RA-09-002, Biennial Decommissioning Funding Status Report

From kanterella
Jump to navigation Jump to search
Biennial Decommissioning Funding Status Report
ML090920407
Person / Time
Site: Harris, Brunswick, Crystal River, Robinson  Duke Energy icon.png
Issue date: 03/25/2009
From: Mccabe B
Progress Energy Carolinas, Progress Energy Florida
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-09-002
Download: ML090920407 (20)


Text

Progress Energy 10 CFR 50.75(f)(1)

PO Box 1551 411 Fayetteville Street Mall Raleigh NC 27602 Serial: RA-09-002 March 25, 2009 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 / LICENSE NOS. DPR-71 AND DPR-62 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302 / LICENSE NO. DPR-72 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 / LICENSE NO. NPF-63 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 / LICENSE NO. DPR-23 BIENNIAL DECOMMISSIONING FUNDING STATUS REPORT Ladies and Gentlemen:

Pursuant to 10 CFR 50.75(f)(1), Carolina Power & Light Company, now doing business as Progress Energy Carolinas, Inc. (PEC), and Florida Power Corporation, now doing business as Progress Energy Florida, Inc. (PEF), submit this biennial status report for funding the decommissioning of each reactor listed above. The specific information required by 10 CFR 50.75(f)(1) is listed on Attachments 1 through 5.

Pursuant to 10 CFR 50.75(e)(1)(ii), Carolina Power & Light Company has authorization from the rate-setting authority of North Carolina to use a real rate of return greater than 2% for the North Carolina portion of the qualified decommissioning trust fund. In particular, the Public Staff of the North Carolina Utilities Commission (NCUC) reviewed the 2004 Decommissioning Cost and Funding Report filed on July 20, 2005, which indicated a projected net-of-tax rate of return of 7.3% for the qualified decommissioning trust fund and a projected cost escalation rate of 4% (resulting in a real rate of return of 3.3%). The Public Staff subsequently filed a report to the NCUC on January 25, 2006, in which they stated, "The projected rates of return appear to be within a reasonable range and are appropriate for the 2004 Cost Studies."

As of December 31, 2008, the total assets in the Carolina Power & Light Company qualified decommissioning trust funds were approximately allocated as 49%, 39%, aind 12% in Domestic Equity, Domestic Fixed Income, and International Equity, respectively. As of December 31, 2008, the total assets in the Carolina Power & Light Company non-qualified decommissioning trust funds were approximately allocated as 100% in Municipal Bonds.

Aoo(

United States Nuclear Regulatory Commission RA-09-002 Page 2 As of December 31, 2008, the total assets in the Florida Power Corporation qualified decommissioning trust funds were approximately allocated as 53%, 31%, and 16% in Domestic Equity, Domestic Fixed Income, and International Equity, respectively. As of December 31, 2008, the total assets in the Florida Power Corporation non-qualified decommissioning trust funds were approximately allocated as 100.0%

in Municipal Bonds.

This document contains no new regulatory commitment.

As a convenience to the NRC, the biennial status report from the North Carolina Eastern Municipal Power Agency (NCEMPA) is enclosed for funding the decommissioning of the reactors, which are identified in Attachments 2, 3, and 4. However, neither co-owner assumes any responsibility for the information contained in the other's report.

Also enclosed, as a convenience to the NRC, is the status report from each co-owner for funding the decommissioning of the reactor identified in Attachment 5. However, none of the co-owners assumes any responsibility for the information contained in any other co-owner's report.

Please contact me at (919) 546-4579 if you need additional information concerning this report.

Sincerely, C eCL Cvn Brian McCabe Manager - Nuclear Regulatory Affairs DBM

'2

United States Nuclear Regulatory Commission RA-09-002 Page 3 Attachments:

" Attachment 1, Status of Financial Assurance Mechanism, H. B. Robinson Steam Electric Plant, Unit No. 2

" Attachment 2, Status of Financial Assurance Mechanism, Brunswick Steam Electric Plant, Unit No. 1

" Attachment 3, Status of Financial Assurance Mechanism, Brunswick Steam Electric Plant, Unit No. 2

" Attachment 4, Status of Financial Assurance Mechanism, Shearon Harris Nuclear Power Plant, Unit No. 1

" Attachment 5, Status of Financial Assurance Mechanism, Crystal River Unit 3 Nuclear Generating Plant

