ES-301, Rev. 9 I

Control Room/ln-Plant Syst2ms Outline Form ES-301-2 Facility: Nine Mile Point Unit 1 Date of Examination: December 11, 2006 Exam Level: RO SRO-I Operating Test No.: NRC EXAMINATION 11 Control Room Systems@(8 for RO); (7 for SRO-I); (2 or 3 for SRO-U, including 1 ESF)

I System / JPM Title Type Code* Safety Function Proc N1-OP-I H.4.0 REACTIVITY Y

RADIOACTIVITY RELEASE KA 288000 A4.01 3.112.9 output fails low and must be removed from s Proc N1-OP-32 H.6.0, H.5.0 HEAT REMOVAL Proc N1-OP-30 H.8.0 ELECTRICAL L

F WLC to automatic control, level transmitter fails downscale, requiring REACTOR WATER manual level control). INVENTORY CONTROL Proc N 1-PM-Q8, N 1- 0 P - I 6 CONTAINMENT Scram JPM is not performed by SRO-I INSTRUMENTATION MSlVs at Power Proc N1-ST-Q26, Sections 8.2 and 8.3 CONTROL KA 239001 A4.01 4.2/4.0 LC1 05-01 NRC Exam 2006 Draft Submittal Iof 2 10/24/06 8:36 AM

KA 295031 EA1.08 3.8/3.9 REACTIVITY entered which directs entry into NI-OP-40 to transfer RPS Bus 1I to alternate INSTRUMENTATION supply, /&C Bus 130)

Proc N1-OP-40 F.1.0 and H.l.O and N1-SOP-40.1 KA 212000 A2.02 3.7/3.9 Bank 0 1-0PS-PJE-212-1-08 JPM 11 Feedwaterl Take Local Manual Control of Feedwater Flow Control I r\ I 2 Valve 12 REACTOR WATER Proc N1-OP-16 H.l.O INVENTORY KA 259001 A2.05 3.0/3.0 CONTROL Bank 01-OPS-PJE-259-1-08 (12 FCV)

@All control room (and in-plant) systems must be different and serve different safety functions; in-plant systems and functions may overlap those tested in the control room.

Planned Simulator JPM Combinations JPM 1,2 JPM 3,4 JPM 5,6 JPM 7 standalone (RO Only)

JPM 8 standalone LC1 05-01 NRC Exam 2006 Draft Submittal 2 of 2 10/24/06 8:36 AM

NINE MILE POINT NUCLEAR STATION OPERATOR JOB PERFORMANCE MEASURE

Title:

Start A Recirc Pump At Power Revision: NRC 2006 Task Number: 20200401 01 Ap provaIs:

Q &

Gederal Superhsor Date NA EXAM SECURITY General Supervisor I

Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (RO/SRO)

Tra inerlEvaIuat o r :

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 25 min Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 1 NRC November 2006

Recommended Start Location: (Completion time based on the start location)

Unit 1 Simulator Simulator Set-up (if required):

IC231 For Exam is equivalent. IC20 modified for 4 loop operation Recirc Pump 11 is shutdown, discharge valve closed and controller in MAN.

Core Flow is reduced to 50 Mlbmlhr Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional I concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Training JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasdFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. NUREG 1123, 202001, A4.01, 3.7/3.7
2. N1-OP-I, H.4.0 Tools and Equipment:
1. None Unit 1 JPM 1 NRC November 2006

Task Standard: Recirc Pump 11 started and controlled by master controller per N1-OP-I.

Initial Conditions:

1. 4 loop power operations are in progress
2. Recirc Pump 11 is to be started and placed in service following corrective maintenance.
3. The pump is NOT in local manual or local lock.
4. All support personnel from Maintenance, I&C and Engineering are available to support the pump start.
5. All required briefings are complete.
6. Approved RMR is with SM and permission is granted to proceed with pump start.
7. Instructor to ask operator for any questions.

Initiating Cues:

RO : (Operators name), start Recirc Pump 11 per N1-OP-1, section H.4.0.

SRO : (Operators name), start Recirc Pump 11 per normal operating procedures.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-O1/ CNG-HU-1.Ol-1001) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-I is obtained. Precautions & Sat/Unsat procedure and review/utilize the limitations reviewed & section H.4.0 correct section of the procedure.
3. IF selected RRP is in Local Manual or Identifies step as NA Sat/Unsat Local lock.. . . . .
4. Verify the following:

Depress the RR MG 11 SCOOP Depresses RR MG 11 SCOOP TUBE Sat/Unsat TUBE AIR FAILURE LOCK RESET AIR FAILURE LOCK RESET pushbutton (F Panel) pushbutton (F Panel)

RR MG 11 SCOOP TUBE AIR Observes RR MGI 1 SCOOP TUBE Sat/Unsat FAILURE LOCK light extinguished. AIR FAILURE LOCK red light extinguished.

Verify Scoop Tube Position Meter Observe Scoop Tube Position Meter Sat/Unsat (middle meter) is set at 40% by (middle meter) at 40% by Control Control Room Indication. Room Indication.

5. Confirm approximately 120 VAC Requests voltage reading from Sat/Unsat across terminals 3 and 4 on Relay 31 Electrical Maintenance (EM)

VOLT REG REMOTE EXC (aux CR) personnel.

Cue: Voltage reading across terminal 3 and Acknowledges report of terminal Sat/U nsat 4 is 120 VAC. voltage.

Unit 1 JPM 1 NRC November 2006

44s Performance Steps Standard Grade

6. Check physical condition of Relay 63X, Directs EM to check relay condition SatlUnsat (Aux CR) and verify contacts pulled in and verify contacts pulled in.

(relay energized).

Cue: Relay is energized with contacts pulled Acknowledges report of relay Sat/Unsat in. condition and relay energized.

7. Directs the following steps be Directs performance and performed (in any order): acknowledges status for the following:

Cue: All conditions below are correct for the pump start.

IF pump is isolated ..... Step NA, pump is not isolated Sat/Unsat Loop Flow instrument valved in Instrument valved in SatlUnsat Reactor Engineer notified.. .. Reactor Engineer notified Sat/Unsat Confirm exciter brushes not lifted Exciter brushes are properly installed Sat/Unsat Confirm I/P air pressure signal > 10 psig Air pressure is above 10 psig Sat/Unsat Bailey Scoop tube positioner connected Positioner is connected Sat/Unsat

8. If placing the loop in service, THEN Directs verification of electrical and Sat/Unsat verify electrical and mechanical stops mechanical stops adjusted for 5 loop adjusted for 5 loop operation. operation.

Cue: Electrical and mechanical stops are Acknowledges report of stop Sat/Unsat adjusted for 5 loop operation. adjustments.

9. Confirm idle loop temperature is within Calls up A427 and A428 for loop 11 Sat/Unsat 45°F of an operating loop by checking Calls up points for any operating loop. SatlUnsat computer points . cl Compares temperatures Sat/Unsat Determines loops differential PasdFail temperatures are within 45°F.

IO. Verify RESET the following:

Sat/Unsat 86 GENERATOR LOCKOUT (Aux 0 Dispatches operator to Aux Control CR) Room to verify lockout is reset.

Cue: Report 86 generator lockout is reset.

PUMP MOTOR VIBRATION Observes alarm F2-1-1 is cleared. Sat/Unsat RESET (F Panel)

Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade

11. Verify recirculation flow is less than 50 Adjust RECIRC MASTER controller to Pass/Fail x I O 6 Ibm/hr. establish flow is less than 50 x IO6 Ibmlhr. (E Console)
12. Verify Recirc Pump MIA station Observeslchecks Verify Recirc Pump Sat/Unsat AUTO/BAL/MAN switch to MAN 11 M/A station AUTO/BAL/MAN switch in MAN.
13. Set RRECIRC PUMP 11 GEMAC Adjust RRECIRC PUMP 11 GEMAC Pass/Fail OUTPUT (BOTTOM METER) to match OUTPUT (BOTTOM METER) to running pumps with a maximum of match running pumps with a 50%. maximum of 50%.
14. Verify closed REACTOR R PUMP 11 Observe REACTOR R PUMP 11 Sat/Unsat DISCHARGE VALVE DISCHARGE VALVE closed by green light indication (F Panel)
15. Verify open the following: valves:

Sat/Unsat 0 REACTOR R PUMP 11 SUCTION 0 Observe REACTOR R PUMP 11 VALVE SUCTION VALVE open by red light indication (F Panel)

Sat/Unsat 0 REACTOR R PUMP 11 BYPASS Observe REACTOR R PUMP 11 VALVE BYPASS VALVE open by red light indication (F Panel)

CAUTION: Failure to trip the generator when frequency drops to 0 hz could result in damage to the generator slip rings.

16. IF frequency drop to 0 hz... . . .. . IF Frequency drops to 0 Hz when field Sat/Unsat/

NA Frequency is NOT expected to drop to 0 breaker closes, THEN places REACTOR RP MOTOR 11 switch at F Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade Panel to STOP. (Not expected)

NOTE: During start sequence, alarm FZ-1-1 is expected to actuate. IF candidate begins to respond to this alarm inform candidate that a second operator will respond to this alarm.

17. Place in START REACTOR RP Place REACTOR RP MOTOR 11 PasslFail MOTOR 11 switch at F Panel and switch at F Panel to START observe auto sequencing to confirm proper operation:

Observes start sequence: Sat/ Unsat MG MOTOR starts MG MOTOR starts MG Generator accelerates to 50-60 MG Generator accelerates to 50-hz 60 hz Generator Field Breaker closes Generator Field Breaker closes Generator slows down toward 20% Generator slows down toward or 11.5 hz 20% or 11.5 hz

18. WHEN speed (Frequency Meter) is Open REACTOR R PUMP 11 Pass/FaiI between 30 and 25 hz, open DISCHARGE VALVE.

REACTOR R PUMP 11 DISCHARGE VALVE.

19. IF reverse flow is observed as IF reverse flow conditions are Sat/Unsat/

indicated by increasing Total observed, reports condition to SRO NA Recirculation Flow and decreasing and notifies SRO of TS 3.6.2 entry reactor power, THEN declare the requirement.

APRMs inoperable and enter TS 3.6.2 (NOT expected)

20. IF desired THEN maintain Total Recirc Acknowledges direction Sat/Unsat/

Flow constant by reducing other NA pumps speeds.

Cue: CRS does NOT desire to maintain total Recirc flow constant.

21. Verify RRP 11 maintained within the Observes parameters and ensures Sat/Unsat following limits: they are below values listed.

