Summary of the February 15, 2022, Meeting with Energy Harbor Nuclear Corp. Regarding the License Amendment Request Related to Revising TS 5.6.3 Core Operating Limits Report (COLR)
ML22053A298
Person / Time
Site: Beaver Valley
Issue date: 02/25/2022
From: Sujata Goetz
Plant Licensing Branch 1
To:
Energy Harbor Nuclear Corp
Goetz S
References
EPID L-2021-LLA-0075
Download: ML22053A298 (4)


Text

February 25, 2022 LICENSEE: Energy Harbor Nuclear Corp.

FACILITY: Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF THE FEBRUARY 15, 2021, MEETING WITH ENERGY HARBOR NUCLEAR CORP. REGARDING THE LICENSE AMENDMENT REQUEST RELATED TO REVISING TECHNICAL SPECIFICATION 5.6.3 CORE OPERATING LIMITS REPORT (COLR) (EPID L-2021-LLA-0075)

On February 15, 2021, a public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) staff and the representatives of Beaver Valley Power Station (the licensee) using Microsoft Teams meeting. The purpose of the meeting was to clarify questions the NRC had regarding the licencees response (Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21300A359) to the NRCs request for additional information (RAI) (ADAMS Accession No. ML21259A164). The meeting notice dated January 25, 2022, is available ADAMS Accession No. ML22013B283. A list of attendees is provided as an enclosure to this letter.

In the meeting, Energy Harbor clarified that the venturi-based feedwater flow measurements provided in the licensees RAI response were not adjusted to match the Leading Edge Flow Meter (LEFM) during the one-year analysis window. The licensee explained that the venturi-based feedwater flow measurements from the plant computer are to be used by operators to calculate calorimetric power when the LEFM is out of service.

The NRC questions were resolved during the meeting and the licensee was not asked to submit any documentation.

Members of the public were not in attendance. Public meeting feedback forms were not received.

Please direct any inquiries to me at 301-415-8004 or Sujata.Goetz@nrc.gov

/RA/

Sujata Goetz, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-314

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES CLARIFICATION MEETING WITH ENERGY HARBOR NUCLEAR CORP. REGARDING TECHNICAL SPECIFICATION 5.6.3 CORE OPERATING LIMITS REPORT (COLR) AT BEAVER VALLEY POWER STATION UNITS 1 AND 2 FEBRUARY 15, 2021 Name Affiliation Sue Goetz U.S. Nuclear Regulatory Commission (NRC)

Josh Kaizer NRC Ravi Grover NRC Jeremy Dean NRC Richard Stattel NRC James Danna NRC Phil Lashley Energy Harbor Sean Padgett Energy Harbor Curt Ciocca Energy Harbor Gary Cacciani Energy Harbor Dave McCreary Energy Harbor Chris Lord Energy Harbor David Hwang Energy Harbor Larry Winkler Pennsylvania Department of Environmental Protection Enclosure

ML22053A298 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NRR/DORL/LPL1/PM NAME SGoetz KZeleznock JDanna SGoetz DATE 02/22/2022 02/24/2022 2/25/2022 2/25/2022