ML111822085

From kanterella
Jump to navigation Jump to search
IR 05000298-11-008; 04/11/11 - 05/03/11; Cooper Nuclear Station; Special Inspection to Evaluate Unexpected Doses to Workers Performing Under-Vessel Maintenance Activities
ML111822085
Person / Time
Site: Cooper Entergy icon.png
Issue date: 07/01/2011
From: Vincent Gaddy
NRC/RGN-IV/DRP/RPB-C
To: O'Grady B
Nebraska Public Power District (NPPD)
References
IR-11-008
Download: ML111822085 (40)


See also: IR 05000298/2011008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

July 1, 2011

Brian J. OGrady, Vice President-Nuclear

and Chief Nuclear Officer

Nebraska Public Power District

72676 648A Avenue

Brownville, NE 68321

Subject: COOPER NUCLEAR STATION - NRC SPECIAL INSPECTION REPORT

05000298/2011008

Dear Mr. OGrady:

On May 3, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a special

inspection at your Cooper Nuclear Station to evaluate the facts and circumstances surrounding

the exposure of three workers to higher than expected dose rates while removing an

intermediate range monitor shuttle tube from beneath the reactor pressure vessel. The

enclosed report documents the inspection findings that were discussed on June 9, 2011, with

Mr. A. Zaremba, Director, Nuclear Safety Assurance, and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

plant personnel.

Based upon exceeding the deterministic criteria for radiation safety specified in NRC

Management Directive 8.3, "NRC Incident Investigation Program, the NRC initiated a special

inspection in accordance with Inspection Procedure 93812, "Special Inspection. The basis for

initiating the special inspection was the work activity led to unplanned changes in restricted area

dose rates in excess of 20 rem per hour in an area where personnel were present. The focus of

the inspection was the event that took place on April 3, 2011, when three workers removed an

intermediate range monitor shuttle tube from beneath the reactor pressure vessel and dose

rates in the area went from 120 millirem per hour to 39 rem per hour at 30 centimeters from the

tip of the shuttle tube, which was the source of the excess dose. The focus areas for review are

detailed in the Special Inspection Charter (Attachment 2). On April 5, 2011, the NRC

determined that the inspection would be conducted and the onsite inspection started on

April 11, 2011.

This report documents six NRC-identified findings of very low safety significance (Green). Five

of these findings were determined to involve violations of NRC requirements. However,

because of their very low safety significance and because they are entered into your corrective

action program, the NRC is treating these findings as noncited violations, consistent with

Section 2.3.2 of the NRC Enforcement Policy. If you contest the violations or the significance of

the noncited violations, you should provide a response within 30 days of the date of this

inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission,

Nebraska Public Power District -2-

ATTN: Document Control Desk, Washington, D.C. 20555-0001, with copies to the Regional

Administrator, U.S. Nuclear Regulatory Commission, Region IV, 612 E. Lamar Blvd, Suite 400,

Arlington, Texas, 76011-4125; the Director, Office of Enforcement, U.S. Nuclear Regulatory

Commission, Washington, D.C. 20555-0001; and the NRC Resident Inspector at the facility. In

addition, if you disagree with the cross-cutting aspect assigned to any finding in this report, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector

at the facility. The information you provide will be considered in accordance with Inspection

Manual Chapter 0305.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response, if you choose to provide one, will be made available

electronically for public inspection in the NRC Public Document Room or from the NRC's

document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html. To the extent possible, your response should not include any personal privacy

or proprietary, information so that it can be made available to the Public without redaction.

Sincerely,

/RA/

Vincent G. Gaddy, Chief

Project Branch C

Division of Reactor Projects

Docket: 50-298

License: DPR-46

Enclosure: NRC Inspection Report 05000298/2011008

w/Attachments:

Attachment 1: Supplemental Information

Attachment 2: Special Inspection Charter

Attachment 3: Pictures and Diagrams

cc w/Enclosures:

Distribution via Listserv

Nebraska Public Power District -3-

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

Acting DRP Deputy Director (Jeff.Clark@nrc.gov)

(Troy.Pruett@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Tom.Blount@nrc.gov)

Senior Resident Inspector (Jeffrey.Josey@nrc.gov)

Resident Inspector (Michael.Chambers@nrc.gov)

Branch Chief, DRP/C (Vincent.Gaddy@nrc.gov)

Senior Project Engineer, DRP/C (Bob.Hagar@nrc.gov)

Project Engineer, DRP/C (Rayomand.Kumana@nrc.gov)

CNS Administrative Assistant (Amy.Elam@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Lynnea.Wilkins@nrc.gov)

Acting Branch Chief, DRS/TSB (Dale.Powers@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

OEDO RIV Coordinator (Stephaine.Bush-Goddard@nrc.gov)

R:\_REACTORS\_CNS\2011\CNS 2011008-RP-DHO.docx

ADAMS: No Yes SUNSI Review Complete Reviewer Initials:

Publicly Available Non-Sensitive

Non-Publicly Available Sensitive

RI:PBA RI/PBE SPE/PBC DRP/PBC

BKTharakan DOverland BHagar VGaddy

E-mail/Vgaddy for E-mail/Vgaddy for /RA/ /RA/

6/28/11 6/28/11 6/14/11 6/29/11

C:DRS/PS2 C:DRS/PS2 DD:DRP

GWerner LRicketson KMKennedy

E-mail/Vgaddy for /RA/

6/29/11 6/15/11

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket: 05000298

License: DPR-46

Report: 05000298/2011008

Licensee: Nebraska Public Power District

Facility: Cooper Nuclear Station

Location: 72676 648A Avenue

Brownville, NE 68321

Dates: April 11 through May 3, 2011

Inspectors: D. Overland, Resident Inspector, Waterford 3 Steam Electric Station

B. Tharakan, CHP, Resident Inspector, South Texas Project

Approved By: Vince Gaddy, Chief

Project Branch C

Division of Reactor Projects

-1- Enclosure

TABLE OF CONTENTS

SUMMARY OF FINDINGS ..........................................................................................................3

REPORT DETAILS .....................................................................................................................7

4OA3 Event Follow-Up................................................................................................................7

1.0 Special Inspection Scope .....................................................................................7

2.0 Event Description and Chronology

2.1 Event Summary ........................................................................................7

2.2 Sequence of Events .................................................................................8

2.3 Immediate Actions Taken ........................................................................10

3.0 Work Planning and Execution

3.1 Work Order Planning ..............................................................................10

3.2 Job Preparation ......................................................................................15

3.3 Work Execution ......................................................................................17

4.0 Radiation Protection Performance

4.1 ALARA Planning .....................................................................................19

4.2 Radiation Work Permit Adequacy ...........................................................19

4.3 ALARA Briefing.......................................................................................20

4.4 Job Coverage .........................................................................................22

4.5 Dose and Dose Rate Assessment ..........................................................27

5.0 Review of Previous Activity Performance ...........................................................28

6.0 Review of Causal Determination and Corrective Actions .................................... 28

4OA6 Meetings........................................................................................................................29

ATTACHMENTS

1 Supplemental Information .............................................................................. A1-1

Key Points of Contact .................................................................................... A1-1

List of Items Opened, Closed, and Discussed ................................................ A1-1

Documents Reviewed .................................................................................... A1-2

2 Special Inspection Charter ............................................................................. A2-1

3 Pictures and Diagrams ................................................................................... A3-1

-2- Enclosure

SUMMARY OF FINDINGS

IR 05000298/2011008; 04/11/11 - 05/03/11; Cooper Nuclear Station; Special inspection to

evaluate unexpected doses to workers performing under-vessel maintenance activities.

The report covered one week of onsite inspection and in-office review through May 3, 2011.

Two resident inspectors performed the inspection. Five Green noncited violations and one

Green finding were identified. The significance of most findings is indicated by their color

(Green, White, Yellow, or Red) using Inspection Manual Chapter 0609, "Significance

Determination Process." The cross-cutting aspect is determined using Inspection Manual

Chapter 0310, Components within the Cross Cutting Areas. Findings for which the

significance determination process does not apply may be Green or be assigned a severity level

after NRC management review. The NRC's program for overseeing the safe operation of

commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process,"

Revision 4, dated December 2006.

A. NRC-Identified and Self Revealing Findings

Cornerstone: Occupational Radiation Safety

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.4.1, for a failure to implement procedures described in Regulatory

Guide 1.33, Appendix A. Specifically, the licensee failed to implement

procedures that provide guidance on creating clear, accurate work instructions.

As a result, the work instructions were not able to be completed as written and

needed parts were not available. This directly contributed to three

instrumentation and control technicians receiving an unexpected radiation dose.

A site stand-down was held to discuss the lessons learned and the event was

entered into the licensees corrective action program as Condition

Report CR-CNS-2011-4431.

This deficiency was reasonable for the licensee to foresee and prevent

occurrence. The finding was more than minor because it is associated with the

human performance attribute of the Occupational Radiation Safety Cornerstone

and affected the cornerstone objective to ensure the adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation. The inspectors evaluated this

finding using Inspection Manual Chapter 0609, Appendix C, Occupational

Radiation Safety Significance Determination Process. The inspectors

determined that the finding is of very low safety significance (Green) because it

was not associated with ALARA planning or work controls, there was no

overexposure, there was no substantial potential for an overexposure, and the

licensees ability to assess dose was not compromised. The finding has a cross-

cutting aspect in the work practices component of the human performance area

because the licensee did not effectively communicate expectations regarding

procedural compliance and that personnel follow procedures. Specifically, the

licensee displayed a cultural behavior that unacceptable behaviors, such as

failing to follow procedures, are acceptable as long as the outcome is desirable

[H.4.(b)](Section 3.1).

-3- Enclosure

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.4.1, for failure to implement procedures described in Regulatory

Guide 1.33, Appendix A. Specifically, the licensee failed to implement

procedures that provide guidance on recognizing risk associated with a

maintenance activity and properly accounting for that risk. This directly

contributed to three instrumentation and control technicians receiving an

unexpected radiation dose. A site stand-down was held to discuss the lessons

learned and the event was entered into the licensees corrective action program

as Condition Report CR-CNS-2011-4435.

This deficiency was reasonable for the licensee to foresee and prevent

occurrence. The finding was more than minor because it is associated with the

human performance attribute of the Occupational Radiation Safety Cornerstone

and affected the cornerstone objective to ensure adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation. The inspectors determined that

the finding is of very low safety significance (Green) because it was not

associated with ALARA planning or work controls, there was no overexposure,

there was no substantial potential for an overexposure, and the licensees ability

to assess dose was not compromised. The finding has a cross-cutting aspect in

the work control component of the human performance area because the

licensee did not plan work activities by incorporating risk insights. Specifically,

the licensee developed a work package that failed to recognize the risk

associated with the activity H.3(a)(Section 3.1).

