TAC:MD6311, Clarify Application of Setpoint Methodology for LSSS Functions, Control Room Habitability, Steam Generator Tube Integrity (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement
Results
Other: CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12, CNL-15-137, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 13, ML080860026, ML080860040, ML081700293, ML082410088, ML083460177, ML090480486, ML101260469, ML102170077, ML102290258, ML103010299, ML11213A130, ML11362A056, ML12234A688, ML13023A315, ML13213A194
|
MONTHYEARML0732401242007-11-26026 November 2007 Summary of Meeting with Tennessee Valley Authority on Use of Eagle 21 at Watts Bar Unit 2 Project stage: Meeting ML0734400222007-12-0505 December 2007 Westinghouse Eagle - 21 Process Protection System Project stage: Request ML0801705432008-01-0303 January 2008 Summary of December 12, 2007, Meeting with Tennessee Valley Authority on Reconstruction of the Licensing Basis for Watts Bar Unit 2 Project stage: Meeting ML0735209712008-01-0303 January 2008 Summary of Meeting with Tennessee Valley Authority on Reconstitution of the Licensing Basis for Watts Bar, Unit 2 Project stage: Meeting ML0812105062008-05-0707 May 2008 Request for Additional Information Regarding Eagle-21 Process Protection System (Tac No. MD6311) Project stage: RAI ML0810101162008-05-0808 May 2008 Review Topics for Safety Evaluation, Attachment 1 Project stage: Approval ML0808600402008-05-0808 May 2008 Enclosure 1- Watts Bar Nuclear Plant, Unit 2 - Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0808600262008-05-0808 May 2008 Assessment of Remaining Operating License Application Review Scope Project stage: Other ML0814300282008-05-14014 May 2008 Transmittal of Annual Radiological Environmental Operating Report of 2007 Project stage: Request ML0817002932008-06-16016 June 2008 Response to Additional Information Request on Regulatory Framework for the Completion of Construction and Licensing, Revision 1 Project stage: Other ML0818504602008-07-0202 July 2008 Final Supplemental Environmental Impact Statement - Request for Additional Information Project stage: Supplement ML0824100882008-08-25025 August 2008 Westinghouse Eagle-21 Process Protection System Project stage: Other ML0834601772008-12-0909 December 2008 Unit 2 - Licensing Basis Preservation and Construction Refurbishment Program for Structures, Systems and Components (Sscs) Project stage: Other ML0904804862009-02-23023 February 2009 TVA December 11, 2008 - Public MtgR1 Project stage: Other ML0904804712009-02-23023 February 2009 Region II - December 2008 Public Meeting with Notes Project stage: Meeting ML0904804662009-02-23023 February 2009 NRR - Public Meeting WBN2 Status 12-11-08 Project stage: Meeting ML0904804362009-02-23023 February 2009 Summary of December 11, 2008, Meeting with Tennessee Valley Authority on Status of Construction and Licensing Activities Project stage: Meeting ML1001204872009-11-12012 November 2009 Application for Special Nuclear Material License in Accordance with 10 CFR 70, Domestic Licensing of Special Nuclear Material Project stage: Request ML1001916842010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97, Section 3 - Design of Structures, Components, Equipment, and Systems, Page 3.8.5-1 Through Page 3.11-9 Project stage: Request ML1001914212010-01-11011 January 2010 Final Safety Analysis Report, Amendment 97 Project stage: Request ML1012604692010-04-29029 April 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 2, and Status of Generic Communications for Unit 2 - Revision 2 Project stage: Other ML1019402362010-06-18018 June 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1021700772010-07-30030 July 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 3, and Status of Generic Communications for Unit 2 - Revision 3 Project stage: Other ML1022902582010-07-31031 July 2010 Final Safety Analysis Report - Response to Preliminary Requests for Additional Information and Requests for Additional Information Project stage: Other ML1030102992010-10-28028 October 2010 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 4, and Status of Generic Communications for Unit 2 - Revision 4 Project stage: Other ML1031207112010-10-29029 October 2010 Instrumentation and Controls Staff Information Requests Project stage: Request ML1031207122010-10-29029 October 2010 Edcr 52321 Draft Scope and Intent, Unit Difference and Technical Evaluation, Enclosure 2, Attachment 1 Project stage: Request ML1031403142010-11-0101 November 2010 OL - TVA Letter to NRC_10-29-10_WBN U2 FSAR 101 Project stage: Request ML1032001462010-11-0909 November 2010 Final Safety Analysis Report (FSAR) - Response to Requests for Additional Information Project