Category:Decommissioning Funding Plan DKTs 30
MONTHYEAR3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0618-02, Site Specific Decommissioning Cost Estimate2018-06-27027 June 2018 Site Specific Decommissioning Cost Estimate 3F0318-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20172018-03-26026 March 2018 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning 3F0517-01, Decommissioning Funding Plan for ISFSIs2017-05-15015 May 2017 Decommissioning Funding Plan for ISFSIs 3F0316-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20152016-03-22022 March 2016 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2015 3F0315-04, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20142015-03-31031 March 2015 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2014 3F0314-03, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20132014-03-31031 March 2014 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2013 RA-13-006, H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports2013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports ML13091A0252013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports RA-12-013, Decommissioning Funding Status Report2012-03-26026 March 2012 Decommissioning Funding Status Report 3F1111-01, Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant2011-11-21021 November 2011 Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant ML1109503662011-03-31031 March 2011 Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-11-004, Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report2011-03-31031 March 2011 Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-09-002, Biennial Decommissioning Funding Status Report2009-03-25025 March 2009 Biennial Decommissioning Funding Status Report ML0708602102007-03-22022 March 2007 Progress Energy - Biennial Decommissioning Funding Status Report ML0315607272003-05-30030 May 2003 Biennial Decommissioning Funding Status Report ML0222802042002-08-0808 August 2002 Decommissioning Trust Fund Correction 2023-03-31
[Table view] Category:40
MONTHYEAR3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0522-03, Notification of Revised Decommissioning Cost Estimate2022-05-26026 May 2022 Notification of Revised Decommissioning Cost Estimate 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0321-06, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20202021-03-29029 March 2021 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2020 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0618-02, Site Specific Decommissioning Cost Estimate2018-06-27027 June 2018 Site Specific Decommissioning Cost Estimate 3F0318-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20172018-03-26026 March 2018 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning 3F0517-01, Decommissioning Funding Plan for ISFSIs2017-05-15015 May 2017 Decommissioning Funding Plan for ISFSIs 3F0316-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20152016-03-22022 March 2016 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2015 3F0315-04, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20142015-03-31031 March 2015 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2014 3F0314-03, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20132014-03-31031 March 2014 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2013 RA-13-006, H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports2013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports ML13091A0252013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports RA-12-013, Decommissioning Funding Status Report2012-03-26026 March 2012 Decommissioning Funding Status Report 3F1111-01, Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant2011-11-21021 November 2011 Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant RA-11-004, Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report2011-03-31031 March 2011 Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report ML1109503662011-03-31031 March 2011 Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-09-002, Biennial Decommissioning Funding Status Report2009-03-25025 March 2009 Biennial Decommissioning Funding Status Report 3F0608-06, Submittal of License Amendment Request 303, Revision 0: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis.2008-06-0303 June 2008 Submittal of License Amendment Request #303, Revision 0: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis. ML0708602102007-03-22022 March 2007 Progress Energy - Biennial Decommissioning Funding Status Report ML0315607272003-05-30030 May 2003 Biennial Decommissioning Funding Status Report 3F0902-06, Florida Power, Crystal River Unit 3 - License Amendment Request 271, Revision 1, Revised Improved Technical Specification (ITS) 3.7.18, for Two Inoperable Control Complex Chillers2002-09-20020 September 2002 Florida Power, Crystal River Unit 3 - License Amendment Request #271, Revision 1, Revised Improved Technical Specification (ITS) 3.7.18, for Two Inoperable Control Complex Chillers ML0222802042002-08-0808 August 2002 Decommissioning Trust Fund Correction 2023-03-31
[Table view] Category:50