  • Green. The inspectors identified a finding for a failure to implement human

performance procedures. Specifically, the licensee failed to implement

procedures that provided guidance on conducting pre-job briefs, preparing work

in the field, and informing technicians on what to do when the workers

encountered a problem. This contributed to three instrumentation and control

technicians receiving an unexpected radiation dose. A site stand-down was held

to discuss the lessons learned from the event. This was entered into the

licensees corrective action program as Condition Report CR-CNS-2011-4258.

The finding was more than minor because it is associated with the human

performance attribute of the Occupational Radiation Safety Cornerstone and

affected the cornerstone objective to ensure the adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation. The inspectors evaluated this

finding using Inspection Manual Chapter 0609, Appendix C, Occupational

Radiation Safety Significance Determination Process. The inspectors

determined that the finding is of very low safety significance (Green) because it

was not associated with ALARA planning or work controls, there was no

overexposure, there was no substantial potential for an overexposure, and the

licensees ability to assess dose was not compromised. The inspectors

determined that the apparent cause of this finding was the licensees failure to

promote the use of human performance tools to ensure job tasks were properly

completed. Therefore, this finding has a cross-cutting aspect in the work

practices component of the human performance area because the licensee did

not adequately communicate human error prevention techniques such that work

activities are completed safely H.4(a)(Section 3.2).

-4- Enclosure

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.4.1, for a failure to comply with procedures described in

Regulatory Guide 1.33, Appendix A. Specifically, the licensee failed to

implement procedures and a work order instruction that required the work order

to be returned to work planners and revised if the original work scope is changed

or a problem is encountered. This directly contributed to three instrumentation

and control technicians receiving an unexpected radiation dose. A site stand-

down was held to discuss the lessons learned from the event. This was entered

into the licensees corrective action program as Condition

Report CR-CNS-2011-4428.

The finding was more than minor because it is associated with the human

performance attribute of the Occupational Radiation Safety Cornerstone and

affected the cornerstone objective to ensure the adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation. The inspectors evaluated this

finding using Inspection Manual Chapter 0609, Appendix C, Occupational

Radiation Safety Significance Determination Process. The inspectors

determined that the finding is of very low safety significance (Green) because it

was not associated with ALARA planning or work controls, there was no

overexposure, there was no substantial potential for an overexposure, and the

licensees ability to assess dose was not compromised. The finding has a cross-

cutting aspect in the decision making component of the human performance area

because the licensee did not use conservative assumptions in decision-making.

Specifically, the licensee did not validate the assumptions made when

considering the change in work scope H.1(b)(Section 3.3).

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.7.2, for the failure to adequately brief radiation workers entering a

locked high radiation area. Specifically, the radiation protection pre-job briefing

failed to make workers knowledgeable of the radiation dose rates that may be

encountered when pulling the intermediate range monitor shuttle tube from under

the reactor pressure vessel and failed to identify any change in work scope or

breach of the nuclear instrument system. This resulted in the workers being

exposed to higher than expected dose rates. The workers immediately

evacuated the area and contacted radiation protection. The licensee held a site

stand-down to discuss lessons learned and this finding was entered into the

licensees corrective action as Condition Report CR-CNS-2011-04441.

The finding was more than minor because it is associated with the human

performance attribute of the Occupational Radiation Safety Cornerstone and

affected the cornerstone objective to ensure the adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation because workers were exposed

to higher dose rates. The inspectors evaluated the significance of the finding

using NRC Inspection Manual 0609, Appendix C, Occupational Radiation Safety

Significance Determination Process, dated August 19, 2008. The inspectors

determined that the finding is of very low safety significance because it was not

associated with ALARA planning or work controls, there was no overexposure,

there was no substantial potential for an overexposure, and the licensees ability

-5- Enclosure

to assess dose was not compromised. In addition, the finding had a cross-

cutting aspect in the work control component of the human performance area

because the licensee did not appropriately communicate, coordinate, and

cooperate with each other during the radiation protection pre-job briefing and

failed to keep personnel apprised of plant conditions that may affect work

activities to ensure radiological safety was maintained H.3(b)(Section 4.3).

  • Green. The inspectors identified a noncited violation of Technical

Specification 5.4.1(a), for the failure to follow Radiation Procedure 9.EN-RP-141,

Job Coverage, Revision 8. Specifically, the radiation protection personnel were

monitoring workers pulling the intermediate range monitor shuttle tube from

under the reactor pressure vessel and failed to implement radiation protection job

coverage requirements that resulted in the workers being exposed to dose rates

as high as 39 rem per hour at 30 centimeters from the tip of the shuttle tube. The

licensee immediately evacuated and restricted access to the area. This finding

was documented in the licensees corrective action program as Condition

Reports CR-CNS-2011-04442, CR-CNS-2011-04255, CR-CNS-2011-04595,

CR-CNS-2011-05443, CR-CNS-2011-05444, CR-CNS-2011-05446,

CR-CNS-2011-05447, and CR-CNS-2011-05448.

The finding was more than minor because it is associated with the human

performance attribute of the Occupational Radiation Safety Cornerstone and

affected the cornerstone objective to ensure the adequate protection of the

worker health and safety from exposure to radiation from radioactive material

during routine civilian nuclear reactor operation because workers were exposed

to higher dose rates. The inspectors evaluated the significance of the finding

using NRC Inspection Manual 0609, Appendix C, Occupational Radiation Safety

Significance Determination Process, dated August 19, 2008. The inspectors

determined that the finding is of very low safety significance because it was not

associated with ALARA planning or work controls, there was no overexposure,

there was no substantial potential for an overexposure, and the licensees ability

to assess dose was not compromised. In addition, the finding has a cross-cutting

aspect in the work practices component of the human performance area because

the licensee failed to use human error prevention techniques such as self-

checking and peer-checking to ensure that job coverage procedures were

followed H.4(a)(Section 4.4).

B. Licensee-Identified Violations

None.

-6- Enclosure

REPORT DETAILS

4OA3 EVENT FOLLOW-UP

1.0 Special Inspection Scope

On April 2, 2011, while licensee workers were removing an intermediate range monitor

shuttle tube assembly from the reactor pressure vessel, they deviated from the written

work instructions. Workers under the vessel received dose rate alarms and exited the

area. The workers dosimeters measured dose rates of 1.35 Rem per hour, 14.3 rem

per hour, and 763 millirem per hour.

The inspection charter (refer to Attachment 2) required the team to: (1) develop a

timeline for the sequence of events, including actions taken prior to and post event, as

well as the associated decision-making process, (2) assess the licensees procedural

compliance during work order preparation and execution, including ALARA and

radiological work permit considerations, (3) characterize the area dose rates and dose

received by personnel, (4) review causal determination and short term corrective action

adequacy, and (5) review previous activity performance and compare to current activity

performance.

The team performed their reviews in accordance with NRC Inspection Procedure 93812,

"Special Inspection Procedure." The team used the requirements in 10 CFR

Parts 19, 20 and 50, the licensees technical specifications, and the licensees

procedures required by technical specifications as criteria for determining compliance.

The team reviewed licensee procedures, corrective action documents, as well as work

orders and radiological work permits for the maintenance activity. The team interviewed

station personnel regarding the events, compared this event to previously performed

evolutions, and assessed the adequacy of the licensees corrective actions. A list of

specific documents reviewed is provided in Attachment 1. The charter for the special

inspection is provided as Attachment 2.

2.0 Event Description and Chronology

2.1 Event Summary

On April 2, 2011, instrumentation and control technicians prepared to remove the source

range monitor B and the intermediate range monitor C shuttle and dry tube assemblies

from the top of the reactor vessel in accordance with Work Orders 4741006

and 4741002. Each intermediate range monitor and source range monitor detector is

contained inside a shuttle tube. This shuttle tube is fixed to a drive tube that a drive

mechanism moves up and down inside a dry tube. The entire tube assembly, along with

the detector was to be replaced. Arrangement of these components is depicted in

Attachment 3.

During the pre-job brief, the workers discussed the activity to be performed and the tools

needed. Nose cones were identified as a needed component, but the type of nose

cones (male or female threads) and their location was unknown. In particular, workers

discussed whether the shuttle tube could be removed from the bottom of the core, rather

than the top (as procedurally directed), however no resolution was achieved.

-7- Enclosure

Prior to beginning work, two nose cones were located, one male-threaded and one

female-threaded. The workers proceeded to conduct the work activity. Source range

monitor B drive tube was removed and the male-threaded nose cone was installed on

the bottom of the dry tube, sealing the shuttle tube inside. Intermediate range monitor C

drive tube was removed, but no other male-threaded nose cones were available to install

on the lower end of the dry tube prior to removal.

When the workers reported this issue to the outage control center, the outage control

center staff gave permission to the workers to remove the shuttle tube from the bottom

of the reactor vessel, rather than sealing it inside the dry tube for removal above the

reactor vessel (as originally planned). The licensee did not modify either the associated

work order or the corresponding radiation work permit to reflect this change.

As the workers removed the shuttle tube from the bottom of the vessel, the three

workers under the vessel received dose rate alarms. The workers then set the tip of the

tube on the floor at the 888 foot elevation and exited the area. The workers dosimeters

measured dose rates of 1.35 rem per hour, 14.3 rem per hour, and 0.763 rem per hour.

Surveys taken of the shuttle tube, during recovery operations, found that the tip of the

shuttle tube measured 3,226 rem per hour on contact and 39 rem per hour at

30 centimeters, and that the general area dose rate was 4.6 rem per hour at waist level,

increasing to 8.6 rem per hour at waist level near the tube.

2.2 Sequence of Events

December 2009 - The licensee identified the need to replace intermediate range

monitor C. Work Order 4741002 was generated to replace intermediate range monitor C

components. The work order contained, in part, the following actions:

  • Remove dry tube, shuttle/drive tube, and detector from top of reactor
  • Install new dry tube and shuttle/drive tube from top of reactor
  • Install new detector

January 2010 - A planner was assigned for Work Order 4741002.

May 2010 - Planning for Work Order 4741002 begins.

November 2010 - The ALARA review of Work Order 4741002 was deemed satisfactory.

December 2010 - Instrumentation and control supervisory walkdown of Work

Order 4741002 was completed (not the same supervisor that performed the job).

February 2011 - The instrumentation and control lead technician completed shop

walkdown of Work Order 4741002. This completed planning of the work order. The

same technician later performed the job.