Generator MW < 0.790 Generator amps < 240 RRP Flow < 16.8 X IO6 Ibm/hr continuous Generator Frequency 11.5 to 56 Hz Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade

22. Adjust pumps speed to match other Adjust RECIRC PUMP 11 SPEED PasslFail pumps. CONTROL MAN adjust knob such that pump speed matches speed of other pumps. (Approx 38 to 40Hz)
23. WHEN pump speed matches other WHEN pump speed matches other Pass/FaiI pumps AND deviation (top meter) is at pumps AND deviation (top meter) is at zero, place RRECIRC PUMP 11 zero, place RRECIRC PUMP 11 SPEED CONTROL IN AUTO OR SPEED CONTROL IN BAL.

BALANCE, if desired.

Cue: Direct speed control placed in BAL

24. Verify P/F map on E Panel updated to 5 loop P/F map is displayed at E Sat/Unsat loop requirements. Panel.
25. Verify reset 50 SR PUMP MOTOR Dispatches operator to verify target is Sat/Unsat STALLED ROTOR target (Aux CR) reset.

Acknowledge report that target is Cue: Report target is reset. reset.

26. IF recovering from 3 loop ..... Step is NA Sat/Unsat
27. Maintain Reactor Recirc MG Set Oil Dispatches operator to maintain oil Sat/Unsat Cooler Outlet Temperatures 110 to temperatures within limits per section 130°F by throttling oil cooler TBCLC F.3.0 outlet valves.
28. Remove any off normal signs Removes any off normal condition Sat/Unsat previously posted for pump started. signs.
29. Report RRP 11 started to SRO. Reports RRP started to SRO Sat/Unsat END OF JPM Terminating Cue: Recirc Pump 11 started and controlled by master controller per N1-OP-I RECORD STOP TIME Unit 1 JPM 1 NRC November 2006

Initial Conditions:

1. 4 loop power operations are in progress
2. Recirc Pump 11 is to be started and placed in service following corrective maintenance .
3. The pump is NOT in local manual or local lock.
4. All support personnel from Maintenance, I&C and engineering are available to support the pump start.
5. All required briefings are complete.
6. Approved RMR is with SM and permission is granted to proceed with pump start.
7. Instructor to ask operator for any questions.

Initiating Cues RO : (Operators name), start Recirc Pump 11 per N1-OP-I, section H.4.0.

SRO : (Operators name), start Recirc Pump 11 per normal operating procedures .

Unit 1 JPM 1 NRC November 2006

SRO Initial Conditions:

1. 4 loop power operations are in progress
2. Recirc Pump 11 is to be started and placed in service following corrective mainte nance .
3. The pump is NOT in local manual or local lock.
4. All support personnel from Maintenance, I&C and engineering are available to support the pump start.

5 . All required briefings are complete.

6. Approved RMR is with SM and permission is granted to proceed with pump start.

7 . Instructor to ask operator for any questions.

Initiating Cues:

SRO : (Operators name), start Recirc Pump 11 per normal operating procedures .

Unit 1 JPM 1 NRC November 2006

NINE MILE POINT NUCLEAR STATION OPERATOR JOB PERFORMANCE MEASURE Tit1 : Shift Reactor Building Supply and Exhaust Fans (Alternate Path) Revisi  : NRC 2006 Task Number: 2880040101 Approvals:

I /6/ZJ/Lzy NA EXAM SECURITY I Gederal Superdsor Date General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

Trainer/Evaluator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 15 Minutes Time Critical Task: No Alternate Path Task: Yes Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 2 NRC November 2006

Recommended Start Location: (Completion time based on the start location)

Unit 1 Simulator Simulator Set-up (if required):

1. IC231 For Exam. Run with JPM 1
2. RX Building Supply and Exhaust Fans 11 in service, in SLOW.
3. Load bat file n06jpm2.bat hzlhvfOlg==l is green light on for SUPPLY FAN 11 When it lights, Exh Fan 12 trips trgset 1 "hzlhvfOlg==l" trg 1 "imf hvOlb ( I 0:05)"

Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas Pass/Fail. All steps are sequenced critical unless denoted by a ' ' 0 " .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

Unit 1 JPM 2 NRC November 2006

References:

1. N1-OP-IO Tools and Equipment:
1. None Task Standard:

Supply Fan 12 and Exhaust Fan I 1 back in service, in fast speed.

Initial Conditions:

1. Reactor Building Exhaust Fan 11 and Reactor Building Supply Fan 11 are in service in SLOW
2. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), place Reactor Building Exhaust and Supply Fans 12 in service per N1-OP-IO Section F. After shifting fans, place the operating fans in FAST speed.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-Ol/Operations Manual) providing correction if necessay.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-IO obtained. SatlUnsat procedure and reviewhtilize the Precautions & limitations reviewed &

correct section of the procedure. section F.1.2, F.2.2 and F.3.1 referenced.

SUBSTITUTE EXHAUST FANS

3. Verify operating RX Building supply Visually observe REACTOR BLDG SaVUnsat and exhaust fans in SLOW. (F.1.2.1) SUPPLY FAN 11 and REACTOR BLDG EXHAUST FAN 11 fans in SLOW red slow light illuminated.
4. Start REACTOR BLDG EXHAUST Rotate REACTOR BLDG EXHAUST PasdFail FAN 12 on SLOW (F.1.2.2) FAN 12 control switch CW to the SLOW position observe red slow light illuminated, green light off.

Unit 1 JPM 2 NRC November 2006

Performance Steps Standard Grade

5. Confirm damper 202-07, REACTOR Observe 202-07 open red light on, SatlUnsat BLDG EXHAUST FAN 12 OUTLET green light off.

DAMPER open. (FI .2.3)

6. Stop REACTOR BLDG EXHAUST Rotate REACTOR BLDG EXHAUST Pass/Fail FAN 11. (FI .2.4) FAN 11 control switch CCW to the Off position.
7. Confirm damper 202-08, REACTOR Observe REACTOR BLDG EXHAUST SatlUnsat BLDG EXHAUST FAN 11 OUTLET FAN 11 OUTLET DAMPER closed DAMPER closed. (F.1.2.5) green light on, red light off.
8. Confirm normal system flow. (F.1.2.6) Observe annunciator L1-2-5 RB SatlUnsat VENT EXH FLOW LOW is clear.

SUBSTITUTE SUPPLY FANS

9. Verify operating RX Building supply Visually observe REACTOR BLDG Sat/Unsat and exhaust fans in SLOW. (F.2.2.1) SUPPLY FAN 11 and REACTOR BLDG EXHAUST FAN 12 fans in SLOW red slow light illuminated.

IO. Start REACTOR BLDG SUPPLY FAN Rotate REACTOR BLDG SUPPLY Pass/Fail 12 on SLOW. (F.2.2.2) FAN 12 control switch CW to the SLOW position observe red slow light illuminated, green light off.

11. Confirm damper FCV 202-04, Observe 202-04 open red light on, Sat/Unsat REACTOR BLDG SUPPLY FAN 12 green light off INLET DAMPER open. (F.2.2.3)
12. Stop REACTOR BLDG SUPPLY FAN 0 Rotate REACTOR BLDG SUPPLY PasdFail
11. (F.2.2.4) FAN I 1 control switch CCW to the Off position and observe red slow light off, green light illuminated.
13. Confirm damper 202-03, REACTOR Observe REACTOR BLDG SUPPLY SatlUnsat BLDG SUPPLY FAN 11 OUTLET FAN 11 OUTLET DAMPER closed DAMPER closed. (F.2.2.5) green light on, red light off.

Unit 1 JPM 2 NRC November 2006

Performa nce Ste ps Standard Grade ALTERNATE PATH WHEN Supply Fan I I is stopped (green light on, RB Exhaust Fan 12 trips.

Annunciators L1-1-5, L1-2-5 and LI-3-4 alarm. RB differential pressure equalizes or goes slightly positive. (EOP-5 ENTRY)

14. Recognize and report alarms. Reports alarms and Exhaust Fan 12 Sat/Unsat/

tripped. NA

15. Implements actions per L1-1-5, RB VENT EXH FAN 11-12 TRIP-VIB Confirm alarm on computer Identifies E126 RB VENT EXH FAN Sat/Unsat printout 12 TRIP 0 Dispatches operator to investigate 0 Dispatches operator to investigate Sat/Unsat IF fan trip verify closed outlet Observe REACTOR BLDG EXHAUST Sat/Unsat damper FAN 12 OUTLET DAMPER closed green light on, red light off IF fan trip start standby Reactor Rotate REACTOR BLDG EXHAUST Pass/Fail Building Exhaust Fan FAN 11 control switch CW to the SLOW position observe red slow light illuminated, green light off.

RB Exhaust Fan I 1 and Supply Fan 12 are running in SLOW speed. RB differential pressure returns to normal. All alarms are clear, except L1-1-5.

SHIFT FAN SPEED

16. IF shifting fan speed from slow to fast, perform the following:

Place operating Reactor Bldg Rotate REACTOR BLDG EXHAUST PasslFail Exhaust fan control switch to FAN 11 control switch CW to the FAST. (F.3.1.1) FAST position observe red fast light illuminated, green and red slow light is off.

Unit 1 JPM 2 NRC November 2006

Performance Steps Standard Grade Place operating Reactor Bldg Rotate REACTOR BLDG SUPPLY PasslFail Supply Fan control switch to FAST. FAN 12 control switch CW to the (F.3.1.2) FAST position observe red fast light illuminated, green and red slow light is off.

Verify Reactor Building/Differential Observe Reactor Building/DifferentiaI SaVUnsat Pressure between -0.25 and -0.4 Pressure between -0.25 and -0.4 inches water. (F.3.1.3) inches water.

IF RB SUPPLY VENT HEATERS Dispatches operator to place switch SaVUnsat ON/OFF CONTROL SWITCH is in to ON OFF, THEN place the RB SUPPLY VENT HEATERS ON/OFF CONTROL SWITCH in ON.

(F.3.1.4)

Cue: When dispatched report switch is placed to ON.

Adjust RB SUPPLY VENT Acknowledges no adjustments are Sat/Unsat HEATERS CONTROL SWITCH as necessary.

directed by Shift Manager Cue: As SM, no adjustments are necessary

17. Notify SRO that REACTOR BLDG Proper communications used. SatlUnsat EXHAUST FAN 11 and REACTOR BLDG supply FAN 12 are running in FAST.

Cue: Acknowledge report.