MONTHYEAR3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0522-03, Notification of Revised Decommissioning Cost Estimate2022-05-26026 May 2022 Notification of Revised Decommissioning Cost Estimate 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0321-06, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20202021-03-29029 March 2021 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2020 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0618-02, Site Specific Decommissioning Cost Estimate2018-06-27027 June 2018 Site Specific Decommissioning Cost Estimate 3F0318-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20172018-03-26026 March 2018 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning 3F0517-01, Decommissioning Funding Plan for ISFSIs2017-05-15015 May 2017 Decommissioning Funding Plan for ISFSIs 3F0316-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20152016-03-22022 March 2016 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2015 3F0315-04, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20142015-03-31031 March 2015 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2014 3F0314-03, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20132014-03-31031 March 2014 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2013 RA-13-006, H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports2013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports ML13091A0252013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports RA-12-013, Decommissioning Funding Status Report2012-03-26026 March 2012 Decommissioning Funding Status Report 3F1111-01, Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant2011-11-21021 November 2011 Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant ML1109503662011-03-31031 March 2011 Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-11-004, Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report2011-03-31031 March 2011 Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-09-002, Biennial Decommissioning Funding Status Report2009-03-25025 March 2009 Biennial Decommissioning Funding Status Report ML0708602102007-03-22022 March 2007 Progress Energy - Biennial Decommissioning Funding Status Report ML0315607272003-05-30030 May 2003 Biennial Decommissioning Funding Status Report ML0222802042002-08-0808 August 2002 Decommissioning Trust Fund Correction 2023-03-31
[Table view] Category:70
MONTHYEAR3F0323-03, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2023-03-31031 March 2023 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0323-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20222023-03-29029 March 2023 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2022 3F0522-03, Notification of Revised Decommissioning Cost Estimate2022-05-26026 May 2022 Notification of Revised Decommissioning Cost Estimate 3F0322-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20212022-03-30030 March 2022 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2021 3F0321-06, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20202021-03-29029 March 2021 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2020 3F0320-04, Decommissioning Funding Plan for Independent Spent Fuel Storage Installation2020-03-19019 March 2020 Decommissioning Funding Plan for Independent Spent Fuel Storage Installation 3F0618-02, Site Specific Decommissioning Cost Estimate2018-06-27027 June 2018 Site Specific Decommissioning Cost Estimate 3F0318-01, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20172018-03-26026 March 2018 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2017 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning 3F0517-01, Decommissioning Funding Plan for ISFSIs2017-05-15015 May 2017 Decommissioning Funding Plan for ISFSIs 3F0316-02, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20152016-03-22022 March 2016 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2015 3F0315-04, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20142015-03-31031 March 2015 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2014 3F0314-03, Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 20132014-03-31031 March 2014 Annual Decommissioning and Irradiated Fuel Management Financial Status Report for 2013 RA-13-006, H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports2013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports ML13091A0252013-03-28028 March 2013 H. B. Robinson, Unit 2, Brunswick, Units 1 and 2, Shearon Harris, Unit 1, and Crystal River, Unit 3, Submittal of Biennial Decommissioning Financial Assurance Reports RA-12-013, Decommissioning Funding Status Report2012-03-26026 March 2012 Decommissioning Funding Status Report 3F1111-01, Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant2011-11-21021 November 2011 Document P23-1651-001, Rev. 0, Preliminary Decommissioning Cost Estimate for the Crystal River, Unit 3 Nuclear Generating Plant RA-11-004, Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report2011-03-31031 March 2011 Brunswick Unit 1 & 2, Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report ML1109503662011-03-31031 March 2011 Crystal River Unit 3, Shearon Unit 1, and H.B. Robinson Unit 2, Biennial Decommissioning Funding Status Report RA-09-002, Biennial Decommissioning Funding Status Report2009-03-25025 March 2009 Biennial Decommissioning Funding Status Report 3F0608-06, Submittal of License Amendment Request 303, Revision 0: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis.2008-06-0303 June 2008 Submittal of License Amendment Request #303, Revision 0: Revision to Final Safety Analysis Report Sections 5.4.3, Structural Design Criteria, and 5.4.5.3, Missile Analysis. ML0708602102007-03-22022 March 2007 Progress Energy - Biennial Decommissioning Funding Status Report ML0315607272003-05-30030 May 2003 Biennial Decommissioning Funding Status Report 3F0902-06, Florida Power, Crystal River Unit 3 - License Amendment Request 271, Revision 1, Revised Improved Technical Specification (ITS) 3.7.18, for Two Inoperable Control Complex Chillers2002-09-20020 September 2002 Florida Power, Crystal River Unit 3 - License Amendment Request #271, Revision 1, Revised Improved Technical Specification (ITS) 3.7.18, for Two Inoperable Control Complex Chillers ML0222802042002-08-0808 August 2002 Decommissioning Trust Fund Correction 2023-03-31