April 2, 2011 - (times approximated)

1730 - During maintenance supervisor turnover, the off-going supervisor

identified that the day-shift crew had pulled the detectors, and was ready to

remove the drive mechanisms and tube assemblies.

-8- Enclosure

1830 - The outage control center brief identifies that the source range monitor

and intermediate range monitor work was a priority. The backup plan to

remove the shuttle tube from under the vessel is not discussed at the brief.

2000 - Outage control center called instrumentation and control superintendent

to get status of locating nose cones for source range monitor and intermediate

range monitor work. Only one nose cone located. Outage control center

inquired about an alternate plan. Back-up plan was to pull the shuttle tube

manually from below. Instrumentation and control told outage control center that

the tube was made of titanium (easily bendable and nonirradiated). Outage

control center requested instrumentation and control to brief radiation protection

and ensure they understood and approved the back-up plan.

2030 - Inspection of top guide was complete, so refuel floor staff would be ready

for dry tube removal at midnight.

2130 - Instrumentation and control superintendent informed that one nose cone

had been located. Refuel floor manager looks for another nose cone.

2200 - The lead instrumentation and control technician conducted a shop brief

for upcoming under-vessel work on the source range and intermediate range

monitors. Attendees were the three technicians and instrumentation and control

supervisor. The feasibility of pulling the shuttle tube from below the vessel is

discussed, but no resolution was achieved.

2206 - Second nose cone located. However, the threads on this nose cone did

not match the threads on the other nose cone, so technicians head to the drywell

with one male-threaded and one female-threaded nose cone. They were not

sure which would be needed.

2230 - The radiation protection ALARA supervisor completed a brief for the

upcoming under-vessel work. Besides the supervisor providing the brief,

attendees were the three technicians who would work under-vessel and another

technician that would remain located outside the drywell to monitor radiological

conditions. This brief did not discuss the backup plan for shuttle tube removal

from the bottom of the vessel.

2300 - Source range monitor B work completed. Work on intermediate range

monitor C begins. Shortly afterward, technicians call instrumentation and control

superintendent to inform that intermediate range monitor C required male

threaded nose cone (like the ones used on source range monitor B), and

requested guidance on removal of shuttle tube without the proper nose cone.

Instrumentation and control superintendent then calls outage control center

maintenance outage manager to request guidance on removing the shuttle tube

from under-vessel. Outage control center maintenance outage manager directed

instrumentation and control superintendent to proceed with removal from under-

vessel. Instrumentation and control superintendent relayed this direction to the

under-vessel technicians.

2400 - Instrumentation and control technicians call their superintendent again to

confirm removal of the shuttle tube from under-vessel. The technicians express

concern that removing the shuttle tube from under the vessel would require

-9- Enclosure

bending the tube and would therefore be irreversible. The instrumentation and

control superintendant requested and received confirmation from outage control

center maintenance outage manager and then related that confirmation to the

under-vessel technicians. Instrumentation and control technicians begin

removing shuttle tube from under-vessel.

April 3, 2011 - (times approximated)

0000 - Outage control center maintenance outage manager informed rest of

outage control center that shuttle tube would be pulled from below vessel. He

stated that the tube was assumed to be titanium, and therefore, would not

activate. However, this assumption was not verified and it turned out that the

shuttle tube was actually stainless steel. Outage control center radiation

protection representative challenged the assumption that titanium would not

activate. During the discussion, the three technicians working under the vessel

received dose rate alarms, immediately evacuated the under-vessel area and

told radiation protection personnel in the area that dose rates had significantly

increased.

0047 - The licensee entered their emergency procedure for elevated radiological

conditions inside the primary containment under-vessel area and drywell access

was restricted.

2.3 Immediate Actions Taken

Upon receiving the electronic dosimeter alarms, the workers immediately evacuated the

drywell. The licensee immediately evacuated all personnel from the drywell, restricted

access to the drywell, and entered Emergency Procedure 5.1RAD, Building Radiation

Trouble, Revision 15, due to unexpected elevated dose rates. The licensee

implemented radiological emergency procedures which identified the source as the

intermediate range monitor shuttle tube that was removed from the reactor pressure

vessel by the workers. The licensee implemented a recovery plan to isolate the source

of radiation and secure it in a shielded lead container. The recovery plan was executed

by three radiation protection technicians who were knowledgeable of the radiological

conditions. The plan included identifying the highest dose rates in the area, which was

the tip of the shuttle tube, and quickly cutting the stainless steel shuttle tube with metal

cutters and securing the approximately one foot piece of the shuttle tube. The remaining

tube was also cut up into approximately one foot pieces and secured in the shielded

container. The shielded container was then placed safely in the spent fuel pool.

3.0 Work Planning and Execution

3.1 Work Order Planning

a. Scope

The inspectors assessed the licensees performance while planning and preparing the

work package to replace source range monitor B and intermediate range monitor C. The

inspectors conducted interviews to assess the knowledge level and qualifications of

planners. The inspectors examined procedural guidance for work package creation to

determine adequacy and completeness. The inspectors also evaluated the licensees

ability to appropriately characterize and compensate for the risk associated with the

- 10 - Enclosure

maintenance activity. Interactions with other working groups, such as operations and

radiation protection, were similarly reviewed. The inspectors also evaluated the

licensees review process to ensure that work packages are complete and accurate.

b. Findings

.1 Introduction. The inspectors identified a Green noncited violation of Technical

Specification 5.4.1, for a failure to implement procedures described in Regulatory

Guide 1.33, Appendix A. Specifically, the licensee failed to implement procedures that

provide guidance on creating and reviewing clear, accurate work instructions. As a

result, the work instructions could not have been completed as written.

Description. On April 3, 2011, three instrumentation and control technicians were

performing Work Order 4741002, to remove intermediate range monitor C from the

underside of the reactor vessel and prepare the dry tube assembly for later removal from

above the reactor vessel. Work Order 4741002, Step 4, directed the technicians to

remove the drive tube per Procedure 14.2.9, SRM/IRM Detector and Drive Tube

Removal, Installation, Testing, and SRM/IRM Troubleshooting, Revision 26. Step 5.8 of

Procedure 14.2.9 directed the technicians to screw a nose cone onto the bottom of the

dry tube, enclosing the shuttle tube within the dry tube. Work Order 4741002, Step 5,

then directed the technicians to remove shuttle tube. However, if Procedure 14.2.9

had been correctly followed, Step 5 of the work order could not have been performed

because the shuttle tube would have been contained within the dry tube. Additionally,

no procedural reference is given for shuttle tube removal. When the inspectors asked

the work planner to clarify the intent of the unclear work instructions, he was unable to

provide any clarification.

Procedure 0.40.4, Planning, Revision 16, Attachment 1, included a checklist that was

to be used to ensure that work instructions were clear and concise. The inspectors

attempted to review this checklist since it was used to plan the work package. However

the checklist had been discarded. Use of the Attachment 1 checklist failed to identify

instructions that were not only unclear to the workers, but also to the work planner.

Additionally, Procedure 0.40.4, Step 5.2.10, required the work planner to ensure that all

specialized tools required to perform the work are identified and available. The nose

cone was not listed as a required part for work order execution and was not readily

available. If the nose cone had been made available (as required by procedure), the

technicians may not have attempted to execute an unclear instruction. This is evidenced

by the technicians performance of Work Order 4741006, removal of source range

monitor B, which contained the same unclear instructions. However, during this work,

the technicians had a male-threaded nose cone, so no attempt was made to remove the

shuttle tube from the bottom.

Another potential barrier to prevent the unclear work order instructions from reaching the

field was provided in Procedure 0.40, Work Control Program, Section 6.1, which

directed an instrumentation and control shop walkdown of the work instructions in

accordance with Procedure 0.40.4, Attachment 7. This attachment contained another

checklist for verifying work instruction. Inspectors attempted to review this checklist to

assess its performance; however this checklist was also discarded. The inspectors

concluded that despite the licensees assurance that the checklist was correctly utilized,

use of the checklist during the shop walkdown failed to identify the unclear work

instructions and lack of necessary parts.

- 11 - Enclosure

Although each individual requirement, if correctly performed, may or may not have

singularly prevented the confusing and incomplete work package from reaching final

approval, together they provide defense-in-depth; a set of guidelines that are intended to

provide multiple opportunities to detect and correct poor work instructions prior to field

execution. The failure of all three of these steps allowed poor work instructions to be

approved.

These unclear work instructions and lack of a needed part contributed to the decision to

remove shuttle tube from the bottom, despite lack of adequate procedural guidance.

As a result, three instrumentation and control technicians received an unexpected

radiation dose.

In interviews with station personnel, the inspectors encountered indications of a

widespread attitude among workers that failures to follow procedures were acceptable if

they achieved the desired outcomes. In those interviews, the inspectors found no

evidence that the licensee had effectively communicated their expectations regarding

procedural compliance. Also, the licensees root cause evaluation, documented as

Condition Report CR-CNS-2011-03763, determined that one root cause of this finding

was a work culture, supported by institutional reinforcement, that unacceptable

behaviors are acceptable as long as the outcome is good.

Analysis. The performance deficiency is that the licensee did not follow Procedure 0.40,

Work Control Program, and Procedure 0.40.4, Planning, when preparing Work Order 4741002. As a result, the work order could not be performed as written. This

deficiency was reasonable for the licensee to foresee and prevent occurrence. The

finding is more than minor because it is associated with the human performance attribute

of the Occupational Radiation Safety Cornerstone and affected the cornerstone objective

to ensure the adequate protection of the worker health and safety from exposure to

radiation from radioactive material during routine civilian nuclear reactor operation, in

that the finding resulted in three technicians receiving an unexpected radiation dose.

The inspectors evaluated the significance of the finding using NRC Inspection

Manual 0609, Appendix C, Occupational Radiation Safety Significance Determination

Process, dated August 19, 2008. The inspectors determined that the finding is of very

low safety significance (Green) because it is not a finding related to ALARA planning or

work controls, it did not result in an overexposure, there was no substantial potential for

overexposure, and the licensees ability to assess dose was not compromised. The

inspectors determined that the apparent cause of this finding was the licensees failure

to correct the attitude among workers that failures to follow procedures were acceptable

if they achieved the desired outcomes. Therefore, the finding has a cross-cutting aspect

in the work practices component of the human performance area because the licensee

did not effectively communicate expectations regarding procedural compliance [H.4.(b)].

Enforcement. Technical Specification 5.4.1 requires the licensee to establish,

implement, and maintain procedures described in Regulatory Guide 1.33, Appendix A.

