REFERENCES PROVIDED TO THE CANDIDATES FOR THE 2007 NRC EXAM Reactor Operator Examination

References:

I Question Reference Provided C-l8015-C, REACTOR VESSEL INSTRUMENT P & I DIAGRAM (With set points removed)

~~

Power to Flow Maps (3-Loop, 4-Loop & 5-LOOP)

N1-SOP-33A.1, LOSS OF 115KV N1-OP-25, CONDENSER AIR REMOVAL AND OFF-GAS SYSTEM, Section F only ARP L2-3 Power to Flow Maps (%LOOP, 4-LOOP & 5-Loop)

RO-64 N1-EOP-2T(With the ent conditions removed), RPV

!Y CONTROL, & Nl-EOP-8 , RPV BLOWDOWN RO-65 N1-EOP-3', FAILURE TO SCRAM 1 RO-75 N1

-~

-EOP-5'. SECONDARY CONTAINMENT CONTROL

'Enlarged EOP graphs and tables are also provided because they can be hard to read.

Senior Reactor 01 brator Examination

References:

Question Reference Provided Number SRO-1 EPIP-EPP-01, EAL MATRIX SRO-2 N1-EOP-4' w i t h the entry conditions removed), PRIMARY CONTAINMENT CONTROL SRO-6 EPIP-EPP-01, EAL MATRIX SRO-7 Nl-EOP-3', FAILURE TO SCRAM SRO-8 N1-EOP-2' (With the entry conditions removed), RPV CONTROL SRO-10 The steam tables and Technical Specifications 3.1.5*, 3.2.9*

and 3.6.1 1*

SRO-12 Technical Specification 3.6.2" SRO-13 Technical Specifications 3.1.5* and 3.6.2*

SRO-14 N1-EOP-2' (With the entry conditions removed), RPV CONTROL, N1-EOP-4T (With the entry conditions removed),

PRIMARY CONTAINMENT CONTROL, & N1-EOP-8T, RPV BLOWDOWN SRO-17 Technical Specifications 3.1.4* and 3.6.3*

SRO-18 N1-SOP-29.1, EOP KEY PARAMETER - ALTERNATE INSTRUMENTATION & Technical Specifications 3.6.11* and 3.6.13*

SRO-20 N1-EOP-2' (With the entry conditions removed), RPV CONTROL, N1-EOP-3T, FAILURE TO SCRAM Nl-EOP-4T (With the entry conditions removed), PRIMARY CONTAINMENT CONTROL

SRO-21 N1-EOP-2' (With the entry conditions removed), RPV CONTROL SRO-22 N l -EOP-4T(With the entry conditions removed), PRIMARY CONTAINMENT CONTROL, & N1-EOP-ST,STEAM COOLING SRO-24 T.S. 3.2.3" SRO-25 Nl-EOP-5', SECONDARY CONTAINMENT CONTROL TEnlarged EOP graphs and tables are also provided because they can be hard to read.