ML052030466

From kanterella
Jump to navigation Jump to search
U1R28 Today, Day 62
ML052030466
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 06/04/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML052030466 (2)


Text

NMC i &-74,'V W Commied to Nuclear Eircellenc'

,% - DAY Point Beach Refueling Outage Edition 62 TODAY

.e I . June 4, 2004

,I CONTACT INFORMATION Control Room Emergency -x291i I

Work Control Center - x6703 OCC - x 7190 - Option 1 Lessons Learned - x7190 - Option 2 Plant Status - x7190 .- Option 3 Accomplishments

  • Filled Main Generator with Hydrogen L jA I
  • Established a Vacuum in Main Generator
  • Enter Mode 3 Personnel Last 24 Hours Outa o . RCS Heatup to 3700 F Safety Date RCS Heatup to 450-40

. . Recordable - 0 Recordable - 1*

I Disabling - 0 Disabling - 0

'OSHA Recordable - Back strain.

Schedule Focus Areas/Priorities l, Last 24 Hours Outage to Date

  • RCS Heatup to NOT/NOP /

ALARA l'. 0.338 85.948 R

  • IT-230 RCS Pressure Test /
  • Resolve Leakage on 1MS-228, Header Dose as of the end of Day 60 Drain &Trap Isolation Inaccordhac w te dom fIomon V-74 At extmppo n s FOI goe- or

., . . . .. I 1. I I . .

June 4, 2004 OUTAGE GOALS NUCLEAR SAFETY.  : G PEFOM PERFORMANCE____NC - . - GOAL ACTUAL HUMAN PERFORMANCE GOAL ACTUAL Unplanned orangelred paths None None Security Violations s 12 loggable events 4 Reactor trips (either unit) None 1 Station human performance clock

-resets None . 4 Safeguards actuation (either unit) None None - Rework :51% On Goal Loss of shutdown cooling None None SCHEDULE PERFORMANCE Outage Duration ..... I L . .. . ,... .. . .

Loss of Rx.vessel level control None None (excludes extensions due to s 30 days Off Goal extended head or BMI inspections) .

INDUSTRIAL SAFETY Mod Implementation 100% of Rev 0 On Goal PERFORMANCE - ._._.

> 85% schedule Lost time accidents None None Schedule Compliance compliance with Off Goal outage milestone Personnel Injuries (OSHA recordable) None Emergent work (during . 2%late additions On Gcar implementation) . s 5% Emergent On_ __

RADIOLOGICAL PERFORMANCE Scope Complete 2 95% of On Goal

  • Rev 0 scope -

Radiation exposure (Excludes additional 100% of Scheduled dose from any head or BMI repair .. 92 R 85.948 R Operator Burdens Operator Burdens On Goal contingencies) ..complete Personnel contaminations 518w

>5K CPM 12 Post Outage availability c 150 days continuous peaton of operation Available at a Iaterdate Radiological events (defined as unplanned uptake w/assigned dose >10 mrem or *1 event 1 BUDGET PERFORMANCE Within -2%t0%o Seouly dose event based on ED alarms outage budget ., Challenged Radmaterial event (defined as any rad e material outside RCA:2 100 CPM)

Operating Experience OE9804 - Reactor Power Exceeded the Licensed Power Limit During saturation of a letdown ion exchanger, the operators did not maintain power below 100.0 percent. The Core Operating Limits Supervisory System (COLSS) alarm annunciated at 100.0 percent, and the operators did not take prompt action to reduce power to' clear the alarm. Although they were borating frequently, they were not aggressive enough to reduce power sufficiently to clear the alarm. Reactor power was'as high as 100.2 percent power with the COLSS alarm in solid for approximately 1 hours1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. The maximum shift average was 99.97 percent Rx power.

Lessons Leamed: Management's expectation was that the COLSS alarm would be promptly cleared. This expectation was not clearly understood by the operating crew. They erroneously felt that since they were actively borating, and reactor power was being controlled, they were meeting the intent of the ARP. In addition, the SRO was frequently distracted by activities he was supervising In support of a'refueling outage on the other unit.

'Human Performance Don't be left In the dark:

An RP Tech went to change out air samples on sping-24. Lighting was out in the area. When he went to turn off power to the pump, the switch wasn't working. The RPT was told in the past that if switch wasn't working, that we can open the electrical box on the back of the sping'irid that you can turn off the pump from there. The darkest area was behind the sping. He opened the electrical box in the dark and saw two switches, but couldn't read them. He then went to get a flashlight., With the flashlight, he read two switches and they both look like they said pump. He turned them both off and changed the samples. When he closed the electrical box with the flashlight, he saw a piece of duct tape on the outside of the door, showing to turn off the top switch.

When confronted with the two switches, the RPT should have stopped and asked for help.

Safety Snippet Never gamble with more than you can handle Two situations to review here. One was a RP worker and contractor trying to maneuver material through a security door. Rather than calling security, they figured they could 'beat the door.' They beat it all right. And the contractor suffered a leg injury from the steel hitting him. The second was an OAII carrying a large box through a door. She ended up catching hitting her hand on the doorframe. How can we prevent these injuries?