END OF JPM Terminating Cue: Supply Fan 12 and Exhaust Fan 11 back in service, in fast speed RECORD STOP TIME Unit 1 JPM 2 NRC November 2006

Initial Conditions:

1. Reactor Building Exhaust Fan 11 and Reactor Building Supply Fan 11 are in service in SLOW.
2. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), place Reactor Building Exhaust and Supply Fans 12 in service per N 1-0P-I 0 Section F. fifter shifting fans, place the operating fans in FAST speed.

./

/I P-Unit I JPM 2 NRC November 2006

N l N t M l L t PWIN I N U L L t A K S I HI ION OPERATOR JOB PERFORMANCE MEASURE

Title:

Place Generator Amplidyne In Service (Alternate Path) Revision: NRC 2006 Task Number: 2450090101 Approvals:

NA EXAM SECURITY I General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

TrainedEvaluator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 10 min Time Critical Task: NO Alternate Path Task: YES Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 3 NRC November 2006

Unit 1 Simulator Simulator Set-up (if required):

For Exam IC228 and run with JPM 4 Amplidyne is shutdown. Voltage Regulation in MANUAL on EXCITER RHEOSTAT Run bat n06jpm3.bat for setup of triggers listed below.

Place malfunction on TRG. EGO3 GENERATOR AUTO VOLTAGE REGULATOR FAILS (DECREASE). When MVAR is adjusted above 100 MVAR, the malfunction activates. MVAR > 100 is hzaegvare >0.60 and malfunction is imf ego3 (1 0:02) trgset 1 hzaegvare >0.60 trg 1 imf ego3 (1 0:02)

Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, 1 will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

Unit 1 JPM 3 NRC November 2006

References:

1. N1-OP-32, H.6.0 and H.5.0 Tools and Equipment:
1. None Task Standard: Generator Voltage control is established using EXCITER RHEOSTAT. MVARS are 50 to 100 to bus. The amplidyne no longer in service.

Initial Conditions:

1. Generator voltage control is with EXCITER RHEOSTAT
2. Amplidyne is shutdown and routine maintenance is complete.
3. Amplidyne is ready to be started up.
4. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), place the generator amplidyne back in service and adjust to 100 to 140 MVARS to bus, in accordance with N1-OP-32.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat SaffUnsat Evaluator Acknowledge repeat back back (GAP-OPS-011 CNG-HU-1.01-1001) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-32 is obtained. Precautions & Sat/Unsat procedure and reviewlutilize the limitations reviewed & section H.6.0 correct section of the procedure.
3. Place VOLTAGE REG TRANSFER VOLTAGE REG TRANSFER switch to Pass/Fail switch to TEST, at E Panel. TEST Green light remains on and VOLT REG AMPLIDYNE meter moves from 0 to about 60 DC Volts in Buck direction,
4. Adjust VOLTAGE REG ADJUSTMENT Adjust VOLTAGE REG Sat/Unsat switch to 0 volts on VOLTAGE REG ADJUSTMENT switch (RAISE) to 0 AMPLIDYNE Meter at E Panel or volts on VOLTAGE REG AMPLIDYNE meter 1M at excitation cubicle. Meter VOLT REG AMPLIDYNE meter moves from 60 to 0 DC Volts Unit 1 JPM 3 NRC November 2006

Performance Steps Standard Grade

5. Place VOLTAGE REG TRANSFER Place VOLTAGE REG TRANSFER Pass/Fail switch to RUN at E Panel. switch to RUN Red light illuminates. Initially VOLTAGE REG AMPLIDYNE meter remains at 0 DC Volts.
6. Adjust VOLTAGE REG ADJUSTMENT Adjust VOLTAGE REG switch to MVAR Loading as directed ADJUSTMENT switch (RAISE) to by Power Control. obtain I00 to I40 MVAR to Bus.

ALTERNATE PATH When M VAR reaches I O U M VAR, malfunction EGO3 becomes active after 2 second delay. MVAR goes to about 325 to Gen. No alarms will actuate but all meter indications are consistent with regulator failure, in the under-excited condition. Af E Console, P H I , PH2 and PH3 GEN amps, GENERATOR MEGAVARS, DC FIELD AMPS all move in the lower direction as the generator becomes under-excited. VOLT REG AMPLIDYNE moves toward DC VOLTS BOOST direction.

7. Recognize and report improper 0 Observe At E Console, PHI, PH2 and Sat/Unsat operation of voltage regulator. PH3 GEN amps, GENERATOR MEGAVARS, DC FIELD AMPS all move in the lower direction.

Provide the following cue, if candidate takes no action or recommends remaining at current conditions:

Cue: As Power Control, request that Nine Mile Point take action to return MVARS to at least 50 to 100 to bus to help stabilize grid voltage.

The candidate should recognize the need to take some action to restore grid voltage and that they should be returning MVARS to a value close to the original value.

Remove the Amplidyne from service per N1-OP-32 H.5.0. as follows:

8. IF conditions permit THEN perform the following:

Unit 1 JPM 3 NRC November 2006

Standard Grade Notify Power Control prior to Contacts power control using Sat/Unsat removal of amplidyne from service. telephone.

Notify NY I S 0 prior to removal of 0 NY IS0 notified by CRS Sat/Unsat amplidyne from service.

Cue: As CRS, inform candidate that CRS will contact NY I S 0 and to proceed.

Adjust EXCITER RHEOSTAT to Adjust EXCITER RHEOSTAT switch Sat/Unsat obtain zero volts on VOLTAGE (LOWER) to obtain zero volts on REG AMPLIDYNE at E Panel VOLTAGE REG AMPLIDYNE at E meter or 1M Excitation Cubicle. Panel meter.

9. Place VOLTAGE REG TRANSFER u VOLTAGE REG TRANSFER switch to PasslFail switch to TEST TEST When VOLTAGE REG TRANSFER switch is placed in TEST, regulation is now on the EXCITER RHEOSTAT.
10. IF directed by SM, THEN place o Acknowledge direction Sat Unsat VOLTAGE REG TRANSFER switch to OFF to secure the amplidyne.

Place VOLTAGE REG TRANSFER Sat/Unsat Cue: As SM, direct the VOLTAGE REG switch to OFF TRANSFER switch to OFF.

Cue: WHEN asked for desired MVAR loading, direct the candidate to establish 50 to 100 MVARs to Bus.

11. WHEN Power Control requests increase or decrease in VARS perform the following:

n Turn the EXCITER RHEOSTAT u Adjust EXCITER RHEOSTAT switch PasdFail knob to RAISE (RAISE) at E Panel to establish 50 to 100 MVARS to bus.

NOTE: WHEN candidate begins to observe conditions in steps 5.4.2 to 5.4.4, inform the candidate that these will be monitored by a second operator.

9. Notify SRO. SRO notified of conditions. Sat/Unsat END OF JPM Terminating Cue: Generator Voltage control is established using EXCITER RHEOSTAT. MVARS are 50 to 100 to bus. The amplidyne no longer in service.

Unit 1 JPM 3 NRC November 2006

RECORD STOP TIME Unit 1 JPM 3 NRC November 2006

"jpm 3 setup n06jpm3.bat "When MVAR is adjusted above 100 MVAR, the malfunction activates.

"MVAR > 100 is "hzaegvare >0.60" and malfunction is "imf ego3 (1 0:02)"

"reset to IC 228 in sim, which has amplidyne shutdown "rst 228 trgset 1 "hzaegvare >0.60" trg 1 "imf ego3 (1 0:02)"

"end setup Unit 1 JPM 3 NRC November 2006

Initial Conditions:

1. Generator voltage control is with EXCITER RHEOSTAT
2. Amplidyne is shutdown and routine maintenance is complete
3. Amplidyne is ready to be started up.
4. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), place the generator amplidyne back in service and adjust to 100 to 140 MVARS to bus. in accordance with N1-OP-32.

Unit 1 JPM 3 NRC November 2006

OPERATOR JOB PERFORMANCE MEASURE

Title:

Shift Source of Power for PBlOl from R1014 to R l O l 1 Revision: NRC 2006 Task Number: 26200201 01 Approvals:

NA EXAM SECURITY I General Supervisor Date Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (RO/SRO)

TrainerIEvaluator:

Evaluation Method: X Perform Simulate EvaI uat ion Location : Plant X Simulator Expected Completion Time: 10 min Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 4 NRC November 2006

Unit 1 Simulator Simulator Set-up (if required):

For NRC Exam IC 228 and run with JPM 3 Power for PBIOI from RIOI 4 Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Petformance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. N1-OP-30, H.8.0 Tools and Equipment:
1. None Unit 1 JPM 4 NRC November 2006

Task Standard: Power for PBlOl shifted from R1014 to R l O l I initial Conditions:

1. Electrical Maintenance has a work package to do surveillance work on R1014.
2. Potential Transformers J1017, J1016, and J1015 are racked in.
3. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), shift the source of power for PBlOl from R1014 to RlOl1, IAW N1-OP-30, Section H.8.0.

Performance Steps Standa rd Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-O1/ CNG-HU-1.01-1001) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-30 is obtained. Precautions & Sat/Unsat procedure and reviewhtilize the limitations reviewed & section H.8.0 correct section of the procedure.
3. Verify racked in potential transformers. 0 Initials complete, since condition is Sat/Unsat stated in Initial Conditions
4. Place PBlOl SUPPLY BREAKER Control switch rotated to the Bypass PasslFail INTERLOCK BY-PASS SWITCH in position.

BYPASS Annunciator A5-2-1, Power Bd. 101 Bkr. Bypass Switch is received

5. Insert Sync key in Breaker R l O l I . Sync Key inserted into Breaker RIOI 1 PasslFail
6. Turn Sync Key on Key rotated clockwise to the ON PasslFail position.
7. Confirm incoming and running voltage 0 Observe incoming and running Sat/Unsat normal. voltages matched.
8. Close Breaker RlOl1. Control switch rotated clockwise to the PasslFail close position.

Red light above switch illuminates, green light above switch extinguishes.

Unit 1 JPM 4 NRC November 2006

Performance Steps Standard Grade

9. Turn Sync Key off. Sync Key rotated to the off position. PasslFail IO. Remove Sync Key. Sync Key removed from Breaker Sat/Unsat R1011.
11. Open Breaker R1014. Control switch rotated counter- Pass/Fail clockwise to the open position.

