ML103210644
Letter Sequence Request | |
---|---|
TAC:MD6311, Clarify Application of Setpoint Methodology for LSSS Functions, Control Room Habitability, Steam Generator Tube Integrity (Approved, Closed) TAC:MD8314, Clarify Application of Setpoint Methodology for LSSS Functions, Control Room Habitability, Steam Generator Tube Integrity (Open) | |
Initiation Results Other: CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12, CNL-15-137, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 13, ML080860026, ML080860040, ML081700293, ML082410088, ML083460177, ML090480486, ML101260469, ML102170077, ML102290258, ML103010299, ML11213A130, ML11362A056, ML12234A688, ML13023A315, ML13213A194 | |
MONTHYEARML0732401242007-11-26026 November 2007
[Table View]Summary of Meeting with Tennessee Valley Authority on Use of Eagle 21 at Watts Bar Unit 2 Project stage: Meeting ML0734400222007-12-0505 December 2007 Westinghouse Eagle - 21 Process Protection System Project stage: Request ML0801705432008-01-0303 January 2008 Summary of December 12, 2007, Meeting with Tennessee Valley Authority on Reconstruction of the Licensing Basis for Watts Bar Unit 2 Project stage: Meeting ML0735209712008-01-0303 January 2008 Summary of Meeting with Tennessee Valley Authority on Reconstitution of the Licensing Basis for Watts Bar, Unit 2 Project stage: Meeting ML0803701852008-02-0101 February 2008 Request to Use American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code, Code Case N-520-2, Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction. Project stage: Other ML0812105062008-05-0707 May 2008 Request for Additional Information Regarding Eagle-21 Process Protection System (Tac No. MD6311) Project stage: RAI ML0810101162008-05-0808 May 2008 Review Topics for Safety Evaluation, Attachment 1 Project stage: Approval ML0808600402008-05-0808 May 2008 Enclosure 1- Watts Bar Nuclear Plant, Unit 2 - Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0808600262008-05-0808 May 2008 Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0814300282008-05-14014 May 2008 Transmittal of Annual Radiological Environmental Operating Report of 2007 Project stage: Request ML0813008092008-05-22022 May 2008 Request for Additional Information, Renewal of Active or Expired N-Type Certificates for Plants Project stage: RAI ML0814901102008-05-28028 May 2008 Status of Generic Communications for Review (Tac No. MD8314) Project stage: Other ML0814901182008-05-28028 May 2008 NRC Review: Generic Communications Status for TVA Watts Bar Unit 2 Project stage: Other ML0817002932008-06-16016 June 2008 Response to Additional Information Request on Regulatory Framework for the Completion of Construction and Licensing, Revision 1 Project stage: Other ML0818504592008-07-0202 July 2008 Response to Request for Additional Information Project stage: Response to RAI ML0818504602008-07-0202 July 2008 Final Supplemental Environmental Impact Statement - Request for Additional Information Project stage: Supplement ML0821402382008-07-29029 July 2008 Generic Communications Status, Revision 1 Project stage: Other ML0824100882008-08-25025 August 2008 Westinghouse Eagle-21 Process Protection System Project stage: Other ML0827500192008-09-26026 September 2008 Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2 - Corrective Action and Special Programs, and Unresolved Safety Issues Project stage: Other ML0825603732008-10-0202 October 2008 Request for Relief Regarding Alternative Rules for Renewal of Active or Expired N-Type Certificates Project stage: Other ML0834601772008-12-0909 December 2008 Unit 2 - Licensing Basis Preservation and Construction Refurbishment Program for Structures, Systems and Components (Sscs) Project stage: Other ML0904804862009-02-23023 February 2009 TVA December 11, 2008 - Public MtgR1 Project stage: Other ML0904804362009-02-23023 February 2009 Summary of December 11, 2008, Meeting with Tennessee Valley Authority on Status of Construction and Licensing Activities Project stage: Meeting ML0904804662009-02-23023 February 2009 NRR - Public Meeting WBN2 Status 12-11-08 Project stage: Meeting ML0904804712009-02-23023 February 2009 Region II - December 2008 Public Meeting with Notes Project stage: Meeting ML1001204872009-11-12012 November 2009 Application for Special Nuclear Material License in Accordance with 10 CFR 70, Domestic Licensing of Special Nuclear Material Project stage: Request ML1001916842010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 3 - Design of Structures, Components, Equipment, and Systems, Page 3.8.5-1 Through Page 3.11-9 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1012002042010-04-20020 April 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1012604692010-04-29029 April 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 2, and Status of Generic Communications for Unit 2 - Revision 2 Project stage: Other ML1016805612010-06-17017 June 2010 Preservice Inspection Program Plan and Additional Information Project stage: Other ML1019402362010-06-18018 June 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1017602222010-06-25025 June 2010 Request to Use ASME Boiler and Pressure Vessel Code, Code Case N-520-3, Alternative Rules for Renewal of Active or Expired N-Type Certificates for Plants Not in Active Construction, Section III, Division 1 Project stage: Other ML1021700772010-07-30030 July 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 3, and Status of Generic Communications for Unit 2 - Revision 3 Project stage: Other ML1022902582010-07-31031 July 2010 Final Safety Analysis Report - Response to Preliminary Requests for Additional Information and Requests for