[Table view] Category:Letter
MONTHYEARML23342A0942024-01-0909 January 2024 Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commission'S Analysis of ADP CR3, Llc'S Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan ML21238A0952021-10-13013 October 2021 Issuance of Amendment No. 259 Approving the ISFSI-Only Emergency Plan, Revision Draft a IR 05000302/20210012021-08-12012 August 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021001 and 05000302/2021002 ML21182A1032021-07-0606 July 2021 Request for Additional Information (RAI) Related to the ISFSI-Only Emergency Plan ML21159A0422021-06-28028 June 2021 VY and CR Indirect License Transfer Package ML21060B4142021-04-12012 April 2021 U.S. Nuclear Regulatory Commission Analysis of Duke Energy Florida, Llc'S Initial Decommissioning Funding Plan for the Crystal River Independent Spent Fuel Storage Installation ML21028A5912021-03-0202 March 2021 Letter to Reid Forwarding Exemption from 10 CFR Part 20, Appendix G, Section Iii.E ML21055A7832021-02-25025 February 2021 Letter to Reid, Change in NRC Staff Project Management for Crystal River Unit 3 Nuclear Generating Plant ML21012A3142021-01-13013 January 2021 Independent Spent Fuel Storage Installation Security Inspection Plan IR 05000302/20200012020-11-19019 November 2020 NRC Inspection Report No. 05000302/2020001, Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, Crystal River, Florida ML20269A2922020-10-0707 October 2020 NRC Form 311 QA Program Approval Revision 10 Related to Crystal River 3 ML20101G5822020-04-10010 April 2020 CR-3 License Transfer SE Corrected Cover Letter ML20069A0232020-04-0101 April 2020 Order Approving Transfer of Licensed Authority from Duke Energy Florida, LLC, to ADP CR3, LLC, and Draft Conforming Administrative License Amendment ML20050D0142020-02-19019 February 2020 NRC Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2020001, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML20050F7702020-02-14014 February 2020 30-Day Notice of Payment from the City of Tallahassee Trust Fund Non-Qualified Nuclear Decommissioning Trust Fund for Crystal River Unit 3 ML20015A5672020-01-15015 January 2020 Independent Spent Fuel Storage Installation Security Inspection Plan ML20009D0432020-01-10010 January 2020 Letter to Hobbs, Crystal River Unit 3 Nuclear Generating Plant - Corrected Safety Evaluation for Approval of Partial Site Release for Facility Operating License No. DPR-72 ML19339G5092020-01-0202 January 2020 Letter to Hobbs, Crystal River Unit 3 Nuclear Generating Plant - Approval of Partial Site Release for Facility Operating License No. DPR-72 ML19343A8252019-12-0606 December 2019 Letter from Erika Bailey, Oak Ridge Institute for Science and Education, to John Hickman, NRC, Forwarding Independent Confirmatory Survey Summary and Results for the 3,854-Acre Area Partial Site Release at the Crystal River Energy Complex IR 05000302/20190022019-11-20020 November 2019 NRC Inspection Report No. 05000302/2019002 and Independent Spent Fuel Storage Installation Inspection Report No. 07201035/2019002, Duke Energy Florida, LLC, Crystal River Unit 3, Crystal River, Florida ML19317D0932019-10-25025 October 2019 Engine Systems, Inc., 10CFR21 Reporting of Defects and Non-Compliance - Engine Systems, Inc. Report No. 10 CFR21-0127, Rev. 0, Emd Fuel Injectors - Seized Plunger and Bushing ML19261A0702019-09-19019 September 2019 VEGP U3 Proficiency Watches Prior to Fuel Load ML19177A0802019-06-26026 June 2019 Nuclear Generating Plant (CR-3) - Notification of Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR) ML19170A1942019-06-14014 June 2019 Application for Order Consenting to Direct Transfer of Control of Licenses and Approving Conforming License Amendment ML19129A1402019-05-15015 May 2019 Letter to Hobbs, Correction to Amendment No. 257 Approving Independent Spent Fuel Storage Installation (ISFSI)-Only Emergency Plan, Revision 1 2024-01-09
[Table view] |
Text
Progress Energy 10 CFR 50.75(f)(1)
, Progress Energy PO Box 1551 411 Fayelteville Street Mall Raleigh NC 27602 Serial: PE&RAS-03-060 May 30, 2003 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302 / LICENSE NO. DPR-72 BIENNIAL DECOMMISSIONING FUNDING STATUS REPORT Ladies and Gentlemen:
As requested by the NRC, Progress Energy Florida, Inc. (PEF) (also known as Florida Power Corporation) submits this status report for funding the decommissioning of the Crystal River Unit 3 Nuclear Generating Plant (CR3). PEF had last submitted this report on March 28, 2002 and, pursuant to 10 CFR 50.75(f)(1), had not intended to submit this biennial report again until 2004. As a result of this requested submittal, PEF now plans to submit the next report prior to March 31, 2005.
As of December 31, 2002, the total PEF assets in the trust funds, qualified and non-qualified, were approximately allocated as 58%, 28%, and 14% for Domestic Fixed Income, Domestic Equity, and International Equity, respectively.
This document contains no new regulatory commitment.
The status report from each CR3 Participant is enclosed as a convenience to the NRC. However, none of the Participants assumes any responsibility for the information contained in any other Participants report.