Green light above switch illuminates, red light above switch extinguishes

12. Place PB101 SUPPLY BREAKER 0 Control switch rotated to the Normal PasslFail INTERLOCK BY-PASS SWITCH in position.

Normal Annunciator A5-2-1, Power Bd. 101 Bkr. Bypass Switch clears

13. Notify SRO that power is shifted from 0 Proper communications used. SatlUnsat R1014 to R1011.

Cue: Acknowledge report.

END OF JPM Terminating Cue: Power for PBIOI shifted from R1014 to RIOI 1 RECORD STOP TIME Unit 1 JPM 4 NRC November 2006

Initial Conditions:

1. Electrical Maintenance has a work package to do surveillance work on R1014.
2. Potential Transformers JIOI 7, J I 016, and J I 015 are racked in.
3. Instructor to ask operator for any questions.

Initiating Cues (Operators name), shift the source of power for PBlOl from R1014 to R101 1, IAW N 1-0P-30, Section H.8.0.

Unit 1 JPM 4 NRC November 2006

- NINE MILE POINT NUCLEAR STATlON OPERATOR JOB PERFORMANCE MEASURE

Title:

Exercising RPV PressureILevel Column Control Switches Revision: NRC 2006 Task Number: 2590060101 Ap provaIs:

QAQ s GenkraI upervis6 r I ,&A Date' NA EXAM SECURITY General Supervisor I

Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (RO/SRO)

T rainer/EvaIuator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 20 min Time Critical Task: NO Alternate Path Task: YES Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 5 NRC November 2006

7 Recommended Start Location: (Completion time based on the start location)

Unit 1 Simulator Simulator Set-up (if required):

IC230 is equivalent to IC20. For Exam run with JPM 6 Run bat n06jpm5.bat file to setup triggers listed below.

RR55 trigger from ZDFWMST3==1 (MASTER in BAL). See attached bat file for 2 conditional trigger.

Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. Nl-PM-Q8, Section 8.13
2. N1-OP-I 6, Section F. 10.0 Tools and Equipment:
1. None Unit 1 JPM 5 NRC November 2006

Task Standard: RPV level control established in manual and high level turbine trip and low level scram is avoided.

Initial Conditions:

1. Plant is at rated conditions.
2. Feedwater Level Control is in normal automatic three element control
3. Whenever RPV water level is being controlled in manual, the level band is 70 to 75 inches.
4. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), perform N1-PM-Q8 section 8.13 for exercising RPV Pressure/Level Columns and Feedwater Mode Control switches.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-O1/ CNG-HU-1.01-1001) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-PM-Q8, 8.13 and N1-OP-I 6, F.10.0 Sat/Unsat procedure and reviewhtilize the are obtained and reviewed.

correct section of the procedure.

FROM Nl-PM-Q8 8.13

3. Confirm 29-01, Turbine Driven Feed Observes FWP 13 is running at F Sat/Unsat Water Pump 13 is running Panel 0 FEEDWATER PUMP 13 FLO FWP 13 VALVE CONTROL signal Red Clutch Engagement lights
5. Record initial control switch positions 0 Record initial control switch positions Sat/Unsat for: for (E Console):

Feedwater Level Column 11 or 12 FEEDWATER LEVEL COL as 11 Reactor Pressure Column 11 or 12 REACT PRESS as 11 Feedwater Mode 3 FEEDWATER MODE as 3 Unit 1 JPM 5 NRC November 2006

Performance Steps Standard Grade

5. Perform Section F. 10 of N1-OP-16 Go to N1-OP-16 Steps 10.1 through Sat/Unsat Steps 10.1 through 10.6 10.6
6. Perform the following:

o IF three Feedwater pumps Indicates step I O . 1.1 is NA, since Sat/Unsat running.. . .. three pumps are not running.

IF shaft driven FWP in service ....... Verifies and indicates in step 10.1.2 Only one motor FWP is running Sat/Unsat Standby FWP 11 VALVE Sat/Unsat CONTROL is in MAN and fully closed.

Cue: When asked report MFLCPR is 0.872 MFLCPR is less than 1.0 Sat/Unsat

7. Balance the FWP VALVE CONTROL M/A station (13) which is in AUTO by performing the following: At F panel Place respective FWP 13 Pump Rotate FW P 13 Pump VALVE PasslFail VALVE CONTROL M/A station CONTROL M/A station mode switch mode switch to BAL. to BAL.

Null respective deviation meter to Adjust FWP 13 VALVE CONTROL PasslFail 50% (red dot) with manual knob. M/A station manual knob to get needle to 50% (nulled).

8. Take manual control of vessel level by Rotate FWP 13 VALVE CONTROL PasslFail placing FWP 13 VALVE CONTROL M/A station mode switch to MAN.

MIA station mode switch to MAN.

9. Control reactor vessel level by Control reactor vessel level by PasslFaill adjusting FWP 13 VALVE CONTROL adjusting FWP 13 VALVE CONTROL NA MIA station manual knob as M/A station manual knob as necessary. necessary. No adjustment should be necessary.

NOTE:

Switching level columns may result in Annunciator F2-3-3 REACT VESSEL LEVEL HIGH-LOW, due to circuit interruption.

Unit 1 JPM 5 NRC November 2006

Performance Steps Standard Grade The same channel of level and pressure should be selected.

10. Shift reactor pressure/level columns or 0 This should be the actual exercising of Feedwater modes as necessary. the switches step.

Cycles switches and returns to Cue: If asked direct each switch cycled original positions.

THREE times and restore to original positions. FEEDWATER LEVEL COL as 11 PasslFaillNA REACT PRESS as 11 PasslFaillNA PasslFaillNA FEEDWATER MODE as 3

11. Maintenance and/or testing can now 0 THEN returns to Nl-PM-Q8 at step Sat/Unsat be conducted on feedwater 8.13.3and initials as complete.

pressure/level columns or feedwater mode with no effect on level control.

NOTE:

SM will direct final position of RPV Pressure/Level Control Switches.

Cue: If necessary, direct RPV Pressure/Level Control Switches returned to their original positions.

IF cycled in JPM step I O , THEN skip step 12 and proceed to JPM step 13.

12. Exercise RPV Pressure/Level Control If switches were not cycled in JPM step Switches as follows: I O , they are PASWFAIL critical steps here.

Record final RPV Pressure/Level Control Switch positions If not cycled in JPM step IO, cycles SatlUnsatl switches here leaves in column 11 NA or Feedwater Level Column 11 or position and records final position.

12 PASS/FAIL

/NA Reactor Pressure Column 11 or 12 Cycle Feedwater Mode Control If not cycled in JPM step 10, cycles Sat/Unsat/

Switch Position switches here leaves 3 position and NA or records position.

Feedwater Mode 3 PASSFAIL INA Unit 1 JPM 5 NRC November 2006

I Performance Steps Standard Grade

13. Complete N1-OP-16, Section F.10 by Go to N1-OP-16 and performs 10.7 petforming Step F.10.7. (all steps). These are listed below in JPM step 14.
14. WHEN testing is complete return reactor vessel level control to AUTO by performing the following:

Place FEEDWATER MASTER Rotate FEEDWATER MASTER PasslFail CONTROL MIA station mode to CONTROL MIA station mode to MAN.

MAN. (E Console)

Null out FWP 13 VALVE Adjust FEEDWATER MASTER Sat/Unsat CONTROL by adjusting the CONTROL M/A station (E Console)

FEEDWATER MASTER output with the manual knob UNTIL CONTROL M/A station output with the deviation meter indicates 50%

the manual knob UNTIL the (red dot) on FWP 13 VALVE deviation meter indicates 50% (red CONTROL GEMAC (F Panel).

dot) on FWP 13 VALVE CONTROL GEMAC.

Place FWP 13 VALVE CONTROL Rotate FWP 13 VALVE CONTROL Pass/Fail M/A station mode to BAL. M/A station mode to BAL. (F panel.. .

NOT E Console)

Control reactor vessel level with Control reactor vessel level with PasslFail manual knob at FEEDWATER manual knob at FEEDWATER MASTER LBS/HR controller in MASTER LBS/HR controller in MAN MAN mode mode (E Console)

Null FEEDWATER MASTER Adjust the thumb/setpoint tape to align Sat/Unsat CONTROL setpoint error by manual setpoint (orange arrow) adjusting the thumblsetpoint tape directly under automatic setpoint to align manual setpoint (orange (green band) (E Console) arrow) directly under automatic setpoint (green band).

Place FEEDWATER MASTER Rotate FEEDWATER MASTER PasslFail CONTROL M/A station mode to CONTROL MIA station mode to AUTO or BAL. Level is now AUTO or BAL (E Console) controlled automatically by Master Controller.

ALTERNATE PATH WHEN FEEDWATER MASTER CONTROL M/A station mode is moved to AUTO or BAL. malfunction RR55 Level transmitter Unit 1 JPM 5 NRC November 2006

Performance Steps Standard Grade FAILS DOWNSCALE activates.

Level Transmitter and indication ID59A goes downscale. Annunciator F2-2-2 REACTOR WATER LEVEL HIGH LOW alarms.

f eedwater flow rises and actual level begins to rise.

15. Recognize and report rising water level condition.
16. Enter N1-SOP-16.1 Note: IF ARP F2-2-2 actions are taken, Performs one of the following to manual control would also be established. prevent high level turbine trip and This is also an acceptable basis for taking scram:

manual control. The SOP is the higher tier document. Place FEEDWATER MASTER PasslFaill CONTROL M/A station mode to NA WHEN either controller is placed in MAN, an MAN. (E Console) immediate reduction in feedwater flow occurs because the MAN signal is still at the OR correct signal for the pre-transient condition, since deviation meters were nulled. Place FWP 13 VALVE CONTROL Pass/Fail/

M/A station mode to MAN. (F NA Panel).

17. Controls RPV water level in MANUAL to Adjusts FEEDWATER MASTER Pass/Fail prevent high RPV water level trips and CONTROL, FWP 13 VALVE low RPV water scram. CONTROL or FWP 12 VALVE CONTROL M/A station mode in MAN to prevent high and low RPV water level trips.
18. Notify SRO that Feedwater level Control Proper communications used. Sat/Unsat is in MANUAL and level is stabilized.

END OF JPM Terminating Cue: RPV level control established in manual and high level turbine trip and low level scram is avoided.

RECORD STOP TIME Unit 1 JPM 5 NRC November 2006

^jpm 5 bat file n06jpm5.bat "to auto trigger the rr55 malfunction to be true when master controller is "placed back in auto, a double condtion must occur.