Appendix A, Section 9, requires, in part, that maintenance that can affect the

performance of safety related equipment should be properly preplanned in accordance

with written procedures appropriate to the circumstances. Licensee Procedures 0.40

and 0.40.4 are similar to those described in Section 9.

Contrary to the above, on April 3, 2011, the licensee did not correctly implement the

above procedures by not properly preplanning maintenance in accordance with written

- 12 - Enclosure

procedures appropriate to the circumstances. Specifically, despite the guidance outlined

in Procedures 0.40 and 0.40.4, the licensee developed a work instruction that did not list

the needed tools and could not be followed as written. As a result, three instrumentation

and control technicians received an unexpected radiation dose. A site stand-down was

held to discuss the lessons learned from the event. Because this was of very low safety

significance and it was entered into the corrective action program as Condition

Reports CR-CNS-2011-4431, CR-CNS-2011-4581, CR-CNS-2011-4582,

CR-CNS-2011-4583, CR-CNS-2011-4584, and CR-CNS-2011-4585, this violation is

being treated as a noncited violation, consistent with Section 2.3.2 of the Enforcement

Policy: NCV 05000298/2011008-01, Unclear Work Instructions.

.2 Introduction. The inspectors identified a Green noncited violation of Technical

Specification 5.4.1, for a failure to implement procedures described in Regulatory

Guide 1.33, Appendix A. Specifically, the licensee failed to implement procedures that

provide guidance on recognizing risk associated with a maintenance activity and

properly accounting for that risk.

Description. On April 3, 2011, three instrumentation and control technicians executed

Work Order 4741002, intended to remove the intermediate range monitor C assembly

from the underside of the reactor vessel. The work order then directed the dry tube

assembly replacement. During this activity, the dry tube assembly should have been

pulled out from above the reactor vessel, creating a hole under the vessel, so a water

seal cap was to be installed under the reactor vessel to prevent reactor coolant from

draining out. This water seal cap becomes the new reactor coolant system pressure

boundary. Correct installation of this cap is critical, since any installation error could

induce a reactor coolant leak under the vessel and create a potential to drain the reactor

vessel.

The activities performed in Work Order 4741002 introduced a high level of risk to the

safe operation of the plant. Procedure 0.40, Work Control Program, Revision 75,

Section 5.7, provides examples of when a work package should be characterized as a

detailed (Level 1) work order. Because of the risk introduced, the procedure required

that Work Order 4741002 be considered a detailed work order, requiring a peer review

by both planning and engineering departments and including operational experience.

However, it was incorrectly characterized as a simple (Level 2) work order, so no

additional reviews were completed and site-specific operating experience was not

included in the work package.

Additionally, Procedure 0.40.4, Planning, Revision 16, Section 5.2.19, required the

plant impact to be determined by using Attachment 3, which includes a checklist. The

overall risk to the plant is then documented in the work package. The inspectors

attempted to review this checklist to assess its performance, however the copy of the

checklist had been discarded. The inspectors concluded that the checklist failed to

correctly categorize the risk associated with the work activity. The resulting plant impact

statement not only incorrectly stated that this work does not introduce unusual hazards

or risks and has no impact on the plant, but also incorrectly stated that the work could

be performed in Mode 4 or 5. This work can only be performed in Mode 5.

As a result of the unrecognized risk, additional barriers to ensure a quality work package

were bypassed. The resulting work package contained unclear work instructions that

could not be performed as written, did not contain a complete listing of parts needed to

- 13 - Enclosure

perform the activity, and did not contain appropriate operating experience. These

deficiencies contributed to the decision to remove the shuttle tube from under the vessel,

despite lack of actual procedural guidance. As a result, three instrumentation and

control technicians received an unexpected radiation dose. A site stand-down was held

to discuss the lessons learned from the event.

Analysis. The performance deficiency is that the licensee did not follow Procedure 0.40,

Work Control Program, and Procedure 0.40.4, Planning, when preparing Work Order 4741002 to determine the risk associated with the maintenance activity. The

resulting failure to recognize the associated risk led to the package being incorrectly

characterized as a simple work order, rather than a detailed work order, and the work

order was not given the appropriate level of attention or review. This deficiency was

reasonable for the licensee to foresee and prevent occurrence. The finding is more than

minor because it is associated with the human performance attribute of the Occupational

Radiation Safety Cornerstone and affected the cornerstone objective to ensure the

adequate protection of the worker health and safety from exposure to radiation from

radioactive material during routine civilian nuclear reactor operation, in that the finding

resulted in three technicians receiving an unexpected radiation dose. The inspectors

evaluated the significance of the finding using NRC Inspection Manual 0609,

Appendix C, Occupational Radiation Safety Significance Determination Process, dated

August 19, 2008. The inspectors determined that the finding is of very low safety

significance (Green) because it is not a finding related to ALARA planning or work

controls, it did not result in an overexposure, there was no substantial potential for

overexposure, and the licensees ability to assess dose was not compromised. The

inspectors determined that the apparent cause of this finding was the licensees failure

to ensure workers recognize the value of incorporating risk insights into plans for

maintenance activities. Therefore, the finding has a cross-cutting aspect in the work

control component of the human performance area because the licensee did not plan

work activities by incorporating risk insights H.3(a).

Enforcement. Technical Specification 5.4.1 requires the licensee to establish,

implement, and maintain procedures described in Regulatory Guide 1.33, Appendix A.

Appendix A, Section 9 requires, in part, that maintenance that can affect the

performance of safety related equipment should be properly preplanned in accordance

with written procedures appropriate to the circumstances. Licensee Procedure 0.40 and

Procedure 0.40.4 are similar to those described in Section 9. Contrary to the above, on

April 3, 2011, the licensee did not correctly implement the above procedures.

Specifically, despite the guidance contained in Procedures 0.40 and 0.40.4, the licensee

developed a work instruction that failed to recognize the risk associated with the activity

and failed to develop risk mitigation strategies. This activity had the potential to drain the

reactor vessel. Because this was of very low safety significance and it was entered into

the corrective action program as Condition Reports CR-CNS-2011-4435 and

CR-CNS-2011-4436, this violation is being treated as a noncited violation, consistent

with Section 2.3.2 of the Enforcement Policy: NCV 05000298/2011008-02, Failure to

Recognize Work Order Risk.

- 14 - Enclosure

3.2 Job Preparation

a. Scope

The inspectors assessed the licensees preparations to perform the work to replace

source range monitor B and intermediate range monitor C. This included conducting

interviews with all personnel present at the pre-job brief to determine the workers level

of understanding of the job to be performed, as well as determine the workers

procedural compliance. Procedural guidance was reviewed for adequacy and

completeness. Interactions with other working groups, such as operations and radiation

protection, were similarly reviewed. Operating experience was also reviewed to

determine the licensees efforts to incorporate and institutionalize the information.

b. Findings

Introduction. The inspectors identified a Green finding for a failure to implement human

performance procedures. Specifically, the licensee failed to implement procedures that

provided guidance on conducting pre-job briefs, preparing work in the field, and

informing technicians on what to do when the workers encountered a problem. As a

result, workers were uncertain how to proceed, especially when needed parts were not

available.

Description. On April 3, 2011, instrumentation and control technicians prepared to

perform Work Order 4741002 by conducting a pre-job brief. The brief was conducted by

the lead technician, with two other technicians and the supervisor present. Neither

technicians nor supervisor had previously performed this activity. The supervisor had

glanced at the work package, but was not familiar with it. Procedure 0-HU-Tools,

Human Performance Tools, Revision 17, Attachment 8, provides guidance on how to

conduct pre-job briefs. Attachment 8, the section entitled How To Do It, lists seven

steps for conducting the brief. Several of those steps were not adequately completed as

follows:

  • Step 1 expected the briefer to have a thorough understanding of every aspect of

the activity, however the lead technician conducting the pre-job brief was not

sure which nose cones were needed, whether the correct nose cones were

readily available, and how the activity would proceed if the correct nose cones

could not be located. The pre-job brief was completed with these questions still

unanswered. The technicians believed they would figure it out after the work

began.

  • Step 2 expected that the pre-job brief include all individuals participating in the

activity and anyone significantly impacted by the activity. The work activity

affected instrumentation and control technicians, radiation protection personnel,

and the outage control center staff. Additional work in the same package also

affected a contractor work group. Representatives from those other work groups

were not present at the instrumentation and control shop pre-job brief. A

separate pre-job brief was held with radiation protection personnel, but the level

of detail and focus of the discussion was different from that of the shop pre-job

brief.

  • Step 3 expected the licensee to review operation experience during pre-job

briefs. One example of operating experience from another site was discussed,

- 15 - Enclosure

but relevant site specific operating experience from 1993 and 1994 was omitted.

The omitted operating experience described how workers received higher-than-

expected doses when a shuttle tube was removed from under the vessel in 1993.

Since the possibility of actually removing the shuttle tube from under the vessel

was discussed during the pre-job, this operating experience may have provided a

prompt to alert the technicians that shuttle tube removal from under the vessel

would elevate dose level and potentially dissuade them from working outside the

procedure.

  • Steps 4 and 5 directed that Procedure 2.01.1, Conduct of Infrequently

Performed Tests or Evolutions, Revision 5, be used. However, this procedure

was not used. Additionally, the pre-job brief checklist directed attention to

potential error traps, such as time pressure and task unfamiliarity, but checklist

identification of these traps failed to prevent an error from occurring.

Work began after the brief was complete. During performance of Work Order 4741002,

the technicians determined that not all the needed parts were present, so a step in the

procedure could not be performed. The technicians stopped work and spoke with the

instrumentation and control supervision, who gave the workers verbal direction. This

direction included marking the procedural step as a discrepancy and continuing work

via an undocumented, unapproved back-up plan discussed at the pre-job brief.

In interviews with station personnel, the inspectors encountered indications of a

widespread attitude among workers that failures to follow procedures were acceptable if

they achieved the desired outcomes. In those interviews, the inspectors found no

evidence that the licensee effectively communicated their expectation regarding

procedural compliance. Also, as documented in Condition Report CR-CNS-2011-03763,

the licensees root cause evaluation determined that one root cause of this event was a

work culture, supported by institutional reinforcement, that unacceptable behaviors are

acceptable, as long as the outcome was good.

