June 18, 2007Mr. Michael KanslerPresidentEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601
SUBJECT:
REVIEW STATUS OF THE LICENSE RENEWAL APPLICATION FOR THEINDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3
Dear Mr. Kansler:
By letter dated April 23, 2007, as supplemented by letter dated May 3, 2007, Entergy NuclearOperations, Inc. (Entergy) submitted an application for renewal of Operating Licenses Nos.DPR-26 and DPR-64 for the Indian Point Nuclear Generating Unit Nos. 2 and 3, respectively. By teleconference on June 6, 2007, U.S. Nuclear Regulatory Commission (NRC) staff informedrepresentatives from Entergy that certain information is needed for the staff to complete theacceptance review of the license renewal application (LRA) for the Indian Point NuclearGenerating Unit Nos. 2 and 3. Specifically, the NRC staff informed Entergy that the currentlicensing basis for Unit 2 was not fully represented in accordance with Part 54.4(a)(3) of Title 10of the Code of Federal Regulations (10 CFR 54.4(a)(3)). During its acceptance review, the NRC staff determined that the applicant has not includedwithin the scope of license renewal those systems, structures, and components relied on in thesafety analyses or plant evaluations to perform a function that demonstrates compliance withthe requirements for station blackout (SBO) per 10 CFR 50.63, and safe shutdown per10 CFR 50.48. In this regard, the LRA did not include information on the gas turbines currentlycredited as an alternate power supply for the Appendix R and SBO events. Please respond within 14 days of the receipt of this letter to inform the staff of your plans toresolve the acceptance issue identified above. If you have any questions on this matter, pleasecontact Bo Pham by telephone at 301-415-8450 or via e-mail at BMP@nrc.gov
.Sincerely,/RA/Pao-Tsin Kuo, DirectorDivision of License RenewalOffice of Nuclear Reactor RegulationDocket Nos. 50-247 and 50-286 cc: See next page June 18, 2007Mr. Michael KanslerPresidentEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601
SUBJECT:
REVIEW STATUS OF THE LICENSE RENEWAL APPLICATION FOR THEINDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3
Dear Mr. Kansler:
By letter dated April 23, 2007, as supplemented by letter dated May 3, 2007, Entergy NuclearOperations, Inc. (Entergy) submitted an application for renewal of Operating Licenses Nos.DPR-26 and DPR-64 for the Indian Point Nuclear Generating Unit Nos. 2 and 3, respectively. By teleconference on June 6, 2007, U.S. Nuclear Regulatory Commission (NRC) staff informedrepresentatives from Entergy that certain information is needed for the staff to complete theacceptance review of the license renewal application (LRA) for the Indian Point NuclearGenerating Unit Nos. 2 and 3. Specifically, the NRC staff informed Entergy that the currentlicensing basis for Unit 2 was not fully represented in accordance with Part 54.4(a)(3) of Title 10of the Code of Federal Regulations (10 CFR 54.4(a)(3)). During its acceptance review, the NRC staff determined that the applicant has not includedwithin the scope of license renewal those systems, structures, and components relied on in thesafety analyses or plant evaluations to perform a function that demonstrates compliance withthe requirements for station blackout (SBO) per 10 CFR 50.63, and safe shutdown per10 CFR 50.48. In this regard, the LRA did not include information on the gas turbines currentlycredited as an alternate power supply for the Appendix R and SBO events. Please respond within 14 days of the receipt of this letter to inform the staff of your plans toresolve the acceptance issue identified above. If you have any questions on this matter, pleasecontact Bo Pham by telephone at 301-415-8450 or via e-mail at BMP@nrc.gov