"first, the master must be placed in MAN (zdfwmst4==1), per the test. When this happens "the green light on A Panel MOD 93 turns on by override (2a4ds7100219)

""now, with the green light hzlegmodo on when the master is placed in AUTO zdfwmst2 or BAL zdfwmst3, the rr55 activates failing the transmitter downscale.

"rst 20 trgset 1 "zdfwmst4==1 I' trg 1 "ior 2a4ds7100219 (1 0) on" trgset 2 "zdfwmst3==l && hzlegmodo(2)==l" trg 2 "imf rr55 (2 0:02)"

"!! zdfwmst2==1 "end setup Unit 1 JPM 5 NRC November 2006

Initial Conditions:

1. Plant is at rated conditions.
2. Feedwater Level Control is in a normal automatic three element control
3. Whenever RPV water level is being controlled in manual, the level band is 70 to 75 inches.
4. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), perform N1-PM-Q8 section 8.13 for exercising RPV Pressure/Level Columns and Feedwater Mode Control switches.

Unit 1 JPM 5 NRC November 2006

NINE MILE POINT NUCLEAR STATION OPERATOR JOB PERFORMANCE MEASURE

Title:

Vent the Drywell During Power Operation Revision: NRC 2006 Task Number: 223901 0401 Approvals:

NA EXAM SECURITY I Genekal Supervzv Date General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

TrainerIEvaluator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 20 min Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if an^ critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 6 NRC November 2006

Recommended Start Location: (Completion time based on the start location)

Unit 1 Simulator Simulator Set-up (if required):

Ic20 Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM I CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasdFail. All steps are sequenced critical unless denoted by a e.
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References :

1. N1-OP-9, H.l.O Tools and Equipment:
1. None Task Standard: Drywell vent lineup is established per N1-OP-9.

Unit 1 JPM 6 NRC November 2006

Initial Conditions:

1. Drywell Pressure is 1.75 psig /
2. NI -ST-VI , VENTING/PURGING PRIMARY CONTAINMENT THROUGH RESCTOR BUILDING VENTILATION SYSTEM is in progress and being is being performed by another operator.
3. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), Vent the Drywell using RBEVS train 11, in accordance with N1-OP-9. Establish flow rate between 500 and 1600 scfm. Lower Drywell pressure to 1.2 psig.

Perfo rmance Ste ps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-O1/ CNG-HU-1.01-1001) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-9 is obtained. Precautions & Sat/Unsat procedure and review/utilize the Limitations reviewed & section H.1.O correct section of the procedure.
3. Perform N1-ST-VI within 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> 0 Check off step complete. Initial SatlUnsat PRIOR to the start and at least once conditions are N1-ST-VI is complete.

every 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> during venting/purging.

4. Vent the primary containment as Proceeds to step 1.3, Drywell Venting Sat/Unsat follows:

Drywell venting, refer to Drywell Venting section

5. Verify in STOP position 201-35 0 201-35 DRYWELL & TORUS VENT & Sat/Unsat DRYWELL & TORUS VENT & PURGE PURGE FAN control switch in STOP FAN control switch.
7. Notify SM to enter LCO 3.4.4 (f) in SM Notifies SM of requirement to enter Sat/U nsat Log Book. LCO in log book.

CUE: As SM, acknowledge requirements to enter LCO and enter in the log book.

8. Verify closed the following valves: Closed by observing green position indicating lights 201-21 DRYWELL & TOR VENT & 201-21 DRYWELL & TOR VENT SatlUnsat PURGE FAN INLET BV & PURGE FAN INLET BV Unit 1 JPM 6 NRC November 2006

Performance Steps Standard Grade 0 201-22 DRYWELL & TOR VENT & 0 201-22 DRYWELL & TOR VENT Satfunsat PURGE FAN OUTLET BV & PURGE FAN OUTLET BV 201.2-33 TORUS N2 MAKE-UP & 0 201.2-33 TORUS N2 MAKE-UP SatlUnsat BLEED ISOL VALVE 11 & BLEED ISOL VALVE 11 201.2-06 TORUS N2 MAKE-UP & 201.2-06 TORUS N2 MAKE-UP Sat/Unsat BLEED ISOL VALVE 12 & BLEED ISOL VALVE 12 0 201.2-32 DRYWELL N2 MAKE-UP 201.2-32 DRYWELL N2 MAKE- SatlUnsat

& BLEED ISOL VALVE 11 UP & BLEED ISOL VALVE 11 0 201.2-03 DRYWELL N2 MAKE-UP 0 201.2-03 DRYWELL N2 MAKE- Sat/Unsat

& BLEED ISOL VALVE 12 UP & BLEED ISOL VALVE 12 0 201.2-136 P SYS DISCH ROUTE 201.2-1 36 P SYS DISCH SaWnsat ROUTE 0 201-1 1 TORUS VENT TO 201-1 1 TORUS VENT TO Sat/Unsat CONDENSER CONDENSER NOTE: Candidate will likely identify component label in simulator is as "TORUWDRYWELL...."

0 201-47EM VENTILATION TIE BV 201-47EM VENTILATION TIE Sat/Unsat BV 202-36 EM VENTILATION FROM Closes 202-36 EM PasslFail REACTOR BLDG BV VENTILATION FROM REACTOR BLDG BV using control switch observes green light on and red light off.

Unit 1 JPM 6 NRC November 2006

Performance Steps Standard Grade 201-16 TORUS N2 VENT & 201-16 TORUS N2 VENT & SatlUnsat PURGE ISOLATION VALVE 11 PURGEISOLATION VALVE 11 201-17 TORUS N2 VENT & 0 201-17 TORUS N2 VENT & SaVUnsat PURGE ISOLATION VALVE 12 PURGE ISOLATION VALVE 12

9. Open 201-1 8 EM VENTLATION 201-18 EM VENTLATION FROM Pass/FaiI FROM DW & TORUS BV DW & TORUS BV open using cs IO. Open EM VENTILATION LOOP INLET 202-37 EM VENTILATION LOOP 11 Pass/Fail BV of selected system (System 11): INLET BV open 202-37 EM VENTILATION LOOP 11 INLET BV
11. Open 201-32 DW N2 VENT & PURGE 201-32 DW N2 VENT & PURGE Pass/Fail ISOLATION VALVE 11 ISOLATION VALVE 11 open
12. Start EM VENT EXHAUST FAN of EM VENT EXHAUST FAN started Pass/Fail selected system (System 1I )
13. Throttle open 201-31 DW N2 VENT & 201-31 DW N2 VENT & PURGE PasslFail PURGE ISOLATION VALVE 12, using ISOLATION VALVE 12 throttles open Pull-to-Stop feature. and establishes flow between 500 and 1600 scfm.
14. Verify flow rate s 1600 CFM 201-31 DW N2 VENT & PURGE Sat/Unsat ISOLATION VALVE 12 throttled open with ~ 1 6 0 CFM 0 established.
15. WHEN pressure in torus is in the When DW pressure is 1.2 psig, closes normal range (refer to Att 6), close the valves to stop purge:

following valves:

0 201-32 DW N2 VENT & PURGE 201-32 DW N2 VENT & PURGE Pass/Fail ISOLATION VALVE 11 ISOLATION VALVE 11 closed 201-31 DW N2 VENT & PURGE 201-31 DW N2 VENT & PURGE Pass/Fail ISOLATION VALVE 12 ISOLATION VALVE 12 closed

16. Stop EM VENT EXHAUST FAN EM VENT EXHAUST FAN stopped Sat/Unsat (System 11)

Unit 1 JPM 6 NRC November 2006

Performance Steps Standard Grade

17. WHEN Drywell venting is complete, verify closed the following valves:

201-18 EM VENTLATION FROM 201-18 EM VENTLATION FROM DW PasslFail DW & TORUS BV & TORUS BV 202-37 EM VENTILATION LOOP 202-37 EM VENTILATION LOOP 11 PasslFail 11 INLET BV INLET BV 202-38 EM VENTILATION LOOP 202-38 EM VENTILATION LOOP 12 PasslFail 12 INLET BV INLET BV

18. Open 202-36 EM VENTILATION 202-36 EM VENTILATION FROM Pass/Fail FROM REACTOR BUILDING BV REACTOR BUILDING BV open
19. Notify SM to exit LCO 3.4.4 (f) in SM SM notified to exit LCO Sat/U nsat Log Book
20. Report status to SRO. Reports completion of DW venting to Sat/Unsat SRO.

END OF JPM Terminating Cue: Drywell vent lineup is established per N1-OP-9.

RECORD STOP TIME Unit 1 JPM 6 NRC November 2006

Initial Conditions:

1. Drywell Pressure is 1.75 psig
2. N1-ST-VI, VENTING/PURGING PRIMARY CONTAINMENT THROUGH RESCTOR BUILDING VENTILATION SYSTEM is in progress and being is being performed by another operator.
3. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), Vent the Drywell using RBEVS train 11, in accordance with Nl-OP-9. Establish flow rate between 500 and 1600 scfm. Lower Drywell pressure to 1.2 psig.

Unit 1 JPM 6 NRC November 2006

OPERATOR JOB PERFORMANCE MEASURE

Title:

Reset RPS and ARI logic After High Drywell Pressure Scram Revision: NRC 2006 Task Number: 2000330401 Approvals:

NA EXAM SECURITY I General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

TrainerlEvaluator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 15 min Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 7 NRC November 2006

start location)

Unit 1 Simulator Simulator Set-up (if required):

lC229. Post scram conditions stabilized High DWP pressure scram received and DWP is now below 3.0 psig ARI manually initiated Ensure Feedpump is operating for level control with low flow valve in auto SOP-I should be marked up indicating which actions are completed.

An instructor should be on the floor to monitor level and acknowledge any other alarms Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. N1-SOP-1
2. ARP F1 Unit 1 JPM 7 NRC November 2006

Tools and Equipment:

1. None Task Standard: RPS and ARI logic channels reset and the SDV is draining. All rods settled to position 00.

Initial Conditions:

1. Plant scram from full power occurred on high drywell pressure about 20 minutes ago.
2. Three control rods did not insert, so ARI was manually initiated.
3. The three rods did insert.
4. N1-SOP-1 Reactor Scram is being implemented.
5. All immediate actions are complete.
6. Scram confirmation actions are complete.
7. IRM and SRM detectors were just inserted.
8. Recovery actions are in progress and conditions have stabilized.
9. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), Reset the scram and verify all rods at position 00.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat .Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-O1/ CNG-HU-1.01-1001) I providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-SOP-1 is obtained. Sat/Unsat procedure and reviewhtilize the correct section of the procedure.