stage: Response to RAI ML1032106442010-11-17017 November 2010 Revision of Commitment for Implementation of the Maintenance Rule Project stage: Request ML1035405602010-12-17017 December 2010 Safety Evaluation Report Supplement 22 (SSER22) - Response to Requests for Additional Information Project stage: Supplement ML1106202192011-02-25025 February 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML1110500092011-04-0808 April 2011 OL - FW: Updated OI List Project stage: Request ML11136A0532011-04-18018 April 2011 OL - TVA Letter to NRC_04-15-11_I&C RAI Response Project stage: Request ML11129A2052011-05-0606 May 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML11178A1552011-06-0303 June 2011 Final Safety Analysis Report (Fsar), Amendment 104 Project stage: Request ML11167A1102011-06-10010 June 2011 Instrumentation and Controls Staff Information Requests Project stage: Request ML11213A1302011-07-27027 July 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 6 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 6 Project stage: Other ML11213A2612011-07-28028 July 2011 Results from Cost-Benefit Analysis of Radwaste System Enhancements Project stage: Request ML11292A1992011-10-17017 October 2011 Revision of Commitment for Unit 2's Implementation of the Maintenance Rule Project stage: Request ML11362A0562011-12-20020 December 2011 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 7 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 7 Project stage: Other ML12234A6882012-08-15015 August 2012 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 8 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 8 Project stage: Other ML12249A1952012-08-30030 August 2012 Instrumentation and Controls Staff Request for Additional Information (RAI) Related to Supplemental Safety Evaluation Report (Sser) Open Item 80 Project stage: Supplement ML12284A5132012-10-0404 October 2012 NRC Bulletin No. 88-08, Thermal Stresses in Piping Connected to Reactor Coolant System (RCS) - Clarification Project stage: Request ML12284A5142012-10-0404 October 2012 Revision of Commitment for Unit 2's Implementation of the Maintenance Rule Project stage: Request ML12312A1672012-10-25025 October 2012 Unit 1 & 2, Watts Bar, Units 1 & 2, 90-Day Response to NRC Bulletin 2012-01, Design Vulnerability in Electric Power System. Project stage: Request ML12349A3792012-12-10010 December 2012 Instrumentation and Controls Staff Request for Additional Information (RAI) Related to Supplemental Safety Evaluation Report (Sser) Open Item 80 Project stage: Supplement ML13023A3152013-01-17017 January 2013 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 9 (TAC No. MD6311), and Status of Generic Communications for Unit 2 -Revision 9 Project stage: Other ML13030A0322013-01-24024 January 2013 Documentation of Liability Insurance Coverage Requested Per Supplemental Safety Evaluation Report (Sser) Open Item 25 Project stage: Request ML13213A1942013-07-25025 July 2013 Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 10 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 10 Project stage: Other 2010-06-18
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000390/20250102024-11-0404 November 2024 Notification of an NRC (FPTI) (NRC Inspection Report 05000390/2025010 0500039/ 2025010) (RFI) CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000390/20243012024-10-17017 October 2024 Operator Licensing Examination Approval 05000390/2024301 and 05000391/2024301 ML24282B0412024-10-15015 October 2024 Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2 and Watts Bar Nuclear Plant, Units 1 and 2 ML24260A1682024-10-0404 October 2024 Regulatory Audit Summary Related to Request to Add and Revise Notes Related to Technical Specification Table 3.3.2-1, Function 5 ML24261C0062024-10-0404 October 2024 Correction to Amendment No. 134 to Facility Operating License No. NPF-90 and Amendment No. 38 to Facility Operating License No. NPF-96 ML24284A1072024-09-26026 September 2024 Affidavit for Request for Withholding Information from Public Disclosure for Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description CNL-24-047, Decommitment of Flood Mode Mitigation Improvement Systems2024-09-24024 September 2024 Decommitment of Flood Mode Mitigation Improvement Systems ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000390/LER-2024-002, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-09-0505 September 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation IR 05000390/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Watts Bar Nuclear Plant, Units 1 and 2 - Report 05000390-2024005 and 05000391-2024005 ML24218A1442024-08-27027 August 2024 Issuance of Amendment Nos. 169 