Analysis. The performance deficiency is that the licensee did not follow

Procedure 0-HU-Tools while preparing for and executing Work Order 4741002. As a

result, the technicians incorrectly continued work when the needed parts were not

available, rather than stopping work. This deficiency was reasonable for the licensee to

foresee and prevent occurrence. The finding is more than minor because it is

associated with the human performance attribute of the Occupational Radiation Safety

Cornerstone and affected the cornerstone objective to ensure the adequate protection of

the worker health and safety from exposure to radiation from radioactive material during

routine civilian nuclear reactor operation, in that the finding resulted in three technicians

receiving an unexpected radiation dose. The inspectors evaluated the significance of

the finding using NRC Inspection Manual 0609, Appendix C, Occupational Radiation

Safety Significance Determination Process, dated August 19, 2008. The inspectors

determined that the finding is of very low safety significance (Green) because it is not a

finding related to ALARA planning or work controls, it did not result in an overexposure,

there was no substantial potential for overexposure, and the licensees ability to assess

dose was not compromised. The inspectors determined that the apparent cause of this

finding was the licensees failure to promote the use of human performance tools to

ensure job tasks were properly completed. Therefore, this finding has a cross-cutting

aspect in the work practices component of the human performance area because the

- 16 - Enclosure

licensee did not adequately communicate human error prevention techniques such that

work activities are completed safely H.4(a).

Enforcement. This finding does not involve enforcement action because no regulatory

requirement was violated: FIN 05000298/2011008-03,Failure to Implement Human

Performance Procedure.

3.3 Work Execution

a. Scope

The inspectors assessed the licensees execution of the work to replace source range

monitor B and intermediate range monitor C. This included reviewing the work order,

procedures, and conducting interviews with all personnel present at the job site, as well

as the decision-makers in the outage control center. The inspectors assessed the

workers and managers level of understanding of the job activity and any contingency

plans or abort criteria. The inspectors reviewed procedural guidance for adequacy and

completeness, and assessed the licensees in-field procedural compliance.

Maintenance practices demonstrated by in-field workers were compared to the

licensees expectations for maintenance activities.

b. Findings

Introduction. The inspectors identified a Green noncited violation of Technical

Specification 5.4.1, for a failure to comply with procedures described in Regulatory

Guide 1.33, Appendix A. Specifically, the licensee failed to implement procedures and a

work order instruction that required the work order to be returned to work planners and

revised if the original work scope is changed or a problem is encountered.

Description. On April 3, 2011, three instrumentation and control technicians were

implementing Work Order 4741002, to remove intermediate range monitor C from the

underside of the reactor vessel and prepare the dry tube assembly for later removal from

above the reactor vessel. Work Order 4741002, Step 4, directed the technicians to

remove the drive tube per Procedure 14.2.9, SRM/IRM Detector and Drive Tube

Removal, Installation, Testing, and SRM/IRM Troubleshooting, Revision 26. Step 5.8 of

Procedure 14.2.9 directed the technicians to install a male-threaded nose cone that is

screwed onto the bottom of the dry tube, enclosing the shuttle tube within the dry tube.

Without this nose cone, the shuttle tube would fall out the bottom of the dry tube and

remain in the reactor vessel when the dry tube is removed from the top. While

performing this task, the technicians determined that the nose cone was not available.

The technicians discussed the inability to continue following the work instructions with

their supervisor. A nonconservative decision was made to pull the shuttle tube out of the

core from the bottom of the vessel rather than enclosing it in the dry tube assembly as

originally directed by the work package. This nonconservative decision was based on

unvalidated assumptions, such as shuttle tube material, expected dose rates, and

instrumentation and control familiarity with the plan change. The technicians pulled the

shuttle tube from the bottom and exposed a 3,226 rem per hour source. The

technicians dosimetry alarmed and they exited the area. As a result, three

instrumentation and control technicians received an unexpected radiation dose. A site

stand-down was held to discuss the lessons learned from the event.

- 17 - Enclosure

Work Order 4741002, Prerequisite 2, stated in part, that if during the performance of the

work order, should problems arise, workers should stop work and return the work

package to planning for revision before proceeding with work.

This guidance is congruent with two other site procedures governing procedural

compliance. Site Procedure 0.40, Work Control Program, Revision 75, Step 7.4.7,

states that if work cannot be performed as written, the worker shall stop work and

contact the supervisor, who assesses the type of change needed in accordance with

Procedure 0.40.4, Planning. Procedure 0.40.4, Revision 16, Step 5.4.1, required that a

work order revision was required if the work scope changes. In this case, the work

scope could not be completed as stated and the licensee made the decision to change

the work scope by pulling the shuttle tube from the bottom, rather than remaining within

the dry tube assembly. Additionally, Procedure 7.0.4, Conduct of Maintenance,

Revision 32, Step 10.2.3, also states that changes in intent of work activities performed

should not be made without changes to the original controlling document (work order).

Despite similar procedural guidance located in different locations, the nonconservative

decision was made to pull the shuttle tube from the bottom of the vessel, rather than

revising the work package as procedurally directed.

Analysis. The performance deficiency is that the licensee did not follow Procedure 0.40,

Work Control Program, and Procedure 7.0.4, Conduct of Maintenance, when Work Order 4741002 could not be performed as written. Work Order 4741002 also included

instructions that required the work package to be sent back to planning to be revised, if

problems arose during work order performance. This deficiency was reasonable for the

licensee to foresee and prevent occurrence. The finding is more than minor because it

is associated with the human performance attribute of the Occupational Radiation Safety

Cornerstone and affected the cornerstone objective to ensure the adequate protection of

the worker health and safety from exposure to radiation from radioactive material during

routine civilian nuclear reactor operation, in that the finding resulted in three technicians

receiving an unexpected radiation dose. The inspectors evaluated the significance of

the finding using NRC Inspection Manual 0609, Appendix C, Occupational Radiation

Safety Significance Determination Process, dated August 19, 2008. The inspectors

determined that the finding is of very low safety significance (Green) because it is not a

finding related to ALARA planning or work controls, it did not result in an overexposure,

there was no substantial potential for overexposure, and the licensees ability to assess

dose was not compromised.

The inspectors determined that the apparent cause of this finding was the licensees

failure to ensure that risk-significant changes to the work orders were made only through

established processes. Therefore, this finding has a cross-cutting aspect in the decision

making component of the human performance area because the licensee did not use a

systematic process to make the risk-significant decision to deviate from work

instructions H.1(b).

Enforcement. Technical Specification 5.4.1 requires the licensee to establish,

implement, and maintain procedures described in Regulatory Guide 1.33, Appendix A.

Appendix A, Section 9 requires, in part, that maintenance that can affect the

performance of safety related equipment should be properly preplanned in accordance

with written procedures appropriate to the circumstances. Licensee Procedure 0.40,

Procedure 7.0.4, and maintenance Work Order 4741002 are similar to those described

- 18 - Enclosure

in Section 9, in that, they required work orders that could not be performed as written to

be returned to planning for revision. Contrary to the above, on April 3, 2011, the

licensee did not correctly implement the above procedures. Specifically, the licensee

failed to return the work package to planning for a revision when the work order could

not be performed as written and when workers changed the intended work scope. As a

result, three instrumentation and control technicians received an unexpected radiation

dose. A site stand-down was held to discuss the lessons learned from the event.

Because this was of very low safety significance and it was entered into the corrective

action program as Condition Reports CR-CNS-2011-4428, CR-CNS-2011-4581,

CR-CNS-2011-4582, CR-CNS-2011-4583, CR-CNS-2011-4585, CR-CNS-2011-4591,

and CR-CNS-2011-4592, this violation is being treated as a noncited violation,

consistent with Section 2.3.2 of the Enforcement Policy: NCV 05000298/2011008-04,

Failure to Revise Unclear Work Instructions.

4.0 Radiation Protection Performance

4.1 ALARA Planning

a. Scope

The inspectors assessed the licensees performance while developing the ALARA work

package to replace source range monitor B and intermediate range monitor C. The

inspectors conducted interviews to assess the knowledge level and qualifications of

ALARA planners. The inspectors examined the adequacy and completeness of

procedural guidance for developing ALARA work packages. Interactions between

radiation protection, maintenance, and operations were reviewed to determine if ALARA

planning was performed with appropriate coordination and communication. The

inspectors also evaluated the licensees review process to ensure that work packages

are complete and accurate.

b. Findings

No findings were identified. The inspectors determined that the ALARA planning for the

job was completed adequately for removing the source range monitor and intermediate

range monitor through the top of the reactor vessel. However, since the workers

changed plans during the execution of the plan and did not seek a revision to the ALARA

plan, a finding was identified in the area of work execution (see Section 3.3).

4.2 Radiation Work Permit Adequacy

a. Scope

The inspectors assessed the licensees performance with respect to maintaining

occupational individual and collective radiation exposures ALARA. The inspectors used

the requirements in 10 CFR Part 20, the technical specifications, and the licensees

procedures required by technical specifications as criteria for determining compliance.

The inspectors reviewed the licensees previous experience with similar jobs, historical

information regarding doses received, and historical and current survey data used to

establish the radiological conditions of the radiation work permit including dose and dose

rate alarm setpoints.

- 19 - Enclosure

b. Findings

No findings were identified. The inspectors determined that the radiation work permit

was adequate for the original plan to remove the source range monitor and intermediate

range monitor through the top of the reactor vessel. However, since the workers

changed plans and did not seek a revision to the radiation work permit, a finding was

identified in the area of work execution (see Section 3.3).

4.3 ALARA Briefing

a. Scope

The inspectors assessed the licensees ALARA briefing of workers preparing to enter the

drywell to perform the work to replace source range monitor B and intermediate range

monitor C. The inspection included conducting interviews with personnel in attendance

at the pre-job ALARA briefing to determine the workers level of understanding of the job

to be performed, as well as, determine if the workers were appropriately briefed per high

radiation area technical specifications and licensee procedures. The inspectors

reviewed the licensees radiation work permit and high radiation area briefing sheets to

determine if the licensee had adequately assessed the scope of the job to be performed.

The inspectors reviewed the licensees implementation of the requirements of 10 CFR

Parts 19 and 20.

b. Findings

Introduction. The inspectors identified a Green noncited violation of Technical

Specification 5.7.2, for the failure to adequately brief radiation workers entering a locked

high radiation area. Specifically, on April 2, 2011, the radiation protection pre-job

briefing failed to discuss radiation dose rates that may be encountered when pulling the

intermediate range monitor shuttle tube from under the reactor pressure vessel and did

not identify any scope change or breach of the under-vessel nuclear instrument system.