THESE may be performed out of sequence. Acceptable to reset RPS before resetting ARI, as long as both are reset and rods are verified to be at position 00.

03. (SOP-1) IF ARI initiated, THEN Reset 0 At F Panel, reset ARI using Pass/Fail ARI. (SOP-1) pushbutton When ARI is reset, the following occurs:

ARI INITIATION CH I 1 and C H I 2 red lights extinguish.

VALVE POSITION SOVl13-229A red VENT light extinguishes and Unit 1 JPM 7 NRC November 2006

Performance Steps Standard Grade green NORMAL light comes on.

VALVE POSITION SOVl13-229B red VENT light extinguishes and green NORMAL light comes on

04. (SOP-I) IF all rod motion has stopped, 0 At F Panel, place both key-lock Pass/Fail THEN place both SCRAM bypass switches to BYPASS DISCHARGE VOLUME HIGH LEVEL BYPASS switches in BYPASS
05. (SOP-I) IF auto initiated scram signals 0 Recognizes that high DWP signal is have cleared THEN sealed in and must be reset at M Panel to reset RPS logic. (ARP F1-I-5 and F4-1-4)

Verify at least 1 CRD pump in Verify one CRD pump running at F Sat/Unsat service Panel by observing red light.

Reset Reactor scram AND verify At M panel, reset CONTAINMENT Pass/FaiI ALL control rods inserted to HIGH PRESSURE A and C AND B position 04 or beyond by observing and D Pushbuttons (ARP F1-1-5 and one or more of the following: F4-1-4).

At M Panel When CONTAINMENT HIGH PRESSURE A and C are reset, relay 1I K 10 resets (energizes). Annunciator F1-1-5, RPS CH 11 DRYWELL PRESS HIGH clears. FI-3-5 RPS CH I I CONTAINMENT ISOLATION F1-4-5 CONTAINMENT ISOLATION PURGE VALVES and F1-4-6 RPS CH I 1 CORE SPRAYAUTO OPERA TlON also clear.

At M Panel When CONTAINMENT HIGH PRESSURE B and D are reset, relay 12K IO resets (energizes). Annunciator F4-1-4 RPS CH 12 DRYWELL HIGH PRESS clears. F4-3-4 RPS CH 12 CONTAINMENT Isolation and F4 3 RPS CH 12 CORE SPRAYAUTO OPERATION also clear.

Unit 1 JPM 7 NRC November 2006

Performance Steps Standard Grade 0 When RPS is reset, White Pilot At E Console, depress Pass/Fail lights on M and F Panels REACTOR TRIP RESET illuminate. All rods indicate 00 pushbutton position on Full Core Display.

All rods verified into at least position 04 by observing one or more of the following:

Full Core Display Full Core Display (All rods SaUUnsat indicate 00 position)

Demand new OD-7 Option 2 Demand new OD-7 Option 2 K104A&B red LED lights lit K104A&B red LED lights lit (1S20 (1S20 Aux CR) (NOT Aux CR) (NOT EXPECTED)

EXPECTED)

All Rods In light illuminated All Rods In light illuminated (Remote Shutdown Panel) (Remote Shutdown Panel) (NOT (NOT EXPECTED) EXPECTED)

Confirm the following valves open: At F Panel observes:

SatlUnsat 44.2-15 and 44.2-16 44.2-15 and 44.2-16 CONTROL CONTROL ROD DRIVE DUMP ROD DRIVE DUMP VOL VENT VOL VENT VALVE VALVE red lights on. Sat/Unsat 44.2-17 and 44.2-18 44.2-17 and 44.2-18 CONTROL CONTROL ROD DUMP VOL ROD DUMP VOL DRAIN IV red Sat/Unsat DRAIN IV lights on.

Confirm F3-2-4 CRD DRAIN-VENT Observes F3-2-4 CRD DRAIN-VENT VALVE CLOSED clear. VALVE CLOSED clear.

6. Reports status to SRO. Report complete. SaUUnsat END OF JPM Terminating Cue: RPS and ARI logic channels reset and the SDV is draining. All rods settled to position 00.

RECORD STOP TIME Unit 1 JPM 7 NRC November 2006

Initial Conditions:

1. Plant scram from full power occurred on high drywell pressure about 20 minutes ago.
2. Three control rods did not insert, so ARI was manually initiated.
3. The three rods did insert.
4. N1-SOP-I Reactor Scram is being implemented.

5 . All immediate actions are complete.

6. Scram confirmation actions are complete.

7 . IRM and SRM detectors were just inserted.

8. Recovery actions are in progress and conditions have stabilized.
9. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), Reset the scram and verify all rods at position 00.

Unit 1 JPM 7 NRC November 2006

OPERATOR JOB PERFORMANCE MEASURE

Title:

MSlV Stroke Test and Limit Switch Test (NI-ST-Q26) Revision: NRC 2006 Task Number: 2399010201 N/A, NRC EXAM SECURITY /

4 G era I Su pervidor Date General Supervisor Date dperations Training (Designee) Operations (Designee)

NIA, NRC EXAM SECURITY I Configuration Control Date Performer: (RO/SRO)

Trainer/Evaluator:

Evaluation Method: X Perform Simulate Evaluation Location: Plant X Simulator Expected Completion Time: 20 Min. Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 8 NRC October 2006

Unit 1 Control Room Simulator Simulator Set-up (if required):

1. Initialize the simulator to IC-20 or equivalent.
2. Take the simulator out of freeze.
3. An instructor may be used on simulator floor, if allowed, to perform as an extra operator, for confirming some indications during valve stroking. Monitoring the valve mimic, as an extra operator is appropriate.

Directions to the InstructorlEvaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a err.
2. During Evaluated JPM:

0 Self checking shall be demonstrated.

3. During Training JPM:

0 Self checking shall be demonstrated.

0 Peer checking shall be demonstrated.

References:

1. NUREG 239001 A4.01 RO 4.2 SRO 4.0
2. NMP Unit One Task Analysis 2399010201, 3.0 (RO)

Tools and Equipment:

None Task Standard: Nl-ST-QZ6 completed for MSlV 01-03, Main Steam Isolation Valve 112.

Initial Conditions:

1. Plant is operating at 100% power with no inoperable equipment.
2. All prerequisites for the test are completed.
3. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), test Main Steam Line Isolation Valve 112 & 121 in accordance with NI-ST-Q26, Section 8.2 & 8.3.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-01/Operations Manual) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference R Nl-ST-Q26 obtained and applicable SaUUnsat procedure and review/utilize the sections reviewed.

correct section of the procedure.

3. Prepare to initiate a half scram on CHANNEL 11.

Verify no RPS Half Scram exists 0 Verify by all scram solenoid lights PasslFail energized 0 Notify the CSO that the following Proper communications used. Sat/Unsat steps will initiate the half scram on RPS CH 11

4. Place Main Steam Isolation Valve 7 % R Test switch is rotated to the 112 PasslFail Test Switch to the 112 position. position.
05. Confirm 01-03 MSlV 112 white test 0 White test light for MSlV 112 is SaUUnsat light ON. verified energized.
06. Confirm 01-03 MSlV 112 yellow test Yellow light is extinguished for MSlV SatlUnsat light OFF. 112.

Performance Steps Standard Grade NOTE to Evaluator:

JPM steps 7 to 14 will occur in rapid sequence. An instructor may perform as an extra operator as necessary for verifications.

7. Momentarily place control switch for Rotate switch for MSlV 112 Pass/Fail MSlV 112 to CLOSE position. momentarily to CLOSE then release.
08. Check RPS Channel 11 half scram Verify the following: Sat/Unsat indications as follows:

CH 11 SCRAM SOLENOID 0 CH 11 SCRAM SOLENOID GROUPS 1,2,3,4 White Light OFF GROUPS 1,2,3,4 White Light CH 11 B.U. SCRAM S.D.V. VENT OFF.

AND DRAIN VALVE Light OFF CH 11 B.U. SCRAM S.D.V. VENT Annunciator F1-1-7, RPS CH 1 1 AND DRAIN VALVE Light OFF MNSM LINE II ISOL Valve 0 Annunciator F1-1-7, RPS CH 11 CLOSED, alarms. MNSM LINE I I ISOL Valve n Annunciator F1-2-1, RPS CH 11 CLOSED, alarms.

AUTO REACTOR TRIP, alarms. Annunciator F1-2-1, RPS CH 11 AUTO REACTOR TRIP, alarms.

9. Confirm 01-03, MSIV-112 automatic Verify the following: Sat/Unsat partial closure indications as follows:

01-03 MSIV-112 Green Light ON 01-03 MSIV-112 Green Light ON 01-03 MSIV-112 Red Light ON 01-03 MSIV-I 12 Red Light ON 01-03 MSIV-112 Mimic Light ON 01-03 MSIV-112 Mimic Light ON IO. Confirm after approximately 20 Yellow light for MSlV is verified BRIGHT. SatlUnsat seconds Yellow light for MSlV 112 is brightly illuminated.

11. Confirm 01-03 MSIV-112 automatic Verify the following:

opening indications as follows:

01-03 MSIV-112 Green Light OFF 01-03 MSIV-112 Green Light OFF 01-03 MSIV-112 Red Light ON 01-03 MSIV-112 Red Light ON 01-03 MSIV-112 Mimic Light OFF 01-03 MSIV-112 Mimic Light OFF

12. Place MSlV 7% Test Switch to the Rotate Test Switch to OFF. PasslFail OFF position.
13. Confirm 01-03 MSlV 112 White Test Observe White Test Light for MSIV- SatlUnsat Light OFF. 112 is OFF.
14. Confirm 01-03 MSlV 112 Yellow Light Observe Yellow Light for MSIV-112 is SaVUnsat OFF. OFF.
15. Depress REACTOR TRIP RESET at Depress Rx Trip RESET Button on E- Sat/Unsat Panel E. console.

Performance Steps Standard Grade

16. Check RPS Channel 11 Half-Scram is Verify the following:

CLEARED:

CHANNEL 11 SCRAM SOLENOID CHANNEL 11 SCRAM SOLENOID Groups 1,2,3,4 White Light ON. Groups 1,2,3,4 White Light ON.

CHANNEL 11 BACKUP SCRAM 0 CHANNEL 11 BACKUP SCRAM VALVE Red Light ON. VALVE Red Light ON.

