint Procedures.
ML17055B5251 March 1986Draft Rev 4 to Administrative Procedure AP-4.0, Administration of Operations.
ML17055B53828 February 1986Rev 0 to Technical Dept Procedure TDP-8, Post-Maint Testing Criteria.Squib
ML20140D33428 February 1986Rev 2 to Offsite Dose Calculation Manual. W/Two Oversize MapsOffsite Dose Calculation Manual
Annual Radiological Environmental Operating Report