Description. On April 2, 2011, three instrumentation and control technicians were

provided with an ALARA pre-job briefing by radiation protection personnel for entry into a

high radiation area to perform work on special (radiation) Work Permit 2011-422. The

job scope included removing intermediate range monitor C shuttle tube from the bottom

of the reactor pressure vessel. The shuttle tube was highly radioactive because it had

been in the reactor core. The ALARA briefing provided information to the workers about

general area dose rates and electronic dosimetry alarm setpoints. However, the ALARA

briefing did not provide dose rates that would be encountered when removing the shuttle

tube because the radiation protection personnel providing the ALARA briefing did not

have an understanding of the full scope of the job and did not ask any questions to

clarify or confirm the full scope of the job. Therefore, the ALARA briefing did not make

workers knowledgeable about the dose rates they would encounter during the job. As a

result, when the workers removed the shuttle tube from the bottom of the vessel,

radiation levels of 3,226 rem per hour on contact with the tip of the shuttle tube and

39 rem per hour at 30 centimeters, as measured later by an AMP-200 detector, were

encountered. The workers electronic dosimetry alarmed and they immediately left the

area and contacted radiation protection personnel.

The inspectors interviewed radiation protection personnel, the three workers, and other

site personnel involved in the event. The inspectors reviewed the special work permit

- 20 - Enclosure

requirements, surveys used during the ALARA briefing, and the radiation protection

briefing form used for the ALARA briefing. The inspectors determined that the ALARA

briefing form indicated no system breach was to be performed during this job, however,

that was not true because the workers planned to breach the incore nuclear instrument

system. The ALARA briefing did not cover a system breach of the nuclear instrument

system, even though it was originally planned. The ALARA briefer lacked a questioning

attitude with respect to gaining an understanding of the full scope of the work activity that

the technicians were about to perform. The briefer did not question the special work

permit dose setpoints that were set at 300 and 600 millirem/hr even though the ALARA

briefing form indicated dose rates in the area of 80-120 millirem/hr. Additionally, there

was no discussion or review of relevant Cooper Nuclear Station operating experience,

which would have identified that high dose rates would be encountered during the

performance of this work activity.

The inspectors determined that the pre-job ALARA briefing was inadequate because the

workers were not made knowledgeable of the dose rates in a high radiation area while

performing the activities they had planned as required by Technical Specification 5.7.2.

The inspectors also determined that the licensee failed to appropriately communicate,

coordinate, and cooperate with each other during the ALARA pre-job briefing and to

keep personnel apprised of plant conditions that may affect work activities to ensure

radiological safety was maintained.

Analysis. The failure to perform an adequate ALARA briefing to make workers

knowledgeable of the dose rates in the work area is a performance deficiency. The

finding is more than minor because it is associated with the human performance attribute

of the Occupational Radiation Safety Cornerstone and affected the cornerstone objective

to ensure the adequate protection of the worker health and safety from exposure to

radiation from radioactive material during routine civilian nuclear reactor operation, in

that the finding resulted in three technicians receiving an unexpected radiation dose.

The inspectors evaluated the significance of the finding using NRC Inspection

Manual 0609, Appendix C, Occupational Radiation Safety Significance Determination

Process, dated August 19, 2008. The inspectors determined that the finding is of very

low safety significance (Green) because it is a finding related to ALARA planning or work

controls, but the licensees three year rolling average for collective dose is less than

240 person-rem. The inspectors determined that the apparent cause of this finding was

that the licensee had not encouraged interdepartmental communication and coordination

between workers to ensure that workers were properly prepared to begin work activities.

Therefore, this finding has a cross-cutting aspect in the work control component of the

human performance area because the licensee did not incorporate actions to address

the need for work groups to communicate, coordinate, and cooperate with each other

during activities in which interdepartmental coordination is necessary to assure human

performance, in that the licensee did not address the need for work groups to

communicate, coordinate, and cooperate with each other during the ALARA pre-job

briefing, which was an activity in which interdepartmental coordination is necessary to

assure human performance H.3(b).

Enforcement. Technical Specification 5.7.2 states that, in addition to the requirements of

Specification 5.7.1, entry into high radiation areas accessible to personnel with dose

rates such that a major portion of the whole body could receive in 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> a deep dose

equivalent in excess of 1000 millirem shall be provided with locked doors except during

periods of access by personnel under an approved special work permit which shall

- 21 - Enclosure

specify the dose rates in the area. Technical Specification 5.7.1(b) states, in part, that

individuals permitted to enter high radiation areas shall be provided with a monitoring

device that continuously integrates the radiation dose and alarms when a preset dose is

received. Entry into such areas may be made after the dose rates in the area have been

established and personnel have been made knowledgeable of them. Contrary to this

requirement, on April 2, 2011, the licensee failed to adequately brief the dose rates in

the immediate work area and make workers knowledgeable of the dose rates within the

high radiation area before allowing entry into the area. Because this violation was of

very low safety significance and it was entered into the corrective action program as

Condition Report CR-CNS-2011-04441, this violation is being treated as a noncited

violation, consistent with Section 2.3.2 of the Enforcement Policy:

NCV 05000298/2011008-05, Failure to Perform an Adequate High Radiation Area

Briefing.

4.4 Job Coverage

a. Scope

The inspectors reviewed the licensees actions with respect to providing radiation

protection coverage of workers entering a locked high radiation area to perform work

during the shuttle tube event. The inspectors used the requirements in 10 CFR Part 20,

the technical specifications, and the licensees procedures required by technical

specifications as criteria for determining compliance. During the inspection, the

inspectors interviewed the radiation protection manager, radiation protection

supervisors, radiation protection technicians, and radiation workers. The inspectors

performed tours of the plant to understand scope of the job during the shuttle tube event.

The inspectors reviewed radiological hazards control and work coverage, including the

adequacy of surveys, radiation work permits, radiation protection job coverage, and

contamination controls. The inspectors reviewed radiation worker and radiation

protection technician performance during the shuttle tube event.

b. Findings

Introduction. The inspectors identified a Green noncited violation of Technical

Specification 5.4.1.a for the failure to follow radiation protection Procedure 9.EN-RP-141,

Job Coverage, Revision 8. Specifically, during the nightshift on April 2, 2011, radiation

protection personnel were monitoring workers pulling the intermediate range monitor

shuttle tube from under the reactor pressure vessel and failed to adequately implement

several requirements of the job coverage procedure which resulted in workers being

exposed to unexpected high dose rates up to 39 rem per hour at 30 centimeters from the

shuttle tube.

Description. On April 2, 2011, three workers entered the drywell, which was a posted

locked high radiation area, to perform work to remove the intermediate range monitor C

shuttle tube. Prior to entering the drywell, the workers donned protective clothing and

respiratory protection (powered air purifying respirators). The radiation protection

technicians at the drywell entry point assisted the workers with donning the respirators

and were responsible for monitoring the workers radiation dose. For entries into locked

high radiation areas, radiation protection technicians were required to monitor work

activities remotely or at the job site. For this activity, the licensee determined that

remote monitoring using teledosimetry (radiation dose transmitted from electronic

- 22 - Enclosure

dosimeters to a remote monitoring station) and continuous communications (via a site

cell phone) was sufficient to provide adequate radiation protection job coverage for the

workers. The required actions for remote monitoring job coverage activities in a locked

high radiation area prior to, and during, the performance of the work were described in

Station Procedure 9.EN-RP-141, Job Coverage, Revision 8.

The inspectors interviewed station personnel, toured the drywell entry point, and

reviewed station procedures. The inspectors identified that radiation protection

personnel had failed to adequately implement several job coverage procedural

requirements, which either resulted in, or contributed to, the workers being exposed to

higher than expected dose rates. The failures are described below:

1. The remote-monitoring technician did not attend the ALARA pre-job briefing for

the work. Attachment 2, Section 2, Responsibilities, Procedure 9.EN-RP-141,

states that the radiation protection technician providing job coverage is

responsible for attending the pre-job briefing. This failure resulted in the remote

monitoring technician not having a full understanding of the work scope, and

therefore, the remote monitoring technician was not able to identify when the

scope changed. The remote monitoring technician believed that the work scope

was limited to an inspection activity only, and not a maintenance activity to

remove the intermediate range monitor C shuttle tube from beneath the reactor

pressure vessel.

2. Radiation protection technicians providing job coverage failed to establish a

method of communication. For this activity, it was decided that site cell phones

would be used to communicate with the workers. Step 2.13 of

Procedure 9.EN-RP-141 required that when using site cell phones as a

communication device during continuous job coverage, it is required to have the

keypad locked. Locking the phone ensured that communication from radiation

protection to the workers was maintained during remote job coverage activities.

(Step 2.13 was added to the procedure as a corrective action to a 2009 NRC

violation because the site cell phone used during job coverage activities in 2009

had been inadvertently turned off and communication with workers was lost.

That issue was documented in NRC Inspection Report 05000298/2009005.)

However, the procedure did not make clear whose responsibility it was for

locking the cell phone. When the inspectors interviewed station personnel to

determine whose responsibility it was to lock the cell phone keypad, the

inspectors received mixed answers, with some personnel stating it was the users

responsibility, others stated it was radiation protection technicians responsibility,

while others stated it was workers responsibility to lock the keypad but radiation

protection personnel had to verify that the cell phone keypad was locked. The

inspectors determined this lack of clarity about whose responsibility it was to

have the phone locked contributed to the failure to ensure the phone was locked

and stayed locked except when needed to establish communications with

radiation protection.

3. The remote monitoring technician failed to review the applicable special

(radiation) work permit as required by Step 5.5.1 of Procedure 9.EN-RP-141.

This requirement ensures that the remote monitoring technician becomes

knowledgeable of the work scope, such that if the scope changes the remote

monitoring technician can take the appropriate actions when necessary. For this

- 23 - Enclosure

event, the appropriate action would have been to stop the job, have the workers

leave the work site, and prepare a revised radiation work permit.

4. The remote monitoring technician providing job coverage failed to communicate

with workers to inform the workers of the radiological hazards associated with the

nuclear instrument system, potential changes that would occur during the course

of activities, understand the details of the work activity, and in particular any job

steps that could impact radiological conditions as required by Step 5.5.4.2 of

Procedure 9.EN-RP-141. The remote monitoring technician did not discuss the

details of the work activity with the workers, and therefore, was not able to

communicate the hazards that were associated with the work activity. The

remote monitoring technician believed the workers were only going to perform an

inspection under the reactor pressure vessel. The remote monitoring technician

assumed that the ALARA pre-job briefing covered all radiological aspects of the

work activity and did not believe the work activity would breach any systems or

remove any parts. This assumption was not verified or validated.

5. Step 6.4.5 of Procedure 9.EN-RP-141 required that communication devices are

verified operational between the remote monitoring station and the work location.