Annunciator F1-1-7, RPS CH 11 0 Annunciator F1-1-7, RPS CH 11 MN MN STM LINE 11 ISOL VALVE STM LINE 11 ISOL VALVE CLOSED, CLOSED, Clear Clear Annunciator F1-2-1, RPS CH 11 0 Annunciator F1-2-1, RPS CH 11 AUTO REACTOR TRIP, Clear AUTO REACTOR TRIP, Clear

17. Condition Monitoring Group confirm all Contact Condition Monitoring Group Sat/Unsat scram pilot valve solenoids are for confirmation that all scram pilot energized by thermography. valve solenoids are energized by thermography.

Cue: As Condition Monitoring Group, report all scram solenoids have been confirmed to be energized by thermography.

18. Prepare to initiate a half scram on CHANNEL 12.

Verify no RPS Half Scram exists 0 Verify by all scram solenoid lights Pass/Fail energized Notify the CSO that the following Proper communications used. SaVUnsat steps will initiate the half scram on RPS CH 12.

19. Place Main Steam Isolation Valve 7% Test switch is rotated to the 121 Pass/Fail Test Switch to the 121 position. position.
20. Confirm 01-02 MSlV 121 white test 0 White test light for MSlV 121 is SaVUnsat light ON. verified energized.
21. Momentarily place 01-02 MSIV-121 Rotate switch for MSIV 121 PasdFail control switch to CLOSE position. momentarily to CLOSE then release.

Grade 022. Check RPS Channel 12 half scram Verify the following: SatlUnsat indications as follows:

0 CH 12 SCRAM SOLENOID CH 12 SCRAM SOLENOID GROUPS 1,2,3,4 White Light OFF. GROUPS 1,2,3,4 White Light CH 12 B.U. SCRAM S.D.V. VENT OFF.

AND DRAIN VALVE Light OFF CH 12 B.U. SCRAM S.D.V. VENT Annunciator F4-1-2, RPS CH 12 AND DRAIN VALVE Light OFF MNSM LINE 12 ISOL Valve Annunciator F4-1-2, RPS CH 12 CLOSED, alarms. MNSM LINE 12 ISOL Valve Annunciator F4-2-8, RPS CH 12 CLOSED, alarms.

AUTO REACTOR TRIP, alarms. Annunciator F4-2-8, RPS CH 12 AUTO REACTOR TRIP, alarms.

23. Confirm 01-02, MSIV-121 automatic 0 Verify the following: Sat/Unsat partial closure indications as follows:

01-02 MSIV-121 Green Light ON 01-02 MSIV-121 Green Light ON 0 01-02 MSIV-121 Red Light ON 01-02 MSIV-121 Red Light ON 0 01-02 MSIV-121 Mimic Light ON 01-02 MSIV-121 Mimic Light ON

24. Place MAIN STEAM ISOLATION Test switch is rotated to the OFF PasdFail VALVE 7% TEST switch to OFF position position.
25. Confirm 01-02 MSlV 121 White Test 0 White Test Light for MSIV-121 is OFF. SatlUnsat Light OFF.
26. Depress REACTOR TRIP RESET at Depress REACTOR TRIP RESET PasslFaiI Panel E. Button on E-console.
27. Check RPS Channel 12 half scram are Verify the following: Sat/U nsat cleared:

CH 12 SCRAM SOLENOID CH 12 SCRAM SOLENOID GROUPS 1,2,3,4 White Light ON. GROUPS 1,2,3,4 White Light ON.

CH 12 B.U. SCRAM S.D.V. VENT CH 12 B.U. SCRAM S.D.V. VENT AND DRAIN VALVE Light ON AND DRAIN VALVE Light ON Annunciator F4-1-2, RPS CH 12 Annunciator F4-1-2, RPS CH 12 MNSM LINE 12 ISOL Valve MNSM LINE 12 ISOL Valve CLOSED, clear. CLOSED, clear.

Annunciator F4-2-8, RPS CH 12 Annunciator F4-2-8, RPS CH 12 AUTO REACTOR TRIP, clear. AUTO REACTOR TRIP, clear.

28. Notifies SRO of status. Proper communication used SatlUnsat END OF JPM Terminating Cue: Nl-ST-Q26 completed for MSlV 01-03 & MSlV 01-02 RECORD STOP TIME
f.

Initial Conditions:

1. Plant is operating at 100% power with no inoperable equipment.
2. All prerequisites for the test are completed.
3. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), test Main Steam Line Isolation Valve 112 & 121 in accordance with Nl-ST-Q26, Section 8.2 & 8.3.

NINE MILE POINT NUCLEAR STATION OPERATOR JOB PERFORMANCE MEASURE

Title:

Lineup for RPV Injection using the Liquid Poison Test Tank Revision: NRC 2006 Task Number: 2009180504 Approvals:

NA EXAM SECURITY I Ge {e raI S upervi%r General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

TrainerlEvaluator:

Evaluation Method: Perform X Simulate Evaluation Location: X Plant Simulator Expected Completion Time: 15 min Time Critical Task: NO Alternate Path Task: NO Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

EvaIuators Signature: Date:

Unit 1 JPM 9 NRC November 2006

Reactor Building (RB Elec. 298) LP System pumps Simulator Set-up (if required):

NA Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a 0 .
2. During Evaluated JPM:

0 Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. N1-EOP-1 Attachment 12
2. NUREG 1123, 295031, EA1.08, 3.8/3.9 Tools and Equipment:
1. None Unit 1 JPM 9NRC November 2006

Task Standard: The Liquid Poison System is lined up for RPV injection utilizing the test tank.

Initial Conditions:

1. EOP-2 has been entered.
2. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), lineup the Liquid Poison System for RPV injection from the Test Tank in accordance with N1-EOP-1 , Attachment 12.

Performance Ste ps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat SaUUnsat Evaluator Acknowledge repeat back back (GAP-OPS-011CNG-HU-1.01-1001) providing correction if necessary, RECORD START TIME
2. Obtain a copy of the reference N1-EOP-1 Attachment 12 is obtained Sat/Unsat procedure and reviewhtilize the and referenced.

correct section of the procedure.

NOTE: VA-1 key (standard operations issued key) is required to unlock manual system valves.

3. Unlock and close 41-05. BV-LIQUID 41-05 unlocked and shut (fully PasslFail POISON TANK OUTLET. clockwise). Located in RB Elec 298.

Cue: 41-05 is shut.

4. Open 41-03, BV DEMIN WATER TO The test tank is approximately full and Pass/Fail LP TEST TANK and fill test tank with 41-03 is shut (full clockwise).

Demin Water.

Cue: Test Tank is full.

5. Unlock and open the following valves: 41-06 and 41-18 unlocked and Pass/FaiI 41-06, BV-LP PUMP 11 SUCTION opened (fully counterclockwise).

FROM TEST TANK 41-18, BV-LP PUMP 12 SUCTION FROM TEST TANK Cue: 41-06 and 41-18 open.

Unit 1 JPM 9NRC November 2006

Performance Steps Standard Grade

6. Control Room informed that LP is lined Control Room notified. SaUUnsat up for RPV injection using test tank.

Cue: Role play for communication, notify Operator that LP pump 12 has been started.

7. Throttle 41-03, BV DEMIN WATER Test tank level maintained at Pass/Fail TO LP TEST TANK to maintain tank approximately % full by throttling 41-approximately full. 03.

Cue: Test Tank level lowered and is now being maintained about Yi full.

8. Notify SRO of status. SRO notified of status. Sat/Unsat END OF JPM Terminating Cue: Liquid poison system is lined up for injection to the RPV utilizing the test tank.

RECORD STOP TIME Unit 1 JPM 9NRC November 2006

Initial Conditions:

1. EOP-2 has been entered.
2. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), lineup the Liquid Poison System for RPV injection from the Test Tank, in accordance with N1-EOP-1 , Attachment 12.

Unit 1 JPM 9NRC November 2006

NINE MILE POINT NUCLEAR STATION OPERATOR JOB PERFORMANCE MEASURE

Title:

Transfer UPS Loads from UPS162A to 162B (Alternate Path) Revision: NRC 2006 Task Number: 2620140101 NA EXAM SECURITY I General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer: (ROISRO)

TrainerIEvaluator:

EvaIuat ion Method : Perform X Simulate Evaluation Location: X Plant Simulator Expected Completion Time: 15 Minutes Time Critical Task: NO Alternate Path Task: YES Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if any critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 1 NRC November2006

Recommended Start Location: (Completion time based on the start location)

TB 261 between DG Room and Aux Control Room Simulator Set-up (if required):

None Directions to the InstructorlEvaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec.

Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Every JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated.

Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to perform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a e.
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. NUREG 1123, 212000, A2.02, RO 3.7, SRO 3.9
2. N1-OP-40, Reactor Protection and A l W S Systems
3. N1-SOP-40.1 - LOSS OF RPS Tools and Equipment:
1. None Task Standard: RPS Bus Transferred from UPS 162A to UPS 162B.

Unit 1 JPM 1 NRC November 2006

Initial Conditions:

1. Plant at 100% power
2. UPS 162A in service supplying RPS Bus 11
3. UPS 162B in standby
4. Instructor to ask operator for any questions Initiating Cues:

(Operators name), transfer RPS Bus 11 from UPS 162A to UPS 162B per N1-OP-40.

Performance Steps Standard Grade

1. Provide repeat back of initiating cue. Proper communications used for repeat Sat/Unsat Evaluator Acknowledge repeat back back (GAP-OPS-01/Operations Manual) providing correction if necessary.

RECORD START TIME

2. Obtain a copy of the reference N1-OP-40 obtained. Precautions & Sat/Unsat procedure and reviewhtilize the limitations reviewed & section F . l .O correct section of the procedure. referenced.
3. Notify Control Room that RPS Bus 11 Proper communications used for Sat/Unsat will be transferred from UPS 162A to repeat back per GAP-OPS-OI/Ops UPS 162B Manual.

Note: UPS 162 is on RB 250

4. At UPS 162B, verify UPS 162B in standby by observing the following:

Rectifier Output (A404) Rectifier Output on Rectifier Bay 1 Sat/Unsat approximately 40 amps reading 40 amps 0 Battery DC Input (AI) 0 amps Battery DC input on Inverter Bay 2 Sat/Unsat reading 0 amp.

Inverter Voltage (V2) 2 120 VAC 13 Inverter output on Inverter Bay 3 Sat/Unsat reads 120 VAC.