.Sincerely, /RA/Pao-Tsin Kuo, DirectorDivision of License RenewalOffice of Nuclear Reactor RegulationDocket Nos. 50-247 and 50-286DISTRIBUTION: See next pageAdams Accession No.: ML071630049OFFICEPM:REBBLA:RLRABC:REBBBC:RLRBOGCD: DLRNAMEB. PhamI. KingR. FranovichR. AuluckS. Turkw/changesPTKuoDATE06/15/0706/12/0706/18/0706/15/0706/14/0706/18/07 OFFICIAL RECORD COPY Letter to M. Kansler from P.T. Kuo, dated June 18, 2007DISTRIBUTION
SUBJECT:
REVIEW STATUS OF THE LICENSE RENEWAL APPLICATION (LRA) FORTHE INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3HARD COPYDLR R/F E-MAIL:PUBLICRidsEdoMailCenterRidsSecyMailCenterRidsOgcMailCenter RidsNrrWpcMail RidsRgn1MailCenter RidsNrrDlrRidsNrrDlrRlraRidsNrrDlrRlrbRidsNrrDlrRlrcRidsNrrDlrRebaRidsNrrDlrRebbRidsNrrDciRidsNrrDraRidsNrrDeRidsNrrDeEembRidsNrrDeEeebRidsNrrDss
BPhamJCaverlyRFranovichKGreenRAuluckMKowal JBoskaECobey, RIRConte, RIMCox, RIDJackson, RIBWittick, RINSheehan, RI OPADScrenci, RI OPASBurnell, OPADMcIntyre, OPARShane, OCAUShoop, OEDOAStubbsJames Davis Indian Point Nuclear Generating, Units 2 and 3 cc:Mr. Gary J. TaylorChief Executive Officer Entergy Operations, Inc.1340 Echelon ParkwayJackson, MS 39213Mr. John T. HerronSenior Vice President and Chief Operating OfficerEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. Fred R. DacimoSite Vice PresidentEntergy Nuclear Operations, Inc.Indian Point Energy Center450 Broadway, GSBP.O. Box 249Buchanan, NY 10511-0249Mr. Paul RubinGeneral Manager, Plant OperationsEntergy Nuclear Operations, Inc.Indian Point Energy Center450 BroadwayP.O. Box 249Buchanan, NY 10511-0249Mr. Oscar LimpiasVice President EngineeringEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. Christopher SchwarzVice President, Operations SupportEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. John F. McCannDirector, LicensingEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Ms. Charlene D. FaisonManager, LicensingEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. Michael J. ColumbDirector of OversightEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. James ComiotesDirector, Nuclear Safety AssuranceEntergy Nuclear Operations, Inc.Indian Point Energy Center450 Broadway, GSBP.O. Box 249Buchanan, NY 10511-0249Mr. Patric ConroyManager, LicensingEntergy Nuclear Operations, Inc.Indian Point Energy Center450 Broadway, GSBP.O. Box 249Buchanana, NY 10511-0249Assistant General CounselEntergy Nuclear Operations, Inc.440 Hamilton AvenueWhite Plains, NY 10601Mr. Peter R. Smith, PresidentNew York State Energy, Research and Development Authority17 Columbia CircleAlbany, NY 12203-6399Mr. Paul EddyNew York State Department of Public Service 3 Empire State PlazaAlbany, NY 12223 Indian Point Nuclear Generating, Units 2 and 3 cc:-2-Regional Administrator, Region IU.S. Nuclear Regulatory Commission475 Allendale RoadKing of Prussia, PA 19406Senior Resident Inspector's OfficeIndian Point 2U.S. Nuclear Regulatory CommissionP.O. Box 59Buchanan, NY 10511Senior Resident Inspector's Office Indian Point 3U.S. Nuclear Regulatory CommissionP.O. Box 59Buchanan, NY 10511Mr. Charles Donaldson, EsquireAssistant Attorney GeneralNew York Department of Law120 BroadwayNew York, NY 10271Mayor, Village of Buchanan236 Tate AvenueBuchanan, NY 10511Mr. Raymond L. AlbaneseFour County Coordinator200 Bradhurst AvenueUnit 4 Westchester CountyHawthorne, NY 10532Mr. William DiProfioPWR SRC Consultant139 Depot RoadEast Kingston, NH 03827Mr. Garry RandolphPWR SRC Consultant1750 Ben Franklin Drive, 7ESarasota, FL 34236Mr. William T. RussellPWR SRC Consultant400 Plantation LaneStevensville, MD 21666-3232Mr. Jim RiccioGreenpeace702 H Street, NWSuite 300Washington, DC 20001Mr. Phillip MusegaasRiverkeeper, Inc.828 South BroadwayTarrytown, NY 10591Mr. Mark JacobsIPSEC46 Highland DriveGarrison, NY 10524Mr. Gordon A. CleftonNuclear Energy Institute1776 I Street, NW, Suite 400Washington, DC 20006-3708 Mr. R. M. WatersTechnical Specialist Licensing450 BroadwayP.O. Box 0249Buchanan, NY 10511-0249