MONTHYEARIR 05000361/20240052024-10-0404 October 2024 NRC Inspection Report 05000361/2024005 and 05000362/2024005 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 07200041/20244012024-08-16016 August 2024 San Onofe Nuclear Generating Station, Security Baseline Inspection Report 07200041/2024401 IR 05000361/20240042024-08-0909 August 2024 NRC Inspection Report 05000361/2024004 and 05000362/2024004 ML24191A2472024-07-0202 July 2024 (Songs), Units 1, 2, and 3, and the Independent Spent Fuel Storage Installation - Revision to the ISFSI-Only Emergency Plan and Associated Changes to Emergency Plan Implementing Procedures ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24141A0802024-05-15015 May 2024 (Songs), Units 1, 2 and 3 and Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Operating Report IR 05000361/20240022024-04-0101 April 2024 – NRC Inspection Report 050-00361/2024-002 and 050-00362/2024-002 ML24094A0642024-03-27027 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Status Report 2023 ML24065A0152024-02-28028 February 2024 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation 2023 ML24044A0812024-02-14014 February 2024 LTR-24-0008: NRC Response to Paul Blanch Email Safety of Spent Nuclear Fuel at SONGS ISFSI IR 05000361/20240012024-02-13013 February 2024 NRC Inspection Report 050-00361/2024-001 and 050-00362/2024-001 (1) ML24037A0542024-01-30030 January 2024 (Songs), Units 2 and 3, Submittal of Annual Corporate Financial Reports ML24022A1492024-01-17017 January 2024 Independent Spent Fuel Storage Installation, Revision 4 to the Physical Security Plan ML24017A2432024-01-15015 January 2024 LTR-24-0008 Paul Blanch, E-mails Request for Formal Response to Requests for Meeting to Discuss Safety Issues with NRC Staff IR 05000361/20230062023-11-29029 November 2023 NRC Inspection Report 05000361/2023-006 and 05000362/2023-006 ML23333A0682023-11-22022 November 2023 (SONGS) Units 1, 2, 3 and Independent Spent Fuel Storage Installation - Notification of Change in Nuclear Officer IR 05000361/20230052023-10-11011 October 2023 NRC Inspection Report 05000361/2023005 and 05000362/2023005 ML23276A5942023-09-28028 September 2023 and Independent Spent Fuel Storage Installation - Supplement to Decommissioning Funding Status Reports ML23268A0922023-09-20020 September 2023 Generation Station, Units 1, 2 and 3, and the Independent Spent Fuel Storage Facility (ISFSI) - Re-Registration of Dry Fuel Storage Casks for Amended Certificate of Compliance No. 1040 IR 05000361/20230012023-09-13013 September 2023 NRC Inspection Report 05000361 2023-001 and 05000362 2023-004 ML23240A5372023-08-18018 August 2023 Confirmatory Survey Activities Summary and Results for the Unit 2 and 3 Intake Structures at the San Onofre Nuclear Generating Station San Clemente CA ML23129A1802023-06-14014 June 2023 Cover Letter to State of CA on Draft EA Regarding San Onofre ISFSI Updated DFPs IR 05000361/20230032023-05-31031 May 2023 NRC Inspection Report 05000361/2023003 and 05000362/2023003 IR 05000361/20230022023-05-23023 May 2023 NRC Inspection Report 05000361/2023-002 and 05000362/2023-002 ML23137A1032023-05-11011 May 2023 (Songs), Units 1, 2 and 3, and Independent Spent Fuel Storage Installation - 2022 Annual Radiological Environmental Operating Report ML23123A0932023-04-28028 April 2023 (Songs), Units 1, 2 and 3, Submittal of Annual Radioactive Effluent Release Report - 2022 ML23230A0882023-04-10010 April 2023 Independent Spent Fuel Storage Installation - Decommissioning Quality Assurance Plan ML23094A1272023-03-29029 March 2023 Independent Spent Fuel Storage Installation - 10 CFR 50.82(a)(8)(v and VII) and 10 CFR 72.30(c) Decommissioning Funding Status Report 2021 ML23094A1332023-03-29029 March 2023 Nuclear Property Insurance ML23062A1172023-02-28028 February 2023 Generation Station Units 1, 2 and 3, Annual Radioactive Effluent Release Report for Independent Spent Fuel Storage Installation - 2022 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23059A2812023-02-22022 February 2023 (Songs), Units 1, 2 and 3, 2022 