Enclosures:

" North Carolina Eastern Municipal Power Agency, Status of Financial Assurance Mechanism (3 pages)

" City of Alachua, Status of Financial Assurance Mechanism (1 page)

" City of Bushnell, Status of Financial Assurance Mechanism (1 page)

" City of Gainesville, Status of Financial Assurance Mechanism (1 page)

" City of Kissimmee, Status of Financial Assurance Mechanism (1 page)

  • City of Leesburg, Status of Financial Assurance Mechanism (1 page)

" City of New Smyrna Beach, Status of Financial Assurance Mechanism (1 page)

" City of Ocala, Status of Financial Assurance Mechanism (1 page)

" Orlando Utilities Commission, Status of Financial Assurance Mechanism (1 page)

  • Seminole Electric Cooperative, Inc., Status of Financial Assurance Mechanism (1 page) c:

L. Reyes, Regional Administrator - Region II USNRC Resident Inspector - BSEP, Unit Nos. 1 and 2 USNRC Resident Inspector - CR3 USNRC Resident Inspector - SHNPP, Unit No. 1 USNRC Resident Inspector - HBRSEP, Unit No. 2 F. Saba, NRR Project Manager - BSEP, Unit Nos. 1 and 2; CR3 M. Vaaler, NRR Project Manager - SHNPP, Unit No. 1; HBRSEP, Unit No. 2 M. M. Carter, II - Chairman, Florida Public Service Commission E. S. Finley, Jr. - Chairman, North Carolina Utilities Commissionf R. Vance - North Carolina Utilities Commission S. Watson - North Carolina Utilities Commission W. L. Cox, III - Acting Section Chief, Radiation Protection Section, North Carolina Department of Environmental and Natural Resources

United States Nuclear Regulatory Commission to RA-09-002 Page 1 of 1 Attachment 1 Status of Financial Assurance Mechanism H. B. Robinson Steam Electric Plant, Unit No. 2 Docket No. 50-261 / License No. DPR-23

  • Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)

$374.2 million at expiration of current license, July 31, 2030

$243.1 million estimated to be required from North Carolina

$131.1 million estimated to be required from All Others

" Amount of decommissioning funds accumulated as of December 31, 2008: $199,782,640

$96,722,580 Qualified Funds accumulated from North Carolina

$35,129,794 Non-Qualified Funds accumulated from North Carolina

$67,930,266 Funds accumulated from All Others

  • Schedule of the annual amounts remaining to be collected NRC Required Minimum: $0.2 million

$0 million required annually from North Carolina

$0.2 million required annually from All Others Allowed by North Carolina Utilities $9,668,420 Commission and Public Service $7,879,432 to be collected annually from North Carolina Commission of South Carolina: $1,788,988 to be collected annually from South Carolina Under wholesale contracts: $1,546,458 (contribution is not credited in future years)

" Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates .ofother factors used in funding projections Rate of escalation in decommissioning costs = 0 %

Rate of earnings on decommissioning funds = 3.3 % (North Carolina Qualified Fund) 2.0 % (North Carolina Non-Qualified Fund) 2.0 % (All Other Contributions)

For wholesale contracts, the resultant assumed real rate of return of 2% is only applicable to funds accumulated from previous contributions associated with those contracts.

None

" Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None

" Material changes to trust agreements Carolina Power & Light Company Trust Agreement was amended on May 1, 2008 to allow contributions to the funds in cash or securities, and to allow the assets to be used to satisfy expenses for early decommissioning of components of the nuclear units as long as in compliance with IRS and NRC Regulations.

United States Nuclear Regulatory Commission to RA-09-002 Page 1 of 1 Attachment 2 Status of Financial Assurance Mechanism Brunswick Steam Electric Plant, Unit No. 1 Docket No. 50-325 / License No. DPR-71

" Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)

$549.7 million at expiration of current license, September 8, 2036 Progress Energy Carolinas, Inc. share (81.67%) = $448.9 million

$291.7 million estimated to be required from North Carolina

$157.2 million estimated to be required from All Others

" Amount of decommissioning funds accumulated as of December 31, 2008: $156,365,737

$82,643,540 Qualified Funds accumulated from North Carolina

$15,678,995 Non-Qualified Funds accumulated from North Carolina

$58,043,202 Funds accumulated from All Others

  • Schedule of the annual amounts remaining to be collected NRC Required Minimum: $1.0 million

