August 1, 2012 - Summary of Meeting with FENOC to Discuss Upcoming National Fire Protection Association Standard 805 License Amendment Request Status
ML12223A467
Person / Time
Site: Beaver Valley
Issue date: 08/22/2012
From: Peter Bamford
Plant Licensing Branch 1
To:
Bamford P
Shared Package
ML12223A456 List:
References
TAC ME9015, TAC ME9016
Download: ML12223A467 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 22, 2012 LICENSEE:

FirstEnergy Nuclear Operating Company FACILITY:

Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF AUGUST 1, 2012, MEETING WITH FIRSTENERGY NUCLEAR OPERATING COMPANY TO DISCUSS UPCOMING NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 LICENSE AMENDMENT REQUEST STATUS (TAC NOS. ME9015 AND ME9016)

On August 1, 2012, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of FirstEnergy Nuclear Operating Company (FENOC, the licensee). The purpose of the meeting was to discuss the status of a proposed future license amendment request (LAR) involving a transition to National Fire Protection Association Standard 805 (NFPA 805) for Beaver Valley Power Station (BVPS), Units 1 and 2. Specifically, the licensee provided notification to the NRC staff that the committed due date of September 30, 2012, for the subject NFPA 805 LAR, will not be met.

The licensee provided an explanation for the projected delay in the scheduled submission of the NFPA 805 LAR. Project challenges have included: Differences in the licensing basis and the plant design between the two BVPS units, an issue involving fire ignition sources in the BVPS, Unit 1 process rack area, as well as other challenges that were not anticipated when the commitment date of September 30,2012, was set. Detailed handout material from the meeting, explaining all of the issues of concern, may be found at Agencywide Documents Access and Management System Accession No. ML12215A415. The licensee's projected revised submission date for the NFPA 805 LAR was estimated to be in the fourth quarter of calendar year 2013. The NRC staff asked questions regarding the technical and scheduling challenges, as well as the licensee's plans to address the upcoming September 30, 2012, deadline. The NRC staff reminded the licensee that their original letter committing to the NFPA 805 process was dated December 22, 2005. The licensee stated that by the end of the current week they would communicate to the NRC a date for submission of a letter containing a formal request for extension of the deadline for the NFPA 805 LAR. This upcoming letter would contain the licensee's basis for a scheduled extension request, as well as a specific proposed submittal date.

No proprietary information was discussed at the meeting. No comments from members of the public participating in the meeting were received. A list of attendees is provided in the Enclosure.

- 2 Please direct any inquiries to me at 301-415-2833 or peter.bamford@nrc.gov.

~tk#

Peter Bamford Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosure:

List of Attendees cc w/encl: Distribution via ListServ

LIST OF ATTENDEES AUGUST 1, 2012, MEETING WITH FENOC TO DISCUSS UPCOMING NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 LICENSE AMENDMENT REQUEST STATUS AT BEAVER VALLEY POWER STATION, UNITS 1 AND 2 FENOC Henry Hegrat Darin Benyak Rich Bologna Carmen Mancuso Greg Halnon James Belfiore Richard Stremble Matt Murtha (via teleconference)

T om McCrary (via teleconference)

Joshua Ross (via teleconference)

Vern Patton (via teleconference)

Francy Mantine (via teleconference)

Sum Leung (via teleconference)

Bob Lubert (via teleconference)

PUBLIC (via teleconference)

Amy Hazelhoff, Enercon Paul Boulden, Appendix R Solutions Kevan Griffith, PKMJ Technical Services Eric Rasky, PKMJ Technical Services Matt Tobin, PKMJ Technical Services Ted Robinson, Citizen Power Mark Schairer, EPM Paul Guymer, Scientech Peter Bamford Gerald Gulla Leslie Fields Jeremy Bowen Stephen Dinsmore Benjamin Beasley Alex Klein Meena Khanna Charles Moulton Jay Robinson John Rogge (via teleconference)

Paul Lain (via teleconference)

Erin Bonney (via teleconference)

Aron Lewin(via teleconference)

Enclosure

- 2 Please direct any inquiries to me at 301-415-2833 or peter.bamford@nrc.gov.

/ra/

Peter Bamford Plant Licensing Branch 1-2 Division of Operating Reactor Licensing OfFice of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosure:

List of Attendees cc w/encl: Distribution via ListServ DISTRIBUTION:

PUBLIC Branch Reading RidsAcrsAcnw_MailCTR Resource RidsNrrDorlLpll-2 Resource RidsOgcRp Resource JRobinson,NRR ALewin, NRR RidsNrrPMBeaverValley Resource RidsNrrLAABaxter Resource RidsRgnlMailCenter Resource JBowen, NRR SDinsmore, NRR GGulla,OE RidsNrrDraApla Resource SKennedy, EDO Region I TWe rtz, NRR LFields, NRR EBonney, RI PLain, NRR JRogge, RI RidsNrrDraAfpb Resource ADAMS Accession Nos.: Package ML12215A400; Meeting Notice ML120050036; Meeting Handouts ML12215A415; Meeting Summary ML12223A467

'via email OFFICE NAME DATE DORLILPLI-2/PM DRAlAFPB/BC PBamford AKlein w/comment 08/13/12 08/17/12 DORLILPLI-2/LA DRAIAPLA/BC ABaxter

  • BBeasley 08/20/12 08/21/12 DORLILPLI-2/BC MKhanna 08/22/12 OFFICIAL RECORD COpy