Neither the workers nor the remote monitoring technician attempted to make

contact with each other during the work activity.

6. Workers used the dedicated radiation protection cell phone to contact the outage

control center to discuss the work activity with maintenance personnel. The

remote monitoring technician could view the workers on the video monitor and

see that the site cell phone designated for radiation protection coverage was in

use and was not locked in accordance with Step 2.13 of the procedure. While

the site cell phone is in use, it cannot be called. There is no call waiting. There

is only a busy signal. Step 6.4.7 of Procedure 9.EN-RP-141 required that if

communication is lost then it should be re-established in accordance with the

procedure, or work activities suspended and personnel cleared from the area.

No attempt was made to perform these requirements while communication was

lost. In addition, the inspectors identified that the licensees dayshift remote

monitoring technicians used radios for communications and nightshift used cell

phones. This inconsistency between dayshift and nightshift contributed to the

loss of communications during this activity. The licensee corrected this

discrepancy by requiring all remote monitoring technicians to use radios for

continuous coverage communications.

7. Workers lowered the shuttle tube to the floor of the drywell prior to receiving

permission to pull it all the way out of the reactor vessel. Step 5.5.4.2 of

Procedure 9.EN-RP-141 required the remote monitoring technician to monitor

the work location to determine if new sources of exposure are being generated

(e.g., trash or parts removed from the system). The shuttle tube is a part of the

nuclear instrument system and was beyond the scope of what the remote

monitoring technician believed to be the work activity (inspection only). Video

monitoring showed the part being lowered to the floor at which point the

technician should have called the workers and told them to stop the activity.

8. The remote monitoring technician failed to exercise the stop work authority.

Step 7.1 of Procedure 9.EN-RP-141 stated that radiation protection technicians

- 24 - Enclosure

have both the responsibility and authority to stop work if there is a change in

work scope or the continuance of work would result in a violation of good

radiological work practices, or a violation of radiological work permit or special

work permit requirements. When the workers changed scope during the

performance of the work activity from what was understood by the remote

monitoring technician, the work was required to be stopped.

The work was not stopped when the shuttle tube was initially pulled from the reactor

vessel. Therefore, the workers under the vessel pulled the entire 27-foot-long shuttle

tube out of the reactor vessel, and exposed themselves to the highly radioactive end of

the shuttle tube. The workers electronic dosimeters alarmed on high dose rate. The

workers immediately left the area under the vessel and informed a radiation protection

technician in the area that the dose rates had significantly increased. The licensee

entered their emergency procedures for unexpected radiation levels in the building,

cleared the drywell, and restricted access until the source of the radiation was identified.

The licensees immediate corrective actions were to restrict access to the drywell,

ensure that further work activities in the drywell had been reviewed and approved by the

radiation protection supervision, and pursue activities to recover the drywell area under

the reactor vessel by securing the shuttle tube.

During the recovery phase of the activity, radiation protection personnel measured

contact radiation dose rates as high as 3,226 rem per hour, and 39 rem per hour at

30 centimeters from the shuttle tube. Radiation protection technicians recovered the

drywell by placing the highly radioactive portion of the shuttle tube in a shielded

container.

While interviewing personnel involved in this event, the inspectors encountered no

indication that workers had used human error prevention techniques to ensure that they

followed procedures.

Analysis. The failure to follow radiation protection job coverage procedures is a

performance deficiency. The finding is more than minor because it could be viewed as,

both, a precursor to a significant event, and if left uncorrected, could have led to a more

safety significant concern. It is also associated with the human performance attribute of

the Occupational Radiation Safety Cornerstone and affected the cornerstone objective to

ensure the adequate protection of the worker health and safety from exposure to

radiation from radioactive material during routine civilian nuclear reactor operation

because it resulted in workers receiving higher than expected doses. The inspectors

evaluated the significance of the finding using NRC Inspection Manual 0609,

Appendix C, Occupational Radiation Safety Significance Determination Process, dated

August 19, 2008. The inspectors determined that the finding is of very low safety

significance (Green) because the finding did not involve ALARA planning and work

controls, did not result in an overexposure, did not involve a substantial potential for

overexposure, and did not compromise the licensees ability to assess dose.

Additionally, the inspectors determined that the apparent cause of this finding was the

licensees failure to encourage workers to use human error prevention techniques to

ensure that they followed procedures. Therefore, this finding has a crosscutting aspect

in the work practices component of the human performance area because the licensee

failed to use human error prevention techniques such as self-checking and peer-

checking to ensure that job coverage procedures were followed H.4(a).

- 25 - Enclosure

Enforcement. Technical Specifications 5.4.1 states in part, that written procedures shall

be established, implemented, and maintained covering the applicable procedures

recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978.

Regulatory Guide 1.33, Section 7, required radiation protection procedures, including

access control to radiation areas. Licensee Procedure 9.EN-RP-141, Job Coverage,

Revision 8, in part, required the licensee to implement the following job coverage

activities :

(1) (Step 2.13) when site cell phones are used as a communication device during

continuous job coverage, the keypad must be locked,

(2) (Step 3.4) communicate with workers to tell them about radiological hazards

associated with the systems to be worked and potential changes that would

occur during the course of activities, and understand the details of the work

activity to be performed and job steps that could impact radiological conditions or

result in personnel contaminations,

(3) (Step 5.5.1) upon assignment, review the applicable special work permit to

determine the scope of work to be performed,

(4) (Step 5.5.4.2) monitor the work location to determine if new sources of exposure

are being generated (e.g., parts removed from the system),

(5) (Step 6.4.5) verify communication devices operate between the remote

monitoring technician station and the work location,

(6) (Step 6.4.7) if continuous coverage by remote monitoring is lost, then either

reestablish continuous job coverage by other means or suspend work activities

and clear personnel from the work area,

(7) (Step 7.1) stop work if there is a change in work scope or if the initiation of work

or the continuance of work would result in a violation of good radiological work

practices or a violation of radiation work permit/special work permit

requirements, and

(8) (Attachment 2, Section 2 responsibilities, Step 2.4) attend the pre-job briefing.

Contrary to the above, on April 3, 2011, the licensee failed to:

(1) lock the cell phone keypad,

(2) inform the workers of radiological hazards associated with the nuclear instrument

system,

(3) review the special work permit,

(4) monitor the work location to determine if new sources of exposure are being

generated,

(5) verify communication devices operation between the remote monitoring

technician and the work location,

- 26 - Enclosure

(6) suspend work activities and clear personnel from the area when communication

was lost,

(7) stop work when there was a change in work scope or the work would result in a

violation of the radiation work permit requirements, and

(8) attend the pre-job briefing.

Because this finding is of very low safety significance and has been entered into the

licensees corrective action program as Condition Reports CR-CNS-2011-04442,

CR-CNS-2011-04255, CR-CNS-2011-04595, CR-CNS-2011 -05443,

CR-CNS-2011-05444, CR-CNS-2011-05446, CR-CNS-2011-05447, and

CR-CNS-2011-05448, this violation is being treated as a noncited violation consistent

with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000298/2011008-06, Failure

to Follow Radiation Protection Job Coverage Procedures.

4.5 Dose and Dose Rate Assessment

a. Scope

The NRC performed an independent assessment of the dose and dose rate information

using time motion studies to identify source of radiation, the exposure time, and the

distance between the source and the workers tissue. The source of the radiation was

the activated tip of the intermediate range monitor B shuttle tube. It was activated by the

nuclear reactor core because it is composed of stainless steel exposed to neutrons

during the operating cycle of the power reactor. Although the shuttle tube is in its

retracted position during the cycle and is only inserted into the core during startup and

shutdown operations, the end of the tube still becomes radioactive from long-term

exposure to neutrons. Approximately, the top one inch of the tube is activated

significantly more than the rest of the tube because of its retracted position, which is

about 24 inches below the bottom core plate. The NRC performed an independent

assessment of the skin dose to the hand of the worker who removed the shuttle tube

from the reactor pressure vessel. This assessment was performed by the NRCs senior

advisor for health physics using a software program called Monte Carlo N-particle. Dose

rate data measured by the licensee during the recovery phase of event was entered into

Monte Carlo N-particle. The data included AMP-200 Geiger Mueller detector and

optically stimulated luminescent dosimeters which are specifically designed to measure

shallow dose equivalent to human tissue. The AMP-200 data included 3,226 rem per

hour on contact and 39 rem per hour at 30 centimeters. The optically stimulated

luminescent data included 0.338 rem per second at one inch from the source. Based on

time motion studies conducted later with workers, the individual handling the shuttle tube

grasped the end of the shuttle tube for about 1.7 seconds.

Based on the time motion study that was reviewed by the inspectors and the

independent Monte Carlo N-particle calculation performed by the NRC, the estimated

skin dose to the hand of the worker who grasped the source was 2.9 rem. This dose is

well below the regulatory limit of 50 rem. The licensee employed a certified health

physicist to perform the dose calculation. The certified health physicist used manual

calculations and a combination of computer codes to determine the skin dose. The

licensees estimated skin dose was 3.1 rem. Although the licensee used a different

methodology than the NRC, the estimated skin doses are in relative agreement and

differ by only 8 percent. Both values are significantly below regulatory limits and

- 27 - Enclosure

therefore warrant no further analysis. The whole body dose assigned to the individual

was 0.040 rem based on the electronic dosimeter readings and the time motion studies.

The whole body dose is also below the annual regulatory limit of 5.0 rem.

b. Findings

No findings were identified.

5.0 Review of Previous Activity Performance

a. Scope

The inspectors reviewed previous intermediate range monitor and source range monitor

removal activities. The inspectors assessed the adequacy of prior work packages and

the execution of those work orders. Previous condition reports and past operating

experience were reviewed for lessons learned. The inspectors compared the previous

work orders to Work Order 4741002, to determine if this method (pulling the shuttle tube

from the bottom) had been used in the past.

b. Findings

No findings were identified. Operating experience showed that a shuttle tube had

previously been pulled from the bottom of the vessel, however this was a necessary

action resulting from a stuck detector. In this instance, the licensee also experienced

elevated radiation levels. The normal (proceduralized) method for replacing the tubing

assembly was to remove the assembly from the top of the core.