$0 million required annually from North Carolina

$1.0 million required annually from All Others Allowed by North Carolina Utilities $952,765 Commission and Public Service $710,564 to be collected annually from North Carolina Commission of South Carolina: $242,201 to be collected annually from South Carolina Under wholesale contracts: $1,436,815 (contribution is not credited in future years)

" Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections Rate of escalation in decommissioning costs = 0%

Rate of earnings on decommissioning funds = 3.3% (North Carolina Qualified Fund) 2.0% (North Carolina Non-Qualified Fund) 2.0% (All Other Contributions)

For wholesale contracts, the resultant assumed real rate of return of 2% is only applicable to funds accumulated from previous contributions associated with those contracts.

" Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v)

None

" Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None

" Material changes to trust agreements Carolina Power & Light Company Trust Agreement was amended on May 1, 2008 to allow contributions to the funds in cash or securities, and to allow the assets to be used to satisfy expenses for early decommissioning of components of the nuclear units as long as in compliance with IRS and NRC Regulations.

United States Nuclear Regulatory Commission to RA-09-002 Page 1 of 1 Attachment 3 Status of Financial Assurance Mechanism Brunswick Steam Electric Plant, Unit No. 2 Docket No. 50-324 / License No. DPR-62

  • Amount of decommissioning funds estimated to be required pursuant to 10 CFR 5 0.75(b) and (c)

$549.7 million at expiration of current license, December 27, 2034 Progress Energy Carolinas, Inc. share (81.67%) = $448.9 million

$291.7 million estimated to be required from North Carolina

$157.2 million estimated to be required from All Others

  • Amount of decommissioning funds accumulated as of December 31, 2008: $170,587,335

$94,129,798 Qualified Funds accumulated from North Carolina

$12,176,519 Non-Qualified Funds accumulated from North Carolina

$64,281,018 Funds accumulated from All Others

  • Schedule of the annual amounts remaining to be collected NRC Required Minimum: $0.7 million

$0 million required annually from North Carolina

$0.7 million required annually from All Others Allowed by North Carolina Utilities $678,033 Commission and Public Service $445,886 to be collected annually from North Carolina Commission of South Carolina: $232,147 to be collected annually from South Carolina Under wholesale contracts: id, /01, I1L .contrlrUtuon is not crecated in Iuture years)

  • Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections Rate of escalation in decommissioning costs = 0%

Rate of earnings on decommissioning funds = 3.3% (North Carolina Qualified Fund) 2.0% (North Carolina Non-Qualified Fund) 2.0% (All Other Contributions)

For wholesale contracts, the resultant assumed real rate of return of 2% is only applicable to funds accumulated from previous contributions associated with those contracts.

None Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None

  • Material changes to trust agreements Carolina Power & Light Company Trust Agreement was amended on May 1, 2008 to allow contributions to the funds in cash or securities, and to allow the assets to be used to satisfy expenses for early decommissioning of components of the nuclear units as long as in compliance with IRS and NRC Regulations.

United States Nuclear Regulatory Commission to RA-09-002 Page 1 of 1 Attachment 4 Status of Financial Assurance Mechanism Shearon Harris Nuclear Power Plant, Unit No. 1 Docket No. 50-400 / License No. NPF-63

" Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)

$393.5 million at expiration of current license, October 24, 2046 Progress Energy Carolinas, Inc. share (83.83%) = $329.9 million

$214.3 million estimated to be required from North Carolina

$115.6 million estimated to be required from All Others

" Amount of decommissioning funds accumulated as of December 31, 2008: $145,301,329

$80,085,248 Qualified Funds accumulated from North Carolina

$20,146,143 Non-Qualified Funds accumulated from North Carolina

$45,069,938 Funds accumulated from All Others

" Schedule of the annual amounts remaining to be collected NRC Required Minimum: $0.1 million

$0 million required annually from North Carolina

$0.1 million required annually from All Others Allowed by North Carolina Utilities $13,885,194 Commission and Public Service $11,497,075 to be collected annually from North Carolina Commission of South Carolina: $2,388,119 to be collected annually from South Carolina Under wholesale contracts: $992,061 (contribution is not credited in future years)

" Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections Rate of escalation in decommissioning costs = 0%

Rate of earnings on decommissioning funds = 3.3% (North Carolina Qualified Fund) 2.0% (North Carolina Non-Qualified Fund) 2.0% (All Other Contributions)

For wholesale contracts, the resultant assumed real rate of return of 2.0% is only applicable to funds accumulated from previous contributions associated with those contracts.