Additional Information Project stage: Other ML1025001712010-09-0101 September 2010 OL - TVA Letter to NRC - WBN U2 FSAR A100 Project stage: Request ML1027005272010-09-29029 September 2010 Request for Relief Regarding Alternative Rules for Renewal of Active or Expired N-Type Certification Project stage: Other ML1030102992010-10-28028 October 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 4, and Status of Generic Communications for Unit 2 - Revision 4 Project stage: Other ML1031207112010-10-29029 October 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1031207122010-10-29029 October 2010 Edcr 52321 Draft Scope and Intent, Unit Difference and Technical Evaluation, Enclosure 2, Attachment 1 Project stage: Request ML1031403142010-11-0101 November 2010 OL - TVA Letter to NRC_10-29-10_WBN U2 FSAR 101 Project stage: Request ML1032001462010-11-0909 November 2010 Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information Project stage: Response to RAI ML1032106442010-11-17017 November 2010 Revision of Commitment for Implementation of the Maintenance Rule Project stage: Request ML1035405602010-12-17017 December 2010 Safety Evaluation Report Supplement 22 (SSER22) - Response to Requests for Additional Information Project stage: Supplement ML1102104862011-01-21021 January 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 5 and Status of Generic Communications for Unit 2 - Revision 5 Project stage: Other ML1106202192011-02-25025 February 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML1110500092011-04-0808 April 2011 OL - FW: Updated OI List Project stage: Request ML11136A0532011-04-18018 April 2011 OL - TVA Letter to NRC_04-15-11_I&C RAI Response Project stage: Request ML11129A2052011-05-0606 May 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML11178A1552011-06-0303 June 2011 Final Safety Analysis Report (Fsar), Amendment 104 Project stage: Request 2010-10-28 |
ML103210644 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 11/17/2010 |
From: | Bajestani M Tennessee Valley Authority |
To: | Office of Nuclear Reactor Regulation, Document Control Desk |
References | |
Download: ML103210644 (2) | |
Similar Documents at Watts Bar | |
---|---|
Category:Letter
MONTHYEARML23319A2452024-01-29029 January 2024
[Table view]Issuance of Amendment Nos. 366 and 360; 164 and 71 Regarding the Adoption of TSTF-567, Revision 1, Add Containment Sump TS to Address GSI-191 Issues ML24008A2462024-01-18018 January 2024 Revision to the Reactor Vessel Material Surveillance Capsule Withdrawal Schedule CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-24-016, Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-01-10010 January 2024 Supplement to Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability2024-01-0909 January 2024 Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability CNL-23-062, Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018)2024-01-0808 January 2024 Application to Revise the Technical Specifications Section 3.8.2, AC Sources-Shutdown, to Remove Reference to the C-S Diesel Generator (WBN-TS-23-018) ML23346A1382024-01-0303 January 2024 Regulatory Audit Summary Related to Request to Increase the Number of Tritium Producing Burnable Absorber Rods CNL-23-069, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-21021 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000390/20234412023-12-21021 December 2023 Plantfinal Significance Determination for a Security-Related Greater than Green Finding, Nov, and Assessment Follow-up, 05000390-2023441 and 05000391-2023441-Public CNL-23-036, Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08)2023-12-18018 December 2023 Application to Revise Function 5 of Technical Specification Table 3.3.2-1, Engineered Safety Feature Actuation System Instrumentation, for the Sequoyah Nuclear Plant and Watts Bar Nuclear Plant (SQN-TS-23-02 and WBN-TS-23-08) IR 05000390/20234042023-12-14014 December 2023 Security Baseline Inspection Report 05000390/2023404 and 05000391/2023404 CNL-23-001, Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01)2023-12-13013 December 2023 Rebaseline of Sections 3.1 and 3.2 of the Technical Specifications (WBN-TS-23-01) ML23293A0572023-12-0606 December 2023 Issuance of Amendment Nos. 163 and 70 Regarding Adoption of TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control IR 05000390/20230102023-11-30030 November 2023 RE-Issue Watts Bar Nuclear Plant - Biennial Problem Identification and Resolution Inspection Report 050000390/2023010 and 05000391/2023010 and Apparent Violation CNL-23-067, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-11-27027 November 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20230032023-11-13013 November 2023 Integrated Inspection Report 05000390/2023003 and 05000391/2023003 and Apparent Violation ML23312A1432023-11-0808 November 2023 Submittal of Dual Unit Updated Final Safety Analysis Report (UFSAR) Amendment 5 CNL-23-059, Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-2023-09-20020 September 2023 Supplement to Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 CNL-23-061, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-09-20020 September 2023 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision ML23251A2002023-09-11011 September 2023 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Units 1 and 2 CNL-23-057, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 642023-09-0505 September 2023 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions. Includes CECC-EPIP-1, Revision 76 and CECC-EPIP-9, Revision 64 IR 05000390/20230052023-08-30030 August 2023 Updated Inspection Plan