Summary of Public Meeting with Tennessee Valley Authority Regarding Watts Bar Nuclear Plant, Unit 1, License Amendment Request to Increase Tritium Production
ML16063A036
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 03/21/2016
From: Dion J
Plant Licensing Branch III
To:
Dion J
References
CAC MF6050
Download: ML16063A036 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 M:m:h 21 I 2016 LICENSEE: Tennessee Valley Authority FACILITY: Watts Bar Nuclear Plant, Unit 1

SUBJECT:

SUMMARY

OF FEBRUARY 5, 2016, PUBLIC MEETING WITH TENNESSEE VALLEY AUTHORITY REGARDING WATTS BAR NUCLEAR PLANT, UNIT 1, LICENSE AMENDMENT REQUEST TO INCREASE TRITIUM PRODUCTION (CAC NO. MF6050)

On February 5, 2016, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Tennessee Valley Authority (TVA) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss a license amendment request (LAR) to increase the maximum number of tritium-producing burnable absorber rods (TPBARs) permitted to be loaded into the reactor core at the Watts Bar Nuclear Plant (WBN), Unit 1. The meeting notice and agenda, dated January 7, 2016, are available in the Agencywide Documents Access and Management System (ADAMS) under Accession No. ML16021A349. Representatives from the Department of Energy also attended the meeting. A list of attendees is enclosed.

The March 31, 2015 LAR (ADAMS Accession No. ML15098A446), proposed to increase the number of TPBARs allowed to be loaded from 704 to 1,792. TVA supplemented its March 2015 submittal with letters dated May 27, 2015, and June 15, 2015 (ADAMS Accession Nos. ML15147A611 and ML15167A359, respectively). The NRC staff identified several outstanding technical issues in TVA's response dated December 22, 2015 (ADAMS Accession No. ML16054A661 ), to the staff's request for additional information issued on October 2, 2015 (ADAMS Accession No. ML15278A048). The outstanding issues related to demonstrating the adequacy of TVA's tritium control and monitoring to ensure onsite exposures will not result in occupational doses above Title 10 of the Code of Federal Regulations Part 20 limits, and demonstrating that effluent releases under the proposed design-basis assumptions will not exceed the dose limit to a member of the public. These issues were communicated to TVA by e-mail dated January 14, 2016 (ADAMS Accession No. ML16053A023).

TVA's presentation (ADAMS Accession No. ML16063A025) included a brief summary of the tritium production program background and previous amendments related to tritium production at WBN, Unit 1. The presentation also addressed operating experience, monitoring programs, the proposed tritium source term in the current amendment request, and liquid waste management.

TVA's presentation included information regarding its plans to supplement the submittal. TVA stated that the tritium control and monitoring program and the proposed design-basis source

term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.

TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.

Members of the public were not in attendance and no Public Meeting Feedback forms were received.

Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.

(',-C'v*---

/f)

~

anne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390

Enclosure:

List of Attendees cc w/enclosure: Distribution via Listserv

LIST OF ATTENDEES Licensee: Tennessee Valley Authority (TVA) Plant: Watts Bar Nuclear Plant, Unit 1

Subject:

License Amendment to Increase Date: February 5, 2016 Tritium Production Location: U.S. Nuclear Regulatory Commission Time: 9:00 a.m. -10:30 a.m.

(NRC) Headquarters, One White Flint North, Room 07-804 NAME TITLE ORGANIZATION NRC/Office of Nuclear Reactor Paul Krohn Acting Deputy Director Regulation (NRR)/Division of Operating Reactor Licensing (DORL)

NRC/NRR/Division of Risk Assessment Alex Klein Acting Deputy Director (ORA)

NRC/NRR/DORL/Plant Licensing Ben Beasley Branch Chief Branch 11-2 (LPL2-2)

NRC/NRR/DRA/Radiation Protection Undine Shoop Branch Chief and Consequence Branch (ARCS)

Robert Schaaf Project Manager NRC/NRR/DORL/LPL2-2 NRC/NRR/DORL/Plant Licensing Jeanne Dion Project Manager Branch 111-2 NRC/NRR/Division of License William Rautzen Health Physicist Renewal/Environmental Review and Project Management Branch Roger Pedersen Senior Health Physicist NRC/NRR/DRA/ARCB Enclosure

NAME TITLE ORGANIZATION Senior Manager, Fleet Erin Henderson Tennessee Valley Authority (TVA)

Regulatory Operations Senior Program Manager Carla Borrelli TVA Tritium Production General Manager, Reactor David Brown TVA Engineering and Fuels Safety Analysis Project Doug Pollock TVA Manager Clint Szabo* TVA Ed Schrull* TVA Bill Sitten* TVA Nanette Founds* Department of Energy (DOE)

Curtis Chambellan* DOE Thomas Hiltz* DOE James Smith* Westinghouse

  • participated via teleconference

term would be revised to address the staff's outstanding issues. In response to a question from the staff, TVA indicated that the proposed source term for the evaluation of accidents in the current submittal would not be changed.

TVA indicated it was in the process of evaluating its schedule for providing the supplement and would give the anticipated date for providing the supplement when this evaluation has been completed. Subsequent to the meeting, TVA informed the staff that it would provide the supplement no later than March 31, 2016.

Members of the public were not in attendance and no Public Meeting Feedback forms were received.

Please direct any inquiries to me at (301) 415-1349 or Jeanne.Dion@nrc.gov.

IRA!

Jeanne A. Dion, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-390

Enclosure:

List of Attendees cc w/enclosure: Distribution via Listserv DISTRIBUTION:

PUBLIC KBucholtz, NRR LPL2-2 R/F RPedersen, NRR RidsNrrPMWattsBar Resource Watts Bar Resident Inspector RidsNrrDlrRerb Resource RidsNrrLABClayton Resource RidsNrrDraArcb Resource TClark, OEDO RidsOpaMail Resource RidsNrrDorllpl2-2 Resource RidsNrrDorl Resource RidsRgn2MailCenter Resource WRautzen, NRR RidsACRS_MailCTR Resource TWertz, NRR ADAMS A ccess1on No.: ML16063A036 Pk;g: ML16063A025

  • ema1*1 concurrence OFFICE NRR/DORL/LPLI 11-2/PM NRR/DORL/LPLll-2/LA NRR/DRNARCB/BC NAME JDion (LRonewicz for) BClayton UShoop*

DATE 3/14/2016 3/07/2016 3/14/2016 OFFICE NRR/DLR/RERB/BC NRR/DORL/LPLll-2/BC N RR/DORL/LP LI 11-2/PM NAME JDanna* BBeasley JDion DATE 3/17/2016 3/17/2016 3/21/2016 OFFICIAL RECORD COPY