and 75 Regarding Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate IR 05000390/20244022024-08-20020 August 2024 – Security Baseline Inspection Report 05000390-2024402 and 05000391/2024402 - Public CNL-24-061, Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08),2024-08-19019 August 2024 Supplement to Application to Revise Function 5 of Technical Specification Table 3.3.2-1, ‘Engineered Safety Feature Actuation System Instrumentation,’ for the Sequoyah and Watts Bar (SQN-TS-23-02 and WBN-TS-23-08), ML24219A0262024-08-12012 August 2024 Request for Withholding Information from Public Disclosure IR 05000390/20240022024-08-0707 August 2024 Integrated Inspection Report 05000390/2024002 and 05000391/2024002 Rev ML24204A2652024-07-25025 July 2024 Regulatory Audit Summary Related to Request to Revise Technical Specification Surveillance Requirement 3.9.5.1 to Reduce the Residual Heat Removal Flow Rate ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24170A8002024-07-15015 July 2024 Issuance of Amendment Nos. 168 and 74 Regarding Revision to Technical Specification Table 1.1-1 for Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Bolts ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter IR 05000390/20244402024-07-12012 July 2024 95001 Supplemental Inspection Supplemental Report 05000390-2024440 and 05000391-2024440 and Follow-Up Assessment Letter 05000391/LER-2024-003, Inoperability of Both Trains of Unit 2 Low Head Safety Injection2024-07-11011 July 2024 Inoperability of Both Trains of Unit 2 Low Head Safety Injection ML24131A0012024-07-0202 July 2024 Issuance of Amendment Nos. 167 and 73 Regarding Adoption of Technical Specification Task Force Traveler TSTF-427-A, Revision 2 CNL-24-052, Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14)2024-06-27027 June 2024 Response to Request for Additional Information Regarding Application to Modify the Technical Specification Surveillance Requirement 3.9.5.1 (WBN-TS-21-14) CNL-24-018, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS2024-06-25025 June 2024 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A, Revision 2, Regarding TS 3.8.1 AC Sources – Operating to Clarify Requirements for Diesel Generator Testing (WBN-TS ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24100A7642024-05-16016 May 2024 Issuance of Amendment No. 166 Regarding Revision to Technical Specification 3.8.2, AC Sources-Shutdown, to Remove Reference to C-S Diesel Generator (CNL-23-062) IR 05000390/20240012024-05-14014 May 2024 Integrated Inspection Report 05000390/2024001 and 05000391/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions 05000391/LER-2024-002, Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO2024-05-0606 May 2024 Re Automatic Reactor Trip Due to Steam Generator 3 Level LO-LO IR 05000391/20240072024-04-30030 April 2024 Assessment Follow-up Letter for Watts Bar Nuclear Plant, Unit 2 – Report 05000391/2024007 ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information CNL-24-037, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 422024-04-22022 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Unit 1 and 2, Nuclear Quality Assurance Plan, TVA-NQA-PLN89-A, Revision 42 ML24087A1912024-04-18018 April 2024 Exemption from Select Requirements of 10 CFR Part 73, Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting CNL-24-024, Hydrologic Engineering Center River Analysis System Project Milestone Status Update2024-04-17017 April 2024 Hydrologic Engineering Center River Analysis System Project Milestone Status Update CNL-24-010, License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19)2024-04-17017 April 2024 License Amendment Request to Recapture Low-Power Testing Time (WBN-TS-23-19) CNL-24-033, Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-04-17017 April 2024 Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24072A0052024-04-15015 April 2024 Issuance of Amendment Nos. 165 and 72 Regarding Increase in the Maximum Number of Tritium Producing Burnable Absorber Rods and Supporting Changes, and Revision to the Updated Final Safety Analysis Report CNL-24-004, Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13)2024-04-0404 April 2024 Application to Modify the Watts Bar Nuclear Plant, Unit 1 and Unit 2 Technical Specifications for Main Control Room Chiller Completion Time Extension (WBN-TS-23-13) IR 05000390/20244012024-04-0202 April 2024 – Security Baseline Inspection Report 05000390/2024401 and 05000391/2024401 - (Public) CNL-24-020, Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements2024-04-0101 April 2024 Clinch River, Sequoyah, Units 1 and 2, Watts Bar, Units 1 and 2, Request for Approval of Quality Assurance Program Description and