Summary of 920820 Meeting W/Util in Rockville,Md Re Util Presentation on Corporate Improvement Program.List of Attendees & Handouts Encl
ML14314A416
Person / Time
Site: Harris, Brunswick, Robinson  Duke Energy icon.png
Issue date: 09/14/1992
From: Lo R
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 9209240330
Download: ML14314A416 (15)


Text

September 14, 1992 Docket Nos. 50-261 50-325 and 50-324 and 50-400 LICENSEE:

CAROLINA POWER & LIGHT COMPANY FACILITY:

H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 BRUNSWICK STEAM ELECTRIC PLANT, UNITS 1 AND 2 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1

SUBJECT:

SUMMARY

OF AUGUST 20, 1992, MEETING REGARDING CORPORATE IMPROVEMENT PROGRAM This refers to the August 20, 1992, meeting conducted at Carolina Power &

Light Company's (CP&L's) request at One White Flint in Rockville, Maryland.

The purpose of the meeting was to allow CP&L to make a presentation on its Corporate Improvement Program (CIP). A summary of this program was submitted to the NRC on July 23, 1992, in response to NRC concerns about the performance of the Brunswick Steam Electric Plant, Units 1 and 2 (Brunswick). A list of attendees, and a copy of the CP&L handouts are enclosed (Enclosures 1 and 2).

The CP&L presentation followed closely the material in the handouts.

The CIP is still being developed and they expect to submit the comprehensive program to the NRC by the end of September 1992.

They agree with the NRC staff that the effectiveness of the program can only be discerned from the long-term plant performance.

CP&L will frequently update the NRC on the implementation and result of the program. This information is essential for Brunswick as the Nuclear Regulatory Commission has recently placed the plant on the NRC "Watch List."

ORIGINAL SIGNED BY:

Ronnie H. Lo, Senior Project Manager Project Directorate II-1 Division of Reactor Projects -

I/II Office of Nuclear Reactor Regulation

Enclosures:

1. Attendance List
2. CP&L Handouts cc w/

Enclosures:

See next page PUL 1111r,", _i)"JK.'

i OFFICE LA:PD F, E

PM: PD2-1 PM:PD2-1 NAME PAnXes RLo:tmi Wozafari NLe Date

///92

//0/92

/

/92 C

/6/

v/

OFFICE qD:PD21:DA NAME Adens Date

/

'/ 1 92 Document Name:

HAR82092.MTS 9209240330 920914 PDR ADOCK 05000261 P

PDR

ENCLOSURE I Ronnie Lo NRR DRPE Mel Shannon HARRIS RI H. Christensen NRC RH Brenda Mozafari NRC, NRR, PDII-1 David C. McCarthy CP&L, Manager Nuclear Licensing Section S. Varga NRR DRPE G. Lainas NRR DRPE E. G. Adensam NRR DRPE Peter Scott CP&L Consultant Walter W. Simpson CP&L Nuclear Business Operations R. B. Starkey, Jr.

CP&L Nuclear Services R. A. Watson CP&L Sr. V.P. Nuclear Generation Brian D. McFeaters CP&L NGG Group Analyst

Carolina Power & Light Company Corporate Improvement Program August 20, 1992

Corporate Improvement Program Discussion Outline

  • Content Definition and Process
  • Structure and Content Overview
  • CIP Implementation Process
  • CIP Administration and Resource Support
  • Highlights of Specific Projects
  • Next Steps
  • Closing Comments and Discussion I...

1

Corporate Improvement Program Content Definition and Process

  • Corporate Senior Management and Nuclear Generation Group Senior Management
  • Began with review of internal and external assessments and plans
  • Collected information on initiatives at other utilities
  • Developed overall framework

CorpoMte Improvement4Program Program Overview Pur ose Create the Foundation for Sustainable Levels of Good Performance Objectives 77s

  • Reduce backlog to manageable levels
  • Institutionalize a new philosophy of operations
  • Remove the barriers to success Four Key lnitiatves"-

Expected Results

  • Communication of Develop Higher and Expectations and More Specific Standards Expectations and Standards Increased Site and Corporate Management Involvement II.