None

" Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None

" Material changes to trust agreements Carolina Power & Light Company Trust Agreement was amended on May 1, 2008 to allow contributions to the funds in cash or securities, and to allow the assets to be used to satisfy expenses for early decommissioning of components of the nuclear units as long as in compliance with IRS and NRC Regulations.

United States Nuclear Regulatory Commission to RA-09-002 Page 1 of 1 Attachment 5 Status of Financial Assurance Mechanism Crystal River Unit 3 Nuclear Generating Plant Docket No. 50-302 / License No. DPR-72

" Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c)

$383.5 million at expiration of current license, December 3, 2016 Progress Energy Florida, Inc. share (91.7806%) = $352.0 million

" Amount of decommissioning funds accumulated as of December 31, 2008:

$351,999,146 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration.)

" Schedule of the annual amounts remaining to be collected None

" Assumptions used regarding rates of escalation in decommissioning costs, rates of earnings on decommissioning funds, and rates of other factors used in funding projections Rate of escalation in decommissioning costs = 0%

Rate of earnings on decommissioning funds = 2%

" Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v)

None

  • Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report None

" Material changes to trust agreements Florida Power Corporation Trust Agreement was amended on May 1, 2008 to allow contributions to the funds in cash or securities, and to allow the assets to be used to satisfy expenses for early decommissioning of components of the nuclear unit as long as in compliance with IRS and NRC Regulations.

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 3 NORTH CAROLINA EASTERN MUNICIPAL POWER AGENCY SUBMITTAL Status of Financial Assurance Mechanism Brunswick Steam Electric Plant, Unit No. 1 (BNP) Docket No. 50-325 1 License No. DPR-71 The following information is submitted in accordance with 10 CFR 50.75(c):

" Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b), (c) and NUREG-1307, Rev. 13:

$549.7 million; NCEMPA Share (18.33%) = $100.8 million

" The fund balance for the amount accumulated as of December 31, 2008:

$ 74,504,413

  • Sum of the annual amounts remaining to be collected:

$ 6,945,000 (through September 8, 2036)

  • Assumptions:

Escalation rate in decommissioning costs = 4.0%

Earnings rate on decommissioning funds = 6.0%

None

  • Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report.

None

  • Material changes to trust agreements.

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 2 of 3 NORTH CAROLINA EASTERN MUNICIPAL POWER AGENCY SUBMITTAL Status of Financial Assurance Mechanism Brunswick Steam Electric Plant, Unit No. 2 (BNP) Docket No. 50-324 1 License No. DPR-62 The following information is submitted in accordance with 10 CFR 50.75(c):

$549.7 million; NCEMPA Share (18.33%) = $100.8 million

  • The fund balance for the amount accumulated as of December 31, 2008:

$74,504,413

" Sum of the annual amounts remaining to be collected:

$6,500,000 (through December 27, 2034)

  • Assumptions:

Escalation rate in decommissioning costs = 4.0%

Earnings rate on decommissioning funds = 6.0%

" Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v).

None

" Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report.

None

" Material changes to trust agreements.

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 3 of 3 NORTH CAROLINA EASTERN MUNICIPAL POWER AGENCY SUBMITTAL Status of Financial Assurance Mechanism Shearon Harris Nuclear Power Plant, Unit No. 1 (HNP) Docket No. 50-400 1 License No. NPF-63 The following information is submitted in accordance with 10 CFR 50.75(c):

" Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b), (c) and NUREG-1307, Rev. 13:

$393.5 million; NCEMPA Share (16.17%) = $63.6 million

" The fund balance for the amount accumulated as of December 31, 2008:

$33,974,090

  • Sum of the annual amounts remaining to be collected:

$18,952,787 (through October 24, 2046)

  • Assumptions:

Escalation rate in decommissioning costs = 4.0%

Earnings rate on decommissioning funds = 6.0%

None

  • Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report.

None

  • Material changes to trust agreements.

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF ALACHUA Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Alachua share (0.0779%) = $298,764.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$298,764 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF BUSHNELL Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Bushnell share (0.0388%) = $148,807.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$148,807 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF GAINESVILLE Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Gainesville share (1.4079%) = $5,399,612