for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390/2023005 and 05000391/2023005 ML23233A0042023-08-28028 August 2023 Proposed Alternative to the Requirements of the ASME Boiler and Pressure Vessel Code for Upper Head Injection Dissimilar Metal Butt Welds IR 05000390/20230022023-08-16016 August 2023 Reissue - Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2023002 and 05000391/2023002 ML23220A1582023-08-0909 August 2023 Integrated Inspection Report 05000390/2023002 and 05000391/2023002 CNL-23-045, License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010)2023-08-0707 August 2023 License Amendment Request to Revise Technical Specification Table 1.1-1 Regarding the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts (WBN-TS-23-010) CNL-23-028, Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06)2023-08-0202 August 2023 Application to Revise Technical Specifications to Adopt TSTF-567-A, Revision 1, Add Containment Sump TS to Address GSI-191 Issues (SQN-TS-23-03 and WBN-TS-23-06) ML23192A4472023-07-31031 July 2023 Staff Assessment of Updated Seismic Hazards at TVA Sites Following the NRC Process for the Ongoing Assessment of Natural Hazards Information CNL-23-055, Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills2023-07-25025 July 2023 Tennessee Valley Authority - Emergency Preparedness Department Procedure Revision. Includes EPDP-3, Revision 3, Emergency Plan Exercises and Preparedness Drills IR 05000390/20230112023-07-24024 July 2023 Quadrennial Focused Engineering Inspection (FEI) Commercial Grade Dedication Report 05000390 2023011 and 05000391 2023011 CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-020, Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06)2023-06-28028 June 2023 Application to Revise Technical Specifications to Adopt TSTF-501-A, Revision 1, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control (WBN-TS-22-06) CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . ML23122A2322023-06-0707 June 2023 Issuance of Amendment Nos. 162 and 69 Regarding Change to Date in Footnotes for Technical Specification 3.7.11, Control Room Emergency Air Temperature Control System (Creatcs) CNL-23-044, Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out2023-06-0101 June 2023 Transmittal of Revision 3 to WCAP-18774-P and WCAP-18774-NP, Addendum to the Rotterdam Dockyard Company Final Stress Report for 173 P.W.R. Vessels TVA III & IV (Report No. 30749-B-030, Rev. 3) - Evaluation of One Closure Stud Out IR 05000390/20234032023-05-30030 May 2023 Cyber Security Inspection Report 05000390/2023403 and 05000391/2023403 ML23131A1812023-05-23023 May 2023 Correction to Amendment No. 161 to Facility Operating License No. NPF-90 CNL-23-042, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-05-16016 May 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20220032023-05-0909 May 2023 Reissue Watts Bar Nuclear Plant - Integrated Inspection Report 05000390/2022003 and 05000391/2022003 ML23125A2202023-05-0505 May 2023 Issuance of Amendment No. 161 Regarding a Change to Footnotes for Technical Specification Table 1.1-1 Modes (Emergency Circumstances) IR 05000390/20230012023-05-0404 May 2023 Integrated Inspection Report 05000390/2023001 and 05000391/2023001 CNL-23-043, Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09)2023-05-0404 May 2023 Emergency License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical Specification Table 1.1-1, Modes (WBN-TS-23-09) CNL-23-032, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 412023-04-27027 April 2023 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 41 CNL-23-030, Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update2023-04-27027 April 2023 Tennessee Valley Authority - Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-23-033, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2023-04-24024 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-23-029, Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2023-04-11011 April 2023 Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML23072A0652023-04-0505 April 2023 Units 1 and 2 Issuance of Amendment Nos. 364 and 358; 160 and 68 Regarding a Revision to Technical Specification 3.4.12 ML23073A2762023-04-0303 April 2023 Individual Notice of Consideration of Issuance of Amendments to Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing (EPID L-2023-LLA-0029) (Letter) CNL-23-023, Annual Insurance Status Report2023-03-30030 March 2023 Annual Insurance Status Report CNL-23-024, TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report2023-03-29029 March 2023 TVA Guarantee of Payment of Deferred Premiums - 2022 Annual Report 2024-01-09 |
Text
Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 November 17, 2010 u.s. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Subject:
Watts Bar Nuclear Plant (WBN) Unit 2 - Revision of Commitment for Unit 2's Implementation of the Maintenance Rule
Reference:
Unit 2 - Regulatory Framework for the Completion of Construction and Licensing Activities for Unit 2" (ADAMS Accession No ML ML080320443)
Item 115 of Enclosure 2 of Reference 1 contained the following commitment: "Implement Maintenance Rule for Unit 2 systems 1 month prior to fuel load."
This letter revises this commitment to read "Implement Maintenance Rule for Unit 2 systems by October 31,2011."
If you have any questions, please contact Bill Crouch at (423) 365-2004.
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 171h day of November, 2010.
Sincerely, M *73OL Masoud j stani Watts B r nit 2 Vice President
U.S. Nuclear Regulatory Commission Page 2 November 17, 2010 cc: U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381