Application to Revise the Technical Specifications Associated with QAPD Requirements 05000391/LER-2024-001, Automatic Reactor Trip Due to Main Generator Protection Relay Actuation2024-03-27027 March 2024 Automatic Reactor Trip Due to Main Generator Protection Relay Actuation CNL-24-007, Annual Insurance Status Report2024-03-27027 March 2024 Annual Insurance Status Report CNL-24-008, Guarantee of Payment of Deferred Premiums - 2023 Annual Report2024-03-27027 March 2024 Guarantee of Payment of Deferred Premiums - 2023 Annual Report CNL-24-025, Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule2024-03-25025 March 2024 Notice of Intent to Pursue License Renewal for Watts Bar Nuclear Plant, Unit 1 - Submittal Schedule ML24081A0262024-03-21021 March 2024 Emergency Plan Implementing Procedure Revisions ML24079A0312024-03-19019 March 2024 Wb 2024-301, Corporate Notification Letter (210-day Ltr) 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24309A0552024-11-0101 November 2024 NRR E-mail Capture - Request for Additional Information - TVA LAR to Revised Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2 Re TS Table 3.3.2-1, Function 5 ML24304A3752024-10-29029 October 2024 NRR E-mail Capture - Request for Additional Information - License Amendment Request (LAR) to Revise Watts Bar Updated Final Safety Analysis Report (UFSAR) for Hydrologic Analysis ML24260A0322024-09-10010 September 2024 NRR E-mail Capture - Request for Additional Information Regarding the Watts Bar Unit 2 Steam Generator Tube Inspection Report for U2R5 ML24155A1372024-05-29029 May 2024 Email from K. Green to S. Hughes Request for Additional Information Related to License Amendment Request to Revise Residual Heat Removal Flow Rate ML24120A1182024-04-29029 April 2024 – Notification of NRC Supplemental Inspection (95001) and Request for Information ML24116A2012024-04-17017 April 2024 Nrctva ISFSI CBS (RFI) ML24045A0312024-02-14014 February 2024 NRR E-mail Capture - Request for Additional Information Related to the Exemption Request for the 10 CFR Part 73 Enhanced Weapons Rule ML23166A1142023-06-15015 June 2023 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2023-03 ML23067A2372023-03-0808 March 2023 WB_2023-02_RP_inspection_doc_request ML23030A3512023-01-25025 January 2023 Notification of Watts Bar Nuclear Plant - Design Bases Assurance Inspection (Programs) and Initial Information Request ML22343A0692022-12-0808 December 2022 NRR E-mail Capture - Request for Additional Information - Sequoyah Nuclear Plant, Units 1 and 2, and Watts Bar Nuclear Plant, Units 1 and 2, License Amendment Request to Revise Technical Specification 3.4.12 (L-2022-LLA-0103) ML22227A0272022-08-11011 August 2022 NRR E-mail Capture - Request for Additional Information Related to Alternative Requests RP-11 for Sequoyah Nuclear Plant, Units 1 and 2, and IST-RR-9 for Watts Bar Nuclear Plant, Units 1 and 2 ML22144A1002022-05-12012 May 2022 NRR E-mail Capture - Request for Additional Information Related to TVAs Request to Revised the TVA Plants Radiological Emergency Plans ML22115A1402022-04-25025 April 2022 NRR E-mail Capture - Requests for Confirmation of Information and Additional Information Regarding Watts Bar Nuclear Plant, Unit 2 Exemption Request Re 10 CFR Part 26 (L-2022-LLE-0017) ML22083A2372022-03-24024 March 2022 NRR E-mail Capture - Request for Additional Information and Confirmation of Information Related to TVAs Request for Changes to Watts Bar Nuclear Plant, Units 1 and 2, Technical Specification 3.7.8 ML22056A3802022-02-25025 February 2022 Document Request for Watts Bar Nuclear Plant - Radiation Protection Inspection - Inspection Report 2022-02 ML21267A1392021-09-23023 September 2021 Document Request for Upcoming RP Inspection at Watts Bar ML21221A2602021-08-0909 August 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Watts Bar, Unit 1 Tech Specs Related to Continuous Opening of the Auxiliary Building Secondary Containment Enclosure Boundary ML21102A1312021-04-19019 April 2021 Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 ML21095A0422021-04-0202 April 2021 NRR E-mail Capture - Added Clarification to RAI 2 for Thot LAR ML21095A0402021-04-0202 April 2021 NRR E-mail Capture - Request for Additional Information Re Generic Letter 95-05 90-Day Report and LAR to Adjust Growth Rate for Thot (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21091A0772021-04-0101 April 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise Technical Specification 5.7.2.19, Containment Leakage Rate Testing Program ML21095A0412021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0442021-04-0101 April 2021 NRR E-mail Capture - Revised Draft RAI - Combined RAI Set for Watts Bar Unit 2 