ML102440237
| ML102440237 | |
| Person / Time | |
|---|---|
| Site: | Surry |
| Issue date: | 09/01/2010 |
| From: | NRC/RGN-II |
| To: | Virginia Electric & Power Co (VEPCO) |
| Shared Package | |
| ML102440227 | List: |
| References | |
| Download: ML102440237 (2) | |
Text
Inspection / Activity Plan Page 1 of 2 09/01/2010 08:21:33 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Surry PSB1EP
- EMERGENCY PREPAREDNESS INSPECTION 2
1, 2 IP Alert and Notification System Testing 7111402 09/07/2010 09/11/2010 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 09/07/2010 09/11/2010 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 09/07/2010 09/11/2010 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 09/07/2010 09/11/2010 1, 2 IP Performance Indicator Verification 71151 09/07/2010 09/11/2010 EB3ISI
- UNIT 1 INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 11/01/2010 11/05/2010 EB3SGISI
- UNIT 1 SG INSERVICE INSPECTION 1
1 IP Inservice Inspection Activities - PWR 7111108P 11/01/2010 11/05/2010 PSB1-RP
- RP OCCUPATIONAL WEEK 1 2
1, 2 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 11/01/2010 11/05/2010 1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/01/2010 11/05/2010 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/01/2010 11/05/2010 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/01/2010 11/05/2010 1, 2 IP Occupational Dose Assessment 71124.04 11/01/2010 11/05/2010 1, 2 IP Radiation Monitoring Instrumentation 71124.05 11/01/2010 11/05/2010 1, 2 IP Performance Indicator Verification 71151 11/01/2010 11/05/2010 PSB1-RP
- RP OCCUPATIONAL WEEK2 3
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/15/2010 11/19/2010 1, 2 IP Occupational ALARA Planning and Controls 71124.02 11/15/2010 11/19/2010 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/15/2010 11/19/2010 1, 2 IP Occupational Dose Assessment 71124.04 11/15/2010 11/19/2010 1, 2 IP Radiation Monitoring Instrumentation 71124.05 11/15/2010 11/19/2010 1, 2 IP Performance Indicator Verification 71151 11/15/2010 11/19/2010 PSB1-TI
- TI-179 NSTS VERIFICATION 1
1, 2 IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 11/15/2010 11/19/2010 OL RQ
- REQUAL INSPECTION 3
1, 2 IP Licensed Operator Requalification Program 7111111B 01/24/2011 01/28/2011 TI-177
- TI-177 GASEOUS INTRUSION 2
1, 2 IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 03/21/2011 03/25/2011 EB3ISI
- UNIT 2 INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 04/25/2011 04/29/2011 EB3SGISI
- UNIT 2 SG INSERVICE INSPECTION 1
2 IP Inservice Inspection Activities - PWR 7111108P 04/25/2011 04/30/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Inspection / Activity Plan Page 2 of 2 09/01/2010 08:21:33 Report 22 09/01/2010 - 12/31/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Surry PI&R
- PROBLEM IDENTIFICATION AND RESOLUTION 4
1, 2 IP Identification and Resolution of Problems 71152B 06/06/2011 06/10/2011 1, 2 IP Identification and Resolution of Problems 71152B 06/20/2011 06/24/2011 EB3HS
- HEAT SINK 1
1, 2 IP Heat Sink Performance 7111107T 06/13/2011 06/17/2011 PSB1-RP
- RP PUBLIC RADIATION PROTECTION INSPT 4
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 06/13/2011 06/17/2011 1, 2 IP Occupational Dose Assessment 71124.04 06/13/2011 06/17/2011 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 06/13/2011 06/17/2011 1, 2 IP Radiological Environmental Monitoring Program 71124.07 06/13/2011 06/17/2011 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 06/13/2011 06/17/2011 1, 2 IP Performance Indicator Verification 71151 06/13/2011 06/17/2011 EB3 LR
- POST-APPROVAL INSPECTION FOR LR 5
1, 2 IP Post-Approval Site Inspection for License Renewal 71003 07/11/2011 07/15/2011 1, 2 IP Post-Approval Site Inspection for License Renewal 71003 07/25/2011 07/29/2011 PSB1EP
- EMERGENCY PREPAREDNESS EXERCISE 3
1, 2 IP Exercise Evaluation 7111401 07/18/2011 07/22/2011 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 07/18/2011 07/22/2011 1, 2 IP Performance Indicator Verification 71151 07/18/2011 07/22/2011 CDBI
- COMPONENT DESIGN BASES INSPECTION 11 1, 2 IP Component Design Bases Inspection 7111121 10/31/2011 11/04/2011 1, 2 IP Component Design Bases Inspection 7111121 11/14/2011 11/18/2011 1, 2 IP Component Design Bases Inspection 7111121 11/28/2011 12/02/2011 1, 2 IP Component Design Bases Inspection 7111121 12/12/2011 12/16/2011 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure