MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23135A7872023-05-19019 May 2023 Summary of Conference Calls Regarding the Spring 2023 Steam Generator Tube Inspections ML23026A3552023-01-31031 January 2023 Summary of Public Meeting with Energy Harbor Nuclear Corp. Regarding Beaver Valley Power Station License Amendment Request to Consolidate Fuel Decay Time TS Into New Limiting Condition for Operation ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML22105A3932022-04-20020 April 2022 Summ. of March 17, 2022, Public Meeting with Ehnc Regarding Planned License Amendment Request to Consolidate Fuel Decay Time Requirements in a New Limiting Condition for Operation for Beaver Valley Power Station, Units 1 and 2 ML22053A2982022-02-25025 February 2022 Summary of the February 15, 2022, Meeting with Energy Harbor Nuclear Corp. Regarding the License Amendment Request Related to Revising TS 5.6.3 Core Operating Limits Report (COLR) ML21308A0712021-11-0909 November 2021 Summary of Teleconference with Energy Harbor Nuclear Corp. Regarding Fall 2021 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20197A2722020-07-15015 July 2020 2020 Beaver Valley, Calvert Cliffs, Limerick Peach Bottom, Susquehanna Annual Assessment Webinar Summary ML20148M3852020-06-0101 June 2020 Summary of May 26, 2020, Public Meeting with Energy Harbor Nuclear Corp. Potential License Amendment Request Related to Steam Generator Tube Sleeve Inspections and Maintenance ML20122A0032020-05-19019 May 2020 Summary of April 22, 2020, Teleconference with Energy Harbor Nuclear Corp. Regarding Spring 2020 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML20111A0142020-04-27027 April 2020 Summary of March 31, 2020, Public Meeting with Energy Harbor Nuclear Corp. to Discuss COVID-19 Potential Submittals of Regulatory Actions ML16125A5072019-10-22022 October 2019 Ti 191 Issue Matrix ML19280A0382019-10-22022 October 2019 Ti 2515-191 Summary of Findings ML19191A1882019-07-0909 July 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - Meeting Summary ML18325A0232018-11-28028 November 2018 Summary of Teleconference with Firstenergy Nuclear Operating Company Regarding Fall 2018 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML18099A0812018-04-0606 April 2018 Bv Annual Assessment Meeting Summary and Attendance List 2018 ML17347A8082017-12-20020 December 2017 December 5, 2017, Summary of Public Meeting with Firstenergy Nuclear Operating Company to Discuss a Proposed License Amendment Request Extending Sleeve Life on the Steam Generator at Beaver Valley Power Station, Unit 2 ML17158B1662017-06-0909 June 2017 Summary of Meeting with Firstenergy Nuclear Operating Company Regarding the Spring 2017 Steam Generator Inspections at Beaver Valley Power Station, Unit 2 ML17082A1842017-03-28028 March 2017 March 20, 2017, Summary of Annual Assessment Meeting with Beaver Valley, Units 1 and 2 ML16250A5012016-10-0303 October 2016 Summary of August 30, 2016, Meeting with Firstenergy Nuclear Operating Company Regarding Planned Submittal of Emergency Action Level Scheme Change ML16105A0082016-04-25025 April 2016 March 30, 2016, Summary of Meeting with Firstenergy Nuclear Operating Company on Its Draft Probabilistic Risk Assessment RAI Related to Its License Amendment Request to Adopt NFPA Standard 805 ML16091A0702016-03-31031 March 2016 2016 Beaver Valley Annual Assessment Meeting Summary 2016 ML15320A3912015-11-24024 November 2015 Summary of Conference Call Regarding the Fall 2015 Steam Generator Inspections ML15225A4812015-08-14014 August 2015 July 23, 2015, Summary of Meeting with Representatives of the U.S. Army Corps, U.S. Nuclear Regulatory Commission and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station ML15135A2982015-05-21021 May 2015 Summary of April 28, 2015, Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and First Energy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Station, ML15104A6652015-04-14014 April 2015 April 9, 2015 Summary of Annual Assessment Meeting with Beaver Valley Power Station, Units 1 and 2 ML14325A7782014-12-16016 December 2014 October 6, 2014, Summary of Pre-Application Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Combination of Site Emergency Plans ML14184B1962014-08-14014 August 2014 Summary of June 18, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, Nuclear Regulatory Commission, and Firstenergy Nuclear Operating Co. to Discuss Flooding Analysis Associated with Beaver Valley Power Stat ML14160B1032014-07-10010 July 2014 June 6, 2014 Summary of Meeting with FENOC Flooding Hazard Reevaluation Extension Request for Beaver Valley Power Station, Units 1 and 2 and Flooding Hazard Reevaluation Report for Davis-Besse Nuclear Power Station, Unit 1 ML14142A0872014-06-0909 June 2014 Summary of Conference Call Regarding the Spring 2014 Steam Generator Inspections ML14099A1732014-04-0909 April 2014 Annual Assessment Meeting Summary, ROP14 ML13295A2182013-10-22022 October 2013 Summary of Public Meeting with Beaver Valley, ML13114A2072013-04-22022 April 2013 Summary of Annual Assessment Meeting at Beaver Valley ML13057A6782013-03-11011 March 2013 2/20/2013 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Proposed Request for Additional Information Response Regarding Beaver Valley Power Station End-of-Life Moderator Temperature Coefficient Testing ML12321A3012012-11-29029 November 2012 Summary of November 15, 2012, Meeting with Firstenergy Nuclear Operating Company to Discuss Upcoming License Amendment Request Relating to the Implementation of the Alternate Pressurized Thermal Shock Rule ML12310A0662012-11-13013 November 2012 Summary of Conference Call with Firstenergy Nuclear Operating Company to Discuss 2012 Steam Generator Tube Inspections ML12293A0402012-11-0101 November 2012 October 18, 2012 - Summary of Meeting with Firstenergy Nuclear Operating Company to Discuss Request for Additional Information Regarding Fenoc'S Extension Request for Upcoming Beaver Valley Power Station National Fire Protection Association ML12277A4082012-10-0303 October 2012 September 26, 2012, Summary of Public Meeting to Discuss FENOC Fleet Performance ML12223A4672012-08-22022 August 2012 August 1, 2012 - Summary of Meeting with FENOC to Discuss Upcoming National Fire Protection Association Standard 805 License Amendment Request Status ML12195A1132012-07-16016 July 2012 Summary of Public Meeting with FENOC Regarding Licensing Practices and Processes ML12104A1052012-04-13013 April 2012 Meeting Summary of Annual Assessment Meeting on March 22, 2012 ML1115805152011-06-15015 June 2011 (BVPS-2) - Summary of Conference Call Regarding the Spring 2011 Steam Generator Tube Inspection Results ML1112504622011-05-0505 May 2011 Summary of Annual Assessment Open House Public Meeting, Beaver Valley ML1035606612010-12-29029 December 2010 Summary of Beaver Valley Power Station, Unit 2 Public Conference Call Regarding Spent Fuel Pool Rerack LAR Draft RAI Responses Discussion ML1027903512010-10-18018 October 2010 Summary of Meeting with Firstenergy Nuclear Operating Company, on the Request for Additional Resposnses Regarding the Spent Fuel Rerack for Beaver Valley Power Station, Unit No. 2 ML1014105172010-05-21021 May 2010 Summary of the May 2010 Annual Assessment Open-House Public Meeting ML1013206652010-05-18018 May 2010 Summary of Category 1 Teleconference with Firstenergy Nuclear Operating Company to Discuss NRC Request for Additional Information Regarding Generic Letter 2004-02 ML1009502432010-04-0505 April 2010 Meeting Summary of 3-31-10 Public Meeting with FENOC ML0931407282009-11-18018 November 2009 Steam Generator Tube Inspections 2024-06-03
[Table view] |
Text
January 26, 2005 LICENSEE: FirstEnergy Nuclear Operating Company (FENOC)
FACILITY: Beaver Valley Power Station, Unit Nos. 1 and 2 (BVPS-1 and 2)
SUBJECT:
SUMMARY
OF DECEMBER 15, 2004, CATEGORY 1 WORKING-LEVEL MEETING WITH FENOC TO DISCUSS THE LICENSEES EXTENDED POWER UPRATE (EPU) SUBMITTAL DATED OCTOBER 4, 2004 (AGENCYWIDE DOCUMENTS ACCESS AND MANAGEMENT SYSTEM (ADAMS) ACCESSION NO. ML042920300)
On December 15, 2004, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC), and representatives of FENOC, the licensee for BVPS-1 and 2 and its contractors, Stone & Webster Corporation and Westinghouse Electric Company (Westinghouse) at the Westinghouse Washington Operations Office located at 12300 Twinbrook Parkway, Suite 330, Rockville, Maryland. The purpose of the meeting was to conduct a working-level discussion of the licensees October 4, 2004, EPU license amendment application for BVPS-1and 2.
FENOC presented information on its application and its interrelationship with other pending and future license amendment requests. It also discussed the research and development of the application, planned staged power ascension and testing, Updated Final Safety Analysis Report and NRC Review Matrix (RS-001) links, necessary plant modifications, BVPS-1 steam generator replacement, full implementation of the alternate source term, non-EPU changes, and implementation schedules.
Following the licensees prepared presentation, NRC staff reviewers and the licensees technical experts divided into breakout sessions to discuss specific general questions the NRC staff members had concerning the application. Members of the public in attendance observed the breakout sessions.
The business portion of the meeting concluded with the licensee requesting the status of the NRC staffs acceptance review of the licensees application. The NRC staff informed the licensee that the acceptance review was in progress and would be completed shortly. The letter documenting the acceptance review results was issued to the licensee on January 6, 2005 (ADAMS accession number ML043440113).
CONTACT: T. Colburn, NRR 301-415-1402 tgc@nrc.gov
FENOC One member of the public was in attendance, representing the State of Pennsylvania. Other members of the public represented the licensee for the R. E. Ginna Nuclear Power Plant.