90-Day Report and Thot LAR (EPIDs L-2021-LRO-0003 and L-2021-LLA-0026) ML21095A0462021-03-22022 March 2021 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Generic Letter 95-05 90-Day Report for Watts Bar Unit 2 ML21039A6402021-02-0808 February 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar Nuclear Plant, Unit 1 Technical Specifications Related to Steam Generator Tube Inspection Frequency ML21012A2032021-01-11011 January 2021 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise the Watts Bar UFSAR to Use Alternate Probability of Detection ML20350B5592020-12-15015 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Adopt Traveler TSTF-490 Deletion of E Bar Definition and Revision to RCS Specific Activity Tech Spec ML20338A3202020-12-0303 December 2020 Notification of an NRC Fire Protection Team Inspection (NRC Inspection Report 05000390/2021011 and 05000391/2021011) and Request for Information ML20322A4412020-11-17017 November 2020 NRR E-mail Capture - Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20322A4392020-11-0505 November 2020 NRR E-mail Capture - Draft Request for Additional Information Regarding Tva'S Request to Revise TS 3.7.11 Related to the MCR Chiller Replacement ML20308A3512020-11-0202 November 2020 Request for Additional Information on WBN Request for Exemption from 10 CFR Part 73, Appendix B, Section VI for the Conduct of an Annual Force-on-Force Exercise (EPID L-2020-LLE-0165 (COVID-19)) ML20253A1782020-09-0909 September 2020 Emergency Preparedness Program Inspection Request for Information ML20266G4592020-08-14014 August 2020 Notification of Inspection and Request for Information ML20196L8622020-07-14014 July 2020 NRR E-mail Capture - Watts Bar Nuclear Plant, Units 1 and 2 - Request for Additional Information Regarding Request to Implement the Full Spectrum LOCA Methodology ML20086G4802020-03-26026 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) - Part 2 ML20085G3572020-03-25025 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20084M1942020-03-24024 March 2020 NRR E-mail Capture - Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML20083J3952020-03-12012 March 2020 NRR E-mail Capture - Draft Request for Additional Information for WBN2 Request Measurement Uncertainty Recapture Power Uprate (L-2019-LLS-0000) ML19340A6842019-12-0505 December 2019 NRR E-mail Capture - Request for Additional Information for WBN2 Request for One-Time Extension of Completion Time for TS 3.7.8 (L-2019-LLA-0020) ML19218A0302019-08-0505 August 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19218A0282019-07-25025 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Draft Second-Round Request for Additional Information Related to Application to Revise Technical Specifications Regarding DC Electrical Systems, TSTF-500, Revision 2 ML19186A4352019-07-0505 July 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Correction to Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19169A3592019-06-18018 June 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Application to Adopt 10 CFR 50.69 ML19148A7912019-05-28028 May 2019 NRR E-mail Capture - Sequoyah Nuclear Plant and Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request for Alternative to OM Code Requirements ML19106A0462019-04-15015 April 2019 NRR E-mail Capture - Watts BAR, Units 1 and 2 Request for Additional Informatin (RAI) Regarding Changes to Technical Specifications Sections 3.8.1, 3.8.7, 3.8.8, and 3.8.9 ML19071A3542019-03-0808 March 2019 NRR E-mail Capture - Watts Bar Nuclear Plant - Final Request for Additional Information Related to Request to Adopt TSTF-425 to Relocate Specific Surveillance Frequency Requirements to Licensee-Controlled Program ML18313A2202018-11-0707 November 2018 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML18282A6372018-10-0909 October 2018 NRR E-mail Capture - RAIs (Final) - LAR to Revise the Steam Generator Technical Specifications for Watts Bar Nuclear Plant, Unit 2 ML18270A2362018-09-26026 September 2018 NRR E-mail Capture - Watts Bar Units 1 and 2 RAIs - Modify TS 3.8.9 Completion Time for Inoperable 120V AC Vital Buses (L-2018-LLA-0050) 2024-09-10
[Table view] |
Text
May 7, 2008 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
WATTS BAR NUCLEAR PLANT UNIT 2 - LICENSING BASIS REGARDING EAGLE-21 PROCESS PROTECTION SYSTEM (TAC NO. MD6311)
Dear Mr. Bhatnagar:
In a letter dated August 3, 2007, the Tennessee Valley Authority (TVA) notified the Nuclear Regulatory Commission (NRC) of its intent to resume licensing and construction of Watts Bar Nuclear Plant (WBN) Unit 2. The letter was submitted in accordance with the Commissions Policy Statement on Deferred Plants, dated October 14, 1987 (52 FR 38077).