Develop Plans to and Oversight Meet the Standards and Create Effective Improved Management Monitoring Methods Effectiveness

  • Improved Work Provde AditinalControl Processes Ill.

Provide Additional Resources to Improved Self Implement Assessment and Improvements Corrective Action Program IV.

Establish an Attitude 0 Improved Plant of Continuous Material Condition Improvement in Improved Personnel Performance Development and Imleen*n Iro edangeen

Corporate Improvement Program Program Overview

'Implementing Projects

1. Root Cause Verification
2.

Work Management Policies & Standards

3. Communication of Work Management Policies and Standards
4. Improvement Plans for Standards
5. First-year Review of Standards
6. Reporting of Standards Compliance
7.

NGG Policy and Procedures Manuals Restructur

8.

Role Change for Nuclear Services Department

9. Corrective Action Assessment
10. Integrated Schedule Program
11.

Business Planning Process Review

12. Supervisory Assessment Center
13. Supervisory Development Program
14.

Technical Training Program

15. Site Assistance Team Recommendations Resolution*
16. Modification Process Redesign
17. Maintenance Process Redesign
18. Work Control Methodology
19. Monthly Plant Material Condition and Housekeeping Report
20. Long-Term Back-log Reduction
21.

Organization Effectiveness Improvements

22. Nuclear Assessment Department Review and Evaluation Primary BNP Focus

Corporate improvement Program CIP Implementation Process Key Points

  • Top-down corporate initiative directed by Nuclear Senior Management
  • Targets of change are Brunswick and the other plants -- and corporate
  • CIP represents a major change for CP&L
  • Corporate support is solid

- Financial

- Organizational

  • CIP will be managed differently than previous improvement initiatives

- More upfront planning

- Implementation

- Oversight

  • Overall goal: one company with consistent levels of good performance at all plants

Corporate Improvement Program CIP Implementation Process (Cont'd)

Activities to Date

  • Draft action plans prepared
  • Reviews and comments provided by CP&L department managers and top executives
  • Funding methodology established
  • Final draft of CIP prepared Next Activities0
  • Full Nuclear Senior Management review scheduled for August 21
  • Final review with Corporate Senior Management
  • Begin intensive communications within the Nuclear Generation Group
  • Detailed CIP submittal to NRC

.6

Corporate Improvement Program CIP Administration and Resource Support Overall Responsibility

  • Senior Vice President of Nuclear Generation Group
  • Executive Assistant to SVP to be assigned responsibility for coordination, monitoring and communication Senior Management Oversight And Control
  • Executive Assistant to prepare status reports and provide to department managers and higher-level executives
  • Nuclear Assessment Department to conduct audits of implementation results every six months
  • Senior Nuclear Advisory Committee to review progress and project close-out 7

Corporate Improvement Program CIP Administration and Resource Support (Cont'd)

Project Close-Out

  • All non-audit type projects to have independent effectiveness follow-up audits
  • Audit reporting will be to SVP of Nuclear Generation Group and to higher-level executives
  • Nuclear Assessment Department to assess total CIP benefits relative to expected results Funding
  • All initiatives with significant resource requirements to be budgeted as separate projects
  • Projects to be funded through individual department business plans or through special, separate Nuclear Generation Group account administered by Senior Vice President

Corporate.m r................... r grm.

Highlights.of.Secific.Project...

.0 A ctio P lans.........,"..........

Root...

Cau e.Vriica.o

  1. 2 Work......

Management...

Policies.....

and.Stndard

  1. 13...

Supervisor Devlomet.rora

..,,".9

x x:':

--Od i' n1d,

Next Steps Submit comprehensive CIP document to NRC by end of September Meet with NRC to review comments on CIP 10

1.
..... I,

.: : X

..................... :.X :.............

Closing Comments and Discussion

" Root cause verification may cause CIP revision

" Corporate commitment in place

" Senior site management commitment in place

DISTRIBUTION:

Docket File)

NRC & Local PDRs PD II-1 Reading TMurl ey/FMi ragl i a JPartlow SVarga GLainas EAdensam RLo PAnderson OGC EJordan DWigginton BMozafari NLe HChristensen RII ACRS (10)

JWechselberger, EDO 17-G-21 JJohnson RH MShannon, RI Harris 180019