0 Static Switch Output (V202) 2 120 0 Static Switch Output on Static Bay 4 Sat/Unsat VAC reads 120 VAC.

Cue: A404 = 40 amps, A I = 0 amps V2 = 120 VAC, V202 = 120 VAC

5. Place in ON position, Synchroscope On Manual Transfer Switch Cab., Pass/Fail Control (S701) and verify the place Synchroscope Control toggle following: UPS A Volts (To switch in ON.

Synchroscope) approximately 120 Observe UPS A Volts to left of synch Sat/Unsat VAC. UPS B Volts (To Synchroscope) switch 120-122 VAC.

approximately 120 VAC Observe UPS B Volts to right of synch Sat/Unsat switch as 120-124 VAC Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade Cue: UPS A Volts = 120 VAC, UPS B Volts = 120 VAC Note: There is not expected to be a frequency or phase difference between UPS A and UPS B.

Therefore, the operator should expect the synchroscope to be at the 12 oclock position.

6. Verify synchroscope on Manual n Observe synchroscope on Manual Sat/Unsat Transfer Switch Cab. Rotating slowly Transfer Switch Cab. Rotating slowly in the FAST direction, or is at the 12 in the FAST (clockwise) direction, or is oclock position. at the 12 oclock position.

Cue: Sync Scope is at the 12 oclock position

7. When needle of synchroscope is Observe synchroscope at/within 10 PasslFail within 10 degrees of 12 oclock degrees before 12 oclock position position, then place Manual Transfer and firmly rotate switch Switch (S702) to the UPS B Supplying counterclockwise to the UPS B Load position. supplying Load protection.

Note: Operation of the manual transfer switch is a two handed operation

8. Confirm load transfer on the Manual At the Manual Transfer Switch Cab.

Transfer Switch Cab. By observing the observes the following following.

0 UPS A Supplying Load Light OFF Observe UPS A Supply Load Light Sat/Unsat extinguished.

AND/OR On Static Switch Bay 4 for UPS, Sat/Unsat UPS 162A Static Switch Output Observe Static Switch Output (A202) 0 amps ammeter for UPS 162A at 0 amps CUE: UPS A Supply Light is extinguished, A202 on UPS 162A = 0 amps UPS B Supplying Load Light ON Observe UPS B Supply Load Light SaVUnsat extinguished.

Observe Static Switch Output ammeter for UPS 162B at 0 amps. Sat/Unsat AN DIOR Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade UPS 162B Static Switch Output (A202) approximately 80-90 amps Cue: UPS B Supplying Light extinguished, Sat/Unsat A202 on UPS 162B = 0 amps

9. Verify no unanticipated annunciators Recognize unexpected condition and Sat/Unsat or computer points present due to contact the Control Room to inquire UPS 162B supply power. about any unexpected alarms or computer points received during transfer to UPS 162B supplying power.

Cue: Multiple unexpected alarms received in the control room. There is a YZ SCRAM on channel 11, execute N I -

SOP-40.1.

I O . Determine that RPS 11 was lost. Proceed to the correct step in N I - PasslFail SOP-40.1.

11. Contact the Control Room and Proper communication used. SatlUnsat determine if Computer Point GI83 (UPS 162 Prot Relay Oper-TRBL) is in alarm.

Cue: Computer Point GI83 (UPS 162 Prot Relay Oper-TRBL) is in alarm.

12. Verify I&C Bus 130A is available to Proper communication used. Sat/Unsat carry RPS Loads.

Cue: I&C Bus 130A is available to carry RPS loads.

13. Notify the CSO that dead bus transfer o Proper communication used. Sat/Unsat is to be performed.
14. Review list of affected systems in N I - Reviewed N 1-SOP-40.1 Sat/Unsat SOP-40.1, Loss of RPS Bus, for the RPS channel to be de-energized.

Cue: The list of affected systems has been reviewed

15. Review Attachment 6 AND current Contact Control Room to ensure N I - Sat/Unsat plant conditions for possible Technical SOP-40.1 Attachment 6 has been Specification impact reviewed for Technical Specification impact.

Cue: Attachment 6 and all Technical Specification impacts have been reviewed.

Unit 1 JPM 1 NRC November 2006

Performance Steps Standard Grade

16. Confirm NO '!hscram signals are Contact Control Room and notify the Sat/Unsat present OR anticipated due to testing CSO that you are transferring RPS on the opposite RPS Bus AND notify Bus # I 1 to I&C Bus 130A the CSO that performance of the following step will initiate a % scram
17. Open R.P.S. BUS # I 1 NORMAL Open R.P.S. BUS # I 1 NORMAL Pass/Fail SUPPLY FROM UPS 162 SUPPLY FROM UPS 162
18. Close R.P.S. BUS # I 1 Close R.P.S. BUS # I 1 Pass/Fail MAINTENANCE SUPPLY FROM I&C MAINTENANCE SUPPLY FROM I&C BUS 130A BUS 130A Cue: All other actions will be performed by another operator.
19. Report status to SRO SRO notified of status. Sat/Unsat END OF JPM Terminating Cue: Transfer of RPS Bus 11 from UPS 162 to I &C Bus 130A is complete.

RECORD STOP TIME Unit 1 JPM 1 NRC November 2006

Initial Conditions:

1. Plant at 100% power
2. UPS 162A in service supplying RPS Bus 11
3. UPS 162B in standby
4. Instructor to ask operator for any questions.

Initiating Cues:

(Operators name), transfer RPS Bus 11 from UPS 162A to UPS 162B per N 1-0P-40.

Unit 1 JPM 1 NRC November 2006

i\ii\t IVIILE ruiiu I IUULLLAK s I H I IUIU OPERATOR JOB PERFORMANCE MEASURE

Title:

Take Manual Control of. .12 Feedwater FCV Locally Revision: NRC 2006 Task Number: 2009090504 Atmrovals:

NA EXAM SECURITY I General Supervisor Date Operations Training (Designee) Operations (Designee)

NA EXAM SECURITY I Configuration Control Date Performer : (ROISRO)

T rainerlEvaIuator:

Evaluation Method: Perform X Simulate EvaIuation Location : X Plant Simulator Expected Completion Time: 15 minutes Time Critical Task: No Alternate Path Task: No Start Time: Stop Time: Completion Time:

JPM Overall Rating: Pass Fail NOTE: A JPM overall rating of fail shall be given if a critical step is graded as fail. Any grade of unsat or individual competency area unsat requires a comment.

Comments:

Evaluators Signature: Date:

Unit 1 JPM 3 NRC November 2006

Turbine Building (TI3 Elev. 291')

Simulator Set-up (if required):

Directions to the Instructor/Evaluator:

Prior to performance of this JPM, obtain SM / CSO general permission to open equipment cabinets and inspection covers. If opening the equipment cabinet or inspection cover will affect Tech. Spec. Operability, operational status, or the effects are unknown, obtain specific SM / CSO permission.

Directions to Operators:

Read Before Everv JPM Performance:

For the performance of this JPM, I will function as the SM, CSO, and Auxiliary Operators. Prior to providing direction to perform this task, I will provide you with the initial conditions and answer any questions. During task performance, I will identify the steps to be simulated, or discuss and provide cues as necessary.

With the exception of accessing panels, NO plant equipment will be physically manipulated. Repositioning of devices will be simulated by discussion and acknowledged by my cues.

Read Before Each Evaluated JPM Performance:

This evaluated JPM is a measure of your ability to pelform this task independently. The Control Room Supervisor has determined that a verifier is not available and that additional / concurrent verification will not be provided; therefore, it should not be requested.

Read Before Each Traininq JPM Performance:

During this Training JPM, the use of applicable methods of verification and checking are expected.

Therefore, either another individual or I will act as the independent verifier or peer checker.

Notes to Instructor / Evaluator:

1. Critical steps are identified in grading areas PasslFail. All steps are sequenced critical unless denoted by a ".".
2. During Evaluated JPM:

Self checking shall be demonstrated.

3. During Training JPM:

Self checking shall be demonstrated.

Peer checking shall be demonstrated.

References:

1. N1-OP-16, H.2.0 Tools and Equipment:

None Required Unit 1 JPM 3 NRC November 2006

Task Standard:

Feedwater FCV 12 placed in local manual control.

Initial Conditions:

1. Instrument air to FW FCV 12 has been lost.
2. FWP 12 is running, with its valve control M/A Station in manual.
3. RP has recently surveyed the area and you are cleared to access all valves.
4. Instructor to ask: Are there any questions?

Initiating cues:

(Operators name), place # I 2 FW FCV in local manual control in accordance with N1-OP-16.

Performance Steps Standard Grade

1. Provides repeat back of initiating cue. Proper communications used for SatlUnsat Evaluator Acknowledge repeat back repeat back (GAP-OPS-01) providing correction if necessary RECORD START TIME
2. Obtain a copy of the reference N1-OP-16 obtained. Precautions & SaWnsat procedure and reviewhtilize the correct limitations reviewed and section H.2.0 section of the procedure referenced.
3. Establish communication with Control Communications established with Sat/Unsat Room. Control Room.

Cue: Role play as Control Room with communications established. As CSO, direct operator to take local manual control of # I 2 Flow Control Valve.

4. Align upper hole in manual control collar Handwheel rotated and holes aligned PasslFail to hole in feedwater flow control valve on FW-12-FCV.

stem by rotating manual control handwheel.

Cue: Holes are aligned.

5. Insert control pin into manual control Pin is inserted into control collar. PasslFail collar hole.
6. Close the operator air supply valve (1/2 Recognize that a ladder is required. SatlUnsat valve). (1 13-1798, BV - IA to FW FCV
12) Handwheel rotated fully CW to close. PasslFail
7. Uncap and open operator top and Handwheels rotated fully CCW to PasslFail bottom piston vents. (29-234,29-236) open.

(29-234, Vent - IA to FW FCV 12 over piston and 29-36, Vent - IA to FW FCV Unit 1 JPM 3 NRC November 2006

PerfoFma nce Steps Standard Grade 12 under piston)

8. Notify CSO of status. CSO notified. Sat/Unsat Cue: Acknowledge report the task is complete.

END OF JPM Terminating Cue: FCV 12 is in local manual control RECORD STOP TIME Unit 1 JPM 3 NRC November 2006

Initial Conditions:

1. Inst. air to # I 2 FW FCV has been lost.
2. # I 2 FWP is running, with its valve control M/A Station in manual.
3. RP has recently surveyed the area and you are cleared to access all valves.
4. Instructor to ask: Are there any questions?

Initiating cues:

(Operators name), place # I 2 FW FCV in local manual control in accordance with N1-OP-16.