In a Staff Requirements Memorandum dated July 25, 2007, the Commission had previously informed the NRC staff that it supported a licensing review approach that would employ the current licensing basis for WBN Unit 1 as the reference basis for the review and licensing of Unit 2.
By letter dated December 5, 2007, TVA informed the NRC of its intent to use of the Westinghouse Electric Corporation Eagle-21 process protection system at WBN Unit 2. In a letter dated February 28, 2008, TVA had responded to a request for additional information dated December 27, 2007.
TVA has indicated that the Eagle-21 system will be built to the same specifications as used for the system installed at WBN Unit 1 and that the hardware would be identical or equivalent and the safety-related firmware would be identical. TVA and Westinghouse did identify that certain hardware changes would be needed because of obsolescence and vendor supply changes. On the basis of the NRC staffs prior approval of the Eagle-21 system at Unit 1, the reliable performance at Unit 1 and other nuclear plants, and the need to maintain the licensing approach for the reference basis for Unit 2, the NRC staff recognizes TVAs intent to incorporate the Eagle-21 process protection system into the WBN 2 design and licensing basis. NRC staff approval will be predicated on the satisfactory evaluation of an application that presents the applicable design bases and safety analyses.
After reviewing these letters, the NRC staff has determined that further information would be needed to ensure a sufficiently complete application for staff review when TVA references the
A. Bhatnagar use of the Eagle 21 system in an application. The details of the specific issues are provided in the enclosure to this letter. TVA should ensure that these items are adequately addressed and incorporated, as necessary, into a future amendment application for WBN Unit 2.
If you should have any questions, please contact me at 301-415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
Request for Additional Information cc w/encl: See next page
A. Bhatnagar use of the Eagle 21 system in an application. The details of the specific issues are provided in the enclosure to this letter. TVA should ensure that these items are adequately addressed and incorporated, as necessary, into a future amendment application for WBN Unit 2.
If you should have any questions, please contact me at 301-415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-391
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION:
PUBLIC RidsNrrPMPMilano H. Garg, NRR RidsAcrsAcnw&mMailCenter WBSPB R/F RidsNrrLABClayton RidsOgcRp RidsNrrDorlDpr RidsNrrDorlWbspb RidsNrrDeEicb RidRgn2MailCenter ADAMS Accession Number: ML081210506 OFFICE WBSPB/PM WBSPB/LA EICB/BC WBSPB/BC NAME PMilano BClayton WKemper LRaghavan (by memo dated)
DATE 05/ 07 /08 05/ 07 /08 03/27/08 05/ 07 /08 OFFICIAL RECORD COPY
Ashok S. Bhatnagar Tennessee Valley Authority WATTS BAR NUCLEAR PLANT UNIT 2 cc:
Mr. Gordon P. Arent General Counsel New Generation Licensing Manager Tennessee Valley Authority Tennessee Valley Authority 6A West Tower 5A Lookout Place 400 West Summit Hill Drive 1101 Market Street Knoxville, TN 37902 Chattanooga, TN 37402-2801 Mr. Michael J. Lorek, Plant Manager Senior Resident Inspector Watts Bar Nuclear Plant Watts Bar Nuclear Plant Tennessee Valley Authority U.S. Nuclear Regulatory Commission P.O. Box 2000 1260 Nuclear Plant Road Spring City, TN 37381 Spring City, TN 37381 Mr. Lawrence E. Nanney, Director Mr. Michael K. Brandon, Manager Tennessee Dept. of Environmental Health Licensing and Industry Affairs & Conservation Watts Bar Nuclear Plant Division of Radiological Health Tennessee Valley Authority 3rd Floor, L&C Annex P.O. Box 2000 401 Church Street Spring City, TN 37381 Nashville, TN 37243-1532 Mr. William R. Campbell, Jr. Mr. Larry E. Nicholson, General Manager Chief Nuclear Officer and Performance Improvement Executive Vice President Tennessee Valley Authority Tennessee Valley Authority 3R Lookout Place 3R Lookout Place 1101 Market Street 1101 Market Street Chattanooga, TN 37402-2801 Chattanooga, TN 37402-2801 Mr. Masoud Bajestani, Vice President County Executive Watts Bar Unit 2 375 Church Street Watts Bar Nuclear Plant Suite 215 Tennessee Valley Authority Dayton, TN 37321 P.O. Box 2000 Spring City, TN 37381 County Mayor P. O. Box 156 Ms. Ann P. Harris Decatur, TN 37322 341 Swing Loop Road Rockwood, TN 37854 Mr. John C. Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
