.,J\l EDISON

i. _*.*.**.~..-*. SOUTHERN GAUFORNIA Douglas R. Baud er Site Vice President & Station Manager San Onofre Nuclear Generating Station An ED/SON /N TER NA TJONA L Company 10 CFR 20 Appendix GilLE December 16, 2011 ATTN: U. S. Nuclear Regulatory Commission, Region IV 1600 East Lamar Boulevard Arlington , TX 76011-4511

Subject:

Docket Number 50-362 10 CFR 20 Appendix G Section III.E Report San Onofre Nuclear Generating Station, Unit 3

Reference:

Letter from R.J. St. Onge (SCE) to the Document Control Desk (NRC) dated May 20 , 2011 ;

Subject:

Docket Numbers 50-361, 50-362, Request for Exemption from 10 CFR 20 Appendix G Section III.E, San Onofre Nuclear Generating Station Units 2 and 3 (ML111430627)

Dear Sir or Madam :

Southern California Edison (SCE) is providing this report in accordance with the requirements in 10 CFR 20 Appendix G Section III.E. This regulation requires an investigation and report to the NRC whenever a shipper does not receive acknowledgement of receipt in the form of a signed NRC Form 540 of a low-level radioact ive waste shipment within 20 days after transfer.

The shipment addressed in this report involved scheduled ground transportation on a special conveyance of a recently replaced original steam generator lower assembly (OSGLA) from the San Onofre Nuclear Generating Station (SONGS) Unit 3 to the EnergySolutions disposal facility in Clive , Utah. On October 12, 2011 SCE transferred possession of the OSGLA to the carrier and the shipment departed the North Industrial Area (NIA) at SONGS and was moved to a nearby staging area located on Old Highway 101. Following mechanical issues associated with the conveyance, the shipment was moved from the staging area back to the NIA on November 06,2011 and possession was transferred back to SCE.

The shipment was accompanied by SCE project personnel and tracked electronically to and from the staging area on Old Highway 101. SCE has documentation of resuming possession of the shipment and that it was returned to the NIA but exceeded the 20 day notice receipt from the date of transfer set forth in 10 CFR 20 Appendix G Section III.E.

P.O. Box 128 San Clemente, CA 92672 (949) 368-9275 PAX 89275 Fax: (949) 368-9881 Doug.Bauder@sce.com

U. S. Nuclear Regulatory Commission December 16, 2011 Region IV Additional details on the shipment may be found in the above reference, SCE's Request for Exemption from 10 CFR 20 Appendix G Section III.E dated May 20,2011. The exemption request was subsequently withdrawn.

There are no regulatory commitments made in this letter.

Sincerely, f (--;v ce: ~ [). £ .:>>:

11..<>.-.-.0.-)'" f* (Yl C(C7"<>J cc: E. E. Collins, NRC Regional Administrator, Region IV R. Hall, NRR Project Manager, San Onofre Units 2 and 3 G. G. Warnick, NRC Senior Resident Inspector, San Onofre Units 2 and 3 Document Control Desk