6.0 Review of Causal Determination and Corrective Actions

a. Scope

The inspectors reviewed the preliminary root cause evaluation report and corrective

actions identified to prevent recurrence of the root causes. The inspectors interviewed

members of the licensees root cause team and licensee management. At the end of the

inspection period, the inspectors did not have the opportunity to review the final version

of the root cause evaluation because the final report had not been completed and

reviewed by licensee management.

b. Findings

No findings were identified. Because the final root cause report had not been completed

at the time of this report, the inspectors were unable to evaluate its adequacy against the

licensees corrective action program procedures. Therefore, the final root cause report

will be subject to inspection at a future date. Notwithstanding the issuance of the final

root cause evaluation report, the inspectors noted that the licensees preliminary root

causes were consistent with the findings identified in this report. The licensees long

term corrective actions are still in the process of being developed, however, interim

actions have been taken to prevent recurrence of this event. These actions include work

order process procedure revisions to include identification of materials required to

perform maintenance, implementing a work order quality review panel, revising work

order risk assessment procedures, revising radiation protection briefing forms to ensure

full extent of job scope is discussed at the ALARA briefing, reinforcing requirement for

- 28 - Enclosure

radiation protection to attend all locked high radiation area briefings, and developing

specific expectations for supervisors to ensure procedure compliance is mandatory.

4OA6 MEETINGS

On April 15, 2011, the team presented the preliminary results of this inspection at the

end of the onsite week to Mr. D. Willis, General Manager Plant Operations, and other

members of the licensee staff who acknowledged the findings. The team returned all

proprietary information reviewed during the inspection prior to leaving the site.

On May 3, 2011, the team presented the final results of the inspection to

Mr. A. Zaremba, Director of Nuclear Safety Assurance, and other members of the

licensee staff via telephonic exit. The team obtained permission from the licensee to use

the diagrams and photographs in this report.

On June 9, 2011, the team re-exited and presented revised results of the inspection to

Mr. A. Zaremba, Director of Nuclear Safety Assurance, and other members of the

licensee staff via telephonic exit.

ATTACHMENT 1: SUPPLEMENTAL INFORMATION

ATTACHMENT 2: SPECIAL INSPECTION CHARTER

ATTACHMENT 3: PICTURES AND DIAGRAMS

- 29 - Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Bednar, Supervisor, Radiation Protection

J. Corey, Manager, Radiation Protection

E. McCutchen, Senior Licensing Engineer, Licensing

H. A. Hawkins, Superintendent, Instrumentation and Control

D. Willis, Plant Manager

A. Zaremba, Director of Nuclear Safety Assurance

NRC Personnel

M. Chambers, Resident Inspector

B. Hagar, Senior Project Engineer

J. Josey, Senior Resident Inspector

R. Pedersen, Senior Health Physicist

S. Sherbini, Senior Level Advisor for Health Physics

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

050000298/2011008-01 NCV Unclear Work Instructions (Section 3.1)

050000298/2011008-02 NCV Failure to Recognize Work Order Risk (Section 3.1)

050000298/2011008-03 FIN Failure to Implement Human Performance Procedure

(Section 3.2)

050000298/2011008-04 NCV Failure to Revise Unclear Work Instructions (Section 3.3)

050000298/2011008-05 NCV Failure to Perform an Adequate High Radiation Area

Briefing (Section 4.3)

050000298/2011008-06 NCV Failure to Follow Radiation Protection Job Coverage

Procedures (Section 4.4)

A1-1 Attachment 1

DOCUMENTS REVIEWED

Section 4OA3: Event Follow-up

CONDITION REPORTS

94-1262 NCR 93-045

CR-CNS-2011-3769 CR-CNS-2011-4584 CR-CNS-2011-4588 CR-CNS-2011-3763

CR-CNS-2011-4255 CR-CNS-2011-4256 CR-CNS-2011-4258 CR-CNS-2011-4317

CR-CNS-2011-4428 CR-CNS-2011-4431 CR-CNS-2011-4432 CR-CNS-2011-4436

CR-CNS-2011-4429 CR-CNS-2011-4430 CR-CNS-2011-4438 CR-CNS-2011-4439

CR-CNS-2011-4440 CR-CNS-2011-4441 CR-CNS-2011-4442 CR-CNS-2011-4583

CR-CNS-2011-4581 CR-CNS-2011-4435 CR-CNS-2011-4433 CR-CNS-2011-4582

CR-CNS-2011-4591 CR-CNS-2011-4585 CR-CNS-2011-4586 CR-CNS-2011-3890

CR-CNS-2011-4592 CR-CNS-2011-4583 CR-CNS-2011-4587 CR-CNS-2011-4258

CR-CNS-2011-4593 CR-CNS-2011-4594 CR-CNS-2011-4595 CR-CNS-2011-4596

CR-CNS-2011-4597 CR-CNS-2011-4598 CR-CNS-2011-4599 CR-CNS-2011-4600

CR-CNS-2011-4601 CR-CNS-2011-5443 CR-CNS-2011-5444 CR-CNS-2011-5446

CR-CNS-2011-5447 CR-CNS-2011-5448 CR-CNS-2011-5450

WORK ORDERS

4741009 4741002 4741006 4491177

RADIATION/SPECIAL WORK PERMITS

2009-422 2011-422 2011-465

PROCEDURES/DOCUMENTS

NUMBER TITLE REVISION

14.2.19 SRM/IRM Detector and Drive Tube Removal, 26

Installation, Testing, and SRM/IRM Troubleshooting

14.2.19 SRM/IRM Detector and Drive Tube Removal, 27

Installation, Testing, and SRM/IRM Troubleshooting

0.40 Work Control Program 75

A1-2 Attachment 1

0.40.4 Planning 16

0.1 Procedure Use and Adherence 36

7.0.4 Conduct of Maintenance 32

0-HU-TOOLS Human Performance Tools 17

2.0.1.1 Conduct of Infrequently Performed Tests and 5

Evolutions

10.29 LPRM and SRM/IRM Dry Tube Removal and 29

Installation

IAC722-00-00, Fig. 12 Detector Drive Unit 0

IAC722-00-00, Fig. 9 Source Range and Intermediate Range Detector 0

Drive

9.EN-RP-141 Job Coverage 8

9.ALARA.4 Radiation Work Permits 14

9.ALARA.5 ALARA Planning and Controls 21

5.1RAD Building Radiation Trouble 15

A1-3 Attachment 1

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGI ON I V

612 EAST LAMAR BLVD, SUITE 400

ARLINGTON, TEXAS 76011-4125

April 7, 2011

MEMORANDUM TO: Dean Overland, Resident Inspector

Projects Branch E

Division of Reactor Projects

Binesh Tharakan, Resident Inspector

Projects Branch A

Division of Reactor Projects

FROM: Kriss Kennedy, Director /RA/

Division of Reactor Projects

SUBJECT: SPECIAL INSPECTION CHARTER TO EVALUATE UNEXPECTED

DOSES TO WORKERS AT COOPER NUCLEAR STATION

A Special Inspection Team is being chartered in response to a work activity that resulted in

unexpected doses to workers at the Cooper Nuclear Station on April 3, 2011. Dean Overland is

designated as the Special Inspection Team Lead with respect to work-control issues. Binesh

Tharakan is designated as the Special Inspection Team Lead with respect to radiological

issues.

A. Basis

On April 3, 2011, while licensee workers were preparing to remove the Intermediate

Range Monitor-C (IRM-C) drive mechanism shuttle tube from the top of the reactor

vessel, they discovered they did not have access to a waterproof nose cone that was to

be attached to the lower end of the tube prior to removal.

When the workers reported this issue to the Outage Control Center (OCC), the OCC

staff reportedly either instructed or gave permission to the workers to remove the shuttle

tube from the bottom of the reactor vessel, instead of from the top as originally planned.

The inspectors understand that the licensee did not modify either the associated work

order or the corresponding Radiation Work Permit (RWP) to reflect this change.

As the workers removed the tube from the bottom of the vessel, the three workers under

the vessel and one worker at the access point received dose-rate alarms. The workers

then set the tip of the tube on the floor at the 888 elevation and exited the area. The

workers dosimeters reportedly measured dose rates of 1.35 rem per hour, 14.3 rem per

hour, and 763 millirem/hr.

A2-1 Attachment 2

Surveys taken later found that the tip of the tube measured 3226 rem/hr on contact and

39 rem/hr at 30 cm, and that the general area dose rate was 4.6 rem/hr at waist level,

increasing to 8.6 rem/hr at waist level near the tube.

B. Scope

The inspection is expected to perform data gathering and fact-finding in order to address

the following:

1. Develop a sequence of events leading up to the event, actions taken upon receipt of

dose rate alarms, and actions taken to reduce the dose rates following the event.

2. Develop a timeline and assess the decision-making process used by licensee

personnel to deviate from the planned method to remove intermediate range

monitor C.

3. Assess licensee compliance with procedures and work orders in accomplishing the

evolution.

4. Compare and contrast performance of this activity on April 3, 2011 to the

performance of similar activities during the current outage.

5. Review history of the licensees conduct of this evolution to determine if they have

used this method of removal prior to April 3, 2011.

6. Characterize the dose rates during the event and the dose received by involved

personnel.

7. Assess as low as reasonably achievable (ALARA) planning for the evolution.

8. Assess adequacy of the radiation work permit and pre-job briefing for this activity.

9. Review any preliminary cause determination the licensee has completed and assess

adequacy of short term corrective actions.

10. Collect data necessary to support completion of the significance determination

process.

C. Guidance

Inspection Procedure 93812, ASpecial Inspection,@ provides additional guidance to be

used by the Special Inspection Team. Your duties will be as described in Inspection

Procedure 93812. The inspection should emphasize fact-finding in its review of the

circumstances surrounding the events. Safety concerns identified that are not directly

related to the event should be reported to the Region IV office for appropriate action.

The team will report to the site, conduct an entrance, and begin inspection no later than

April 11, 2011. While onsite, you will provide daily status briefings to Region IV

management, who will coordinate with the Office of Nuclear Reactor Regulation to

ensure that all other parties are kept informed. Depending on the outcome of the

inspection, inspection results will be documented in U. S. Nuclear Regulatory

Commission (NRC) Special Inspection Report No. 05000298/2011008. This report will

be issued within 45 days of the completion of the inspection.

A2-2 Attachment 2

This Charter may be modified should the team develop significant new information that

warrants review. Should you have any questions concerning this charter, please contact

Vince Gaddy or Bob Hagar.

R:\_Reactors\CNS 2011\SI Charter 110407.docx ADAMS ML

SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials VGG

Publicly Avail Yes No Sensitive Yes No Sens. Type Initials

VGG

RIV:C/DRP/PBC C/DRP/PBC D:DRP D:DRP

RHagar: jm VGaddy KKennedy

/RA/ /RA/ /RA/

04/ 6 /2011 04/ 7 /2011 04/ 7 /2011

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

A2-3 Attachment 2

A3-1 Attachment 3

A3-2 Attachment 3