Design Bases and Analyses Issues Related to Westinghouse Eagle-21 Process Protection System Tennessee Valley Authority Watts Bar Nuclear Plant Unit 2 Docket No. 50-391 By letter dated December 5, 2007, as supplemented on February 28, 2008 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML073440022 and ML080640269, respectively), Tennessee Valley Authority (TVA) informed the Nuclear Regulatory Commission (NRC) of its intent to use of the Westinghouse Electric Corporation Eagle-21 process protection system for Watts Bar Nuclear Plant, Unit 2 (WBN 2).
After reviewing the information presented by TVA, the NRC staff finds that the following will need to be addressed when TVA submits an amendment covering this system:
- 1. On page E1-1 of Enclosure 1 to the February 28 letter, TVA stated that an external communication interface was added that included a serial-to-ethernet controller board in each Eagle-21 multibus chassis. TVA further stated that the link is designed such that it is not possible for the nonsafety-related integrated computer system signals to feedback to the safety-related Eagle 21.
Has this addition and associated changes been tested to prove the statement? If so, provide the test procedures and test results.
- 2. On page E1-1 of Enclosure 1, TVA stated that the main control room annunciator printer was replaced with a central processing unit and a monitor as part of a prior design change.
Identify whether this modification has any impact on the defense against common mode failure, since TVAs analysis was based on manual action. Is there a possible common mode failure that could disable both the Eagle-21 and the central processing unit?
- 3. In its December 27, 2007, request for additional information (ADAMS Accession No. ML073610443), the NRC staff requested the list of commitments made by TVA for the Eagle-21 system. In its response, TVA listed four items that will remain open pending completion of these activities. However, the NRC staff has noted that in Supplement 13 of its Safety Evaluation Report for Unit 1, its acceptance was based on a TVA commitment to maintain administrative control on the use of walkie-talkie, portable telephones, and temporary equipment in areas where the use of walkie-talkies is already prohibited.
Identify any further commitments made by TVA during the acceptance of the Eagle 21 system.
Enclosure
- 4. In Item 3 of Enclosure 2, TVA states that the flow measurement uncertainty will be validated as part of the reactor protection system evaluation, which is included in the scope of the Eagle-21 installation.
Provide further details to clarify the meaning of this commitment.
- 5. On page E1-8 of Enclosure 1, TVA discusses instrument setpoint methodology. The NRC staff has had much interaction with the industry on this issue, and the staff has issued Regulatory Information Summary (RIS) 2006-17, which provides guidance on the acceptable instrument setpoint methodologies.
Provide the instrument setpoint methodology and a discussion about how the requirements RIS 2006-17 are met.
- 6. On pages 2 and 3 of Attachment 1 to Enclosure 1, hardware changes made to the Eagle-21 system after it was approved for WBN 1 were identified.
- a. Five of these changes are safety-related.
Have these hardware changes been qualified for the environment including radio frequency interference/electro-magnetic interference? Have these changes been through the hardware verification and validation program?
- b. Three changes are identified as nonsafety-related.
Have these changes been analyzed to ensure that their failure will not create any effect on the safety-related components? Provide the test reports for each of these issues.
- 7. Confirm that the scope of Eagle-21 system for WBN 2 is the same as Unit 1. Also, identify all the functions where Eagle 21 has been applied.