Members of the public chose not to complete any Public Meeting Feedback Forms (NRC Form 659) which were available at the meeting. is a list of the meeting attendees, and Attachment 2 is a copy of the licensees slides presented at the meeting.
Please direct any inquiries to Messrs. Timothy G. Colburn, Senior Project Manager, at 301-415-1402, or John F. Stang, Lead Project Manager for power uprates, at 301-415-1345.
/RA/
Timothy G. Colburn, Senior Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412 Attachments: 1. List of Attendees
- 2. Licensees Handout cc w/atts: See next page
ML050110268 OFFICE PDI-1/PM PDI-2/LA PDIII-1/LPM PDI-1/SC NAME TColburn MOBrien JStang RLaufer DATE 1/13/05 1/14/05 1/24/05 1/25/05 LIST OF ATTENDEES CATEGORY 1 WORKING-LEVEL MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY (FENOC), ET AL.
LICENSE AMENDMENT APPLICATION FOR EXTENDED POWER UPRATE FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 DECEMBER 15, 2004, 9:00 AM-1:30 PM NAME ORGANIZATION
- 1. T. Colburn NRC/NRR/DLPM/PDI-1
- 2. R. Lobel NRC/NRR/SPSB
- 3. J. Stang NRC/NRR/DLPM/PDIII-1
- 4. W. Ruland NRC/NRR/DLPM/D:PDIII
- 5. J. Medoff NRC/NRR/DE/EMCB
- 6. S. Klementowicz NRC/NRR/IPSB
- 7. M. Rock NRC/NRR/IPSB
- 8. T. Scarbrough NRC/NRR/DE/EMEB
- 9. G. Makur NRC/NRR/DE/EMCB
- 10. R. Wolfgang NRC/NRR/DSSA/SPLB
- 11. I. Ahmed NRC/NRR/DE/EEIB
- 12. N. Patel NRC/NRR/DE/EEIB
- 13. S. Miranda NRC/NRR/DSSA/SRXB
- 14. P. Patnaik NRC/NRR/DE/EMCB
- 15. K. Martin NRC/NRR/DIPM/IROB
- 16. L. Fields NRC/NRR/DRIP/RLEP
- 17. S. Laur NRC/NRR/DSSA/SPSB
- 18. A. Stubbs NRC/NRR/DSSA/SPLB
- 19. R. Clark NRC/NRR/DLPM/PDI-1
- 20. Kenneth Frederick FENOC
- 21. Mike Testa FENOC
- 22. F. Schaffner FENOC
- 23. S. Sarver FENOC
- 24. C. Custer FENOC
- 25. H. Hegrat FENOC
- 26. J. DeBlasio Westinghouse Electric Company
- 27. R. Surman Westinghouse Electric Company
- 28. T. Madden Stone & Webster Corporation
- 29. N. Hanley Stone & Webster Corporation
- 30. S. Ferguson Stone & Webster Corporation
- 31. G. Wrobel Constellation Energy Group
- 32. C. Ciocca FENOC Contractor
- 33. L. Ryan Pennsylvania Bureau of Radiation Protection Attachment 1
MEETING SLIDES Attachment 2
Beaver Valley Power Station, Unit Nos. 1 and 2 cc:
Mary OReilly, Attorney Rich Janati, Chief FirstEnergy Nuclear Operating Company Division of Nuclear Safety FirstEnergy Corporation Bureau of Radiation Protection 76 South Main Street Deparment of Environmental Protection Akron, OH 44308 Rachel Carson State Office Building P.O. Box 8469 FirstEnergy Nuclear Operating Company Harrisburg, PA 17105-8469 Regulatory Affairs/Performance Improvement Mayor of the Borough of Shippingport Larry R. Freeland, Manager P O Box 3 Beaver Valley Power Station Shippingport, PA 15077 Post Office Box 4, BV-A Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission Commissioner James R. Lewis 475 Allendale Road West Virginia Division of Labor King of Prussia, PA 19406 749-B, Building No. 6 Capitol Complex Resident Inspector Charleston, WV 25305 U.S. Nuclear Regulatory Commission Post Office Box 298 Director, Utilities Department Shippingport, PA 15077 Public Utilities Commission 180 East Broad Street FirstEnergy Nuclear Operating Company Columbus, OH 43266-0573 Beaver Valley Power Station ATTN: R. G. Mende, Director Director, Pennsylvania Emergency Work Management (BV-IPAB)
Management Agency Post Office Box 4 2605 Interstate Dr. Shippingport, PA 15077 Harrisburg, PA 17110-9364 FirstEnergy Nuclear Operating Company Ohio EPA-DERR Beaver Valley Power Station ATTN: Zack A. Clayton Mr. B. F. Sepelak Post Office Box 1049 Post Office Box 4, BV-A Columbus, OH 43266-0149 Shippingport, PA 15077 Dr. Judith Johnsrud National Energy Committee Sierra Club 433 Orlando Avenue State College, PA 16803 J. H. Lash, Plant Manager (BV-IPAB)
FirstEnergy Nuclear Operating Company Beaver Valley Power Station Post Office Box 4 Shippingport, PA 15077