Annual Turtle Incidental Take Report ML23046A3792023-02-22022 February 2023 NRC Inspection Report 050-00361/2023-001 and 050-00362/2023-001 ML23045A2022023-02-0909 February 2023 Submittal of Annual Corporate Financial Reports for San Onofre Nuclear Generating Station (SONGS) Units 2 and 3 for Fy Ending June 30, 2022 ML22287A1352023-01-0505 January 2023 Issuance of Exemption from Title 10 of the Code of Federal Regulations Part 72.106(B), Independent Spent Fuel Storage Installation Controlled Area Boundary (L-2021-LLE-0056) ML22348A0622023-01-0404 January 2023 NRC to SCE, Transmittal of the National Marine Fisheries Service'S December 12, 2022, Letter of Concurrence for Decommissioning of San Onofre Nuclear Generating Statiion, Units 2 and 3 IR 05000206/20220062022-12-15015 December 2022 NRC Inspection Report 05000206/2022006, 05000361/2022-006, and 05000362/2022-006 ML22347A2122022-12-12012 December 2022 NMFS to NRC, Endangered Species Act Section 7(a)(2) Concurrence Letter for Decommissioning of the San Onofre Nuclear Generating Station ML22340A6652022-12-0505 December 2022 Letter from John Fassell, Chief; Re., State of California Department of Public Health Review and Comments on SONGS Draft Environmental Assessment ML22333A8192022-11-21021 November 2022 Submittal of San Onofre Nuclear Generating Station, Units 2 and 3, Defueled Safety Analysis Report, Revised November 2022 IR 05000361/20220052022-11-17017 November 2022 NRC Inspection Report 05000361/2022-005 and 05000362/2022-005 ML22301A1462022-10-20020 October 2022 Report of Violations of the National Pollutant Discharge Elimination System Permit San Onofre Nuclear Generating Station (Songs), Units 2 and 3 ML22277A0162022-09-29029 September 2022 Independent Spent Fuel Storage Installation Response to Request for Additional Information Regarding Request for Exemption from 10 CFR 72.106(b) IR 05000361/20220042022-09-26026 September 2022 NRC Inspection Report 05000361/2022-004 and 05000362/2022-004 ML22238A0552022-08-29029 August 2022 U.S. Nuclear Regulatory Commission'S Analysis of Southern California Edison'S Decommissioning Funding Status Report for San Onofre Nuclear Generating Station, Units 1, 2, and 3 ML22234A1602022-07-31031 July 2022 Final Report Per 10 CFR Part 21, Degraded Snubber SF1154 Hydraulic Fluid Batch No. 18CLVS431 ML22207B8612022-07-26026 July 2022 NRC (Public) Inspection Report 05000361/2022003; 05000362/2022003 IR 05000361/20220032022-07-26026 July 2022 NRC Inspection Report (Public) 05000361-2022003 and 05000362-2022003 (002) IR 05000361/20220022022-05-12012 May 2022 NRC Inspection Report 05000361/2022-002 and 05000362/2022-002 2024-09-18
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 22, 2014 Mr. Peter T. Dietrich Senior Vice President and Chief Nuclear Officer Southern California Edison Company San Onofre Nuclear Generating Station P.O. Box 128 San Clemente, CA 92674-0128
SUBJECT:
SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3-NRC RESPONSE TO SOUTHERN CALIFORNIA EDISON'S FINAL RESPONSE TO THE MARCH 2012 REQUEST FOR INFORMATION LETTER
Dear Mr. Dietrich:
By letter dated March 12, 2012, 1 the U.S. Nuclear Regulatory Commission (NRC) issued a request for information per Title 10 to the Code of Federal Regulations (1 0 CFR), Subpart 50.54(f) (50.54(f) letter), to all nuclear power reactor licensees and construction permit holders in response to lessons-learned from Japan's March 2011, earthquake and subsequent tsunami.
Enclosures 1 through 4 to the 50.54(f) letter include information requests regarding Recommendations 2.1 and 2.3 for seismic and flooding hazard actions, and Enclosure 5 includes R!3commendation 9.3 for emergency preparedness, as part of the response to the Near- Term Task Force Recommendations for Enhancing Reactor Safety in the 21st Century report, issued July 12, 2011. 2 The 50.54(f) letter requests licensees to perform seismic and flooding walkdowns and hazard re-evaluations, and perform emergency preparedness communication and staffing evaluations for prolonged loss of power events.