Please contact me at (919) 546-6901 if you need additional information concerning this report.
Sin erely, Omes W. Holt Manager - Performance Evaluation & Regulatory Affairs HAS
Attachment:
Status of Financial Assurance Mechanism, Crystal River Unit 3 Nuclear Generating Plant fNdl
United States Nuclear Regulatory Commission PE&RAS-03-060 Page 2
Enclosures:
- City of Alachua Status Report for Decommissioning Financial Assurance
- City of Bushnell Status Report for Decommissioning Financial Assurance
- City of Gainesville Status Report for Decommissioning Financial Assurance
- City of Kissimmee Status Report for Decommissioning Financial Assurance
- City of Leesburg Status Report for Decommissioning Financial Assurance
- City of New Smyrna Beach Status Report for Decommissioning Financial Assurance
- City of Ocala Status Report for Decommissioning Financial Assurance
- Orlando Utilities Commission Status Report for Decommissioning Financial Assurance
- Seminole Electric Cooperative, Inc. Status Report for Decommissioning Financial Assurance c: L. A. Reyes, Regional Administrator - Region II J. S. Stewart, USNRC Senior Resident Inspector - CR3 B. L. Mozafari, NRR Project Manager - CR3 E. L. Jacobs, Jr., Florida Public Service Commission
United States Nuclear Regulatory Commission PE&RAS-03-060 Page 3 Attachment Progress Energy Florida, Inc.
Status of Financial Assurance Mechanism Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 / License No. DPR-72
- Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)
$326,444,217 at expiration of current license, December 3, 2016 Progress Energy Florida, Inc. share (91.7806%) = $299,612,461
- Amount of decommissioning funds accumulated as of December 31, 2002
$299,612,461 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration.)
- Schedule of the annual amounts remaining to be collected None
- Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections Rate of escalation in decommissioning costs = 0%
Rate of earnings on decommissioning funds = 2%
None
- Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None
- Material changes to trust agreements None
CITY OF ALACHUA Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of Alachua share (0.07779%) = $254,300.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$254,300 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed Cost Escalation Rate is 5.3%.
The assumed eamings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.50%
for the rest.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
CITY OF BUSHNELL Status of Financial Assurance Mechanism Crystal River Plant - Docket No. 50-302 I License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of Bushnell share (0.03880%) = $126,660.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$126,660. (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed Cost Escalation Rate is 5.3%.
The assumed eamings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.50%
for the rest.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
CITY OF GAINESVILLE Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of Gainesville share (1.04079%) = $4,596,008.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$4,596,008 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed Cost Escalation Rate is 5.3%.
The assumed eamings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.50%
for the rest.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
CITY OF KISSIMMEE Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 1 License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of Kissimmee share (0.6754%) = $2,204,804.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$2,204,804. (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed Cost Escalation Rate is 5.3%.
The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.50%
for the rest.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
CITY OF LEESBURG Status of Financial Assurance Mechanism Crystal River Plant - Docket No. 50-3021 License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of Leesburg share (0.8244%) = $2,691,206.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$2,691,206 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed Cost Escalation Rate is 5.3%.
The assumed eamings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.50%
for the rest.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
CITY OF NEW SMYRNA BEACH Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
City of New Smyma Beach share (0.5608 %) = $1,830,699.17.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$1,895,961 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed cost escalation rate is 4.00%.
The assumed earnings rate is 3.75%.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
ORLANDO UTILITIES COMMISSION Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 1 License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
Orlando Utilities Commission share (1.6020%) = $5,229,636.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$5,229,636. (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected:
None
- 4) Assumptions:
The assumed cost escalation rate is 5.0%.
The assumed eamings rate is 5.5%.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None
SEMINOLE ELECTRIC COOPERATIVE, INC.
Status of Financial Assurance Mechanism Crystal River Plant - Docket No. 50-302 / License No. DPR-72
- 1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 10.
$326,444,217 at expiration of current license on December 3, 2016.
Seminole Electric Cooperative, Inc. share (1.6994%) = $5,547,593.
- 2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2002:
$4,740,732 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)
- 3) Annual amounts remaining to be collected (in 2000 $):
2003 $62,067 2004 $62,.067 2005 $62 067 2006 $62.067 2007 $62,067 2008 $62,067 2009 $62,067 2010 $62.,067 2011 $62,067 2012 $62 067 2013 $62,067 2014 $62,067 2015 $62,067 2016 $0
- 4) Assumptions:
The assumed cost escalation rate is 5.27%.
The assumed eamings rate is 8.00%.
- 5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):
None
- 6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:
None
- 7) Material changes to trust agreements:
None