By letter dated June 12, 201,3, 3 Southern California Edison.(SCE) submitted a letter certifying
- permanent cessation of power operations of San Onofre Nuclear Generating Station (SONGS),
Units 2 and 3, per 10 CFR Subpart 50.82(a)(1)(i). Subsequently, by letters dated June 28, 4 and July 22, 2013, 5 SCE submitted letters certifying that the fuel has been permanently removed from the Unit 3 and Unit 2 reactors, respectively, per 10 CFR Subpart 50.82(a)(1 )(ii). SCE acknowledged in the June and July letters that, once the certifications are docketed, the SONGS Units 2 and 3 licenses no longer authorize operation of the reactors, or placement or retention of fuel in the reactor vessels.
By letter dated September 30, 2013, 6 SCE stated that the SONGS units are no longer operating plants, but are permanently shut down and defueled reactors. Therefore, the licensee considers the requests of the 50.54(f) letter to no longer be applicable to SONGS, Units 2 and 3, and no lo11ger plans on proceeding with any further implementation of the requests in the 50.54(f) letter or any alternative approach for Recommendations 2.1, 2.3 and 9.3.
The 10 CFR 50.54(f) letter is available via the Agencywide Documents Access and Management System (ADAMS),
Accession No. ML12053A340.
The NTTF report is available under ADAMS Accession No. ML111861807.
The June 12, 2013 letter is available under ADAMS Accession No. ML131640201.
The June 28, 2013 letter is available under ADAMS Accession No. ML13183A391.
The July letter is available under ADAMS Accession No. ML13204A304.
The September letter is available under ADAMS Accession No. ML13276A020.
P. Dietrich The NRC staff verified that the SONGS, Units 2 and 3, certifications are docketed and that the licenses no longer authorize operation of the reactors or placement or retention of fuel in the reactor vessels. Further, the NRC staff has reviewed the licensee's responses to the information requests described in Enclosures 1 through 5 of the 50.54(f) letter and have determined that the requests are no longer necessary for SONGS, Units 2 and 3.
No further responses or actions associated with the 50.54(f) letter are necessary since the licensee is no longer authorized to load fuel .into the vessel and potential fuel-related accident scenarios are limited to the spent fuel pool. Unlike the reactor, the safety of fuel located in the spent fuel pool is assured for an extended period through maintenance of pool structural integrity, which preserves coolant inventory and maintains margin to prevent criticality. Small changes in the flooding hazard elevation would not threaten the structural integrity of a flooded pool. Further, previous evaluations of spent fuel pool structures have determined that seismic margins are very large. As seismic and flooding studies. continue for the remainder of the operating fleet, new information concerning the adequacy of design bases of spent fuel pools will be evaluated for applicability to decommissioned sites using existing NRC processes.
Based on the discussion above, the safety of the fuel stored in spent fuel pools would not be substantially affected by potential changes in the flooding or seismic hazard levels.
Furthermore, for beyond design basis external events challenging the safety of the spent fuel, recovery and mitigation actions could be completed over a long period of time due to the slow progression of any accident as a result of the very low decay heat levels present in the pool within a few months following 'permanent shutdown of the reactor. Thus, spent fuel pool beyond design basis accident scenarios at decommissioning reactor sites do not require the enhanced communication and.staffing that may be necessary for the reactor-centered events the 50.54(f) letter addresses.
Should you have any questions regarding this letter, please contact Mr. Nicholas DiFrancesco at 301-415-1115 or Nicholas.DiFrancesco@NRC.gov.
Sincerely, Michele G. Evans, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-361 and 50-362 cc: Listserv
ML13329A826 *via e-mail
- OFFICE DORL!LPL4-2/PM DORL/LPL4-2/LA JLD/PMB/PM JLD/PMB/BC OGC*
NAME CGratton (LRegner for) JBurkhardt (BCiayton for) LRegner MMitchell EHouseman DATE 01/16/2014 01'/16/2014 01/13/2014 12/04/2013 01/13/2014 OFFICE DORL!LPL4-2/BC NSIR/DPR/0* NRO/DSEA/0 DORL!D NAME DBroaddus Rlewis SFianders MEvans DATE 01/16/2014 12/18/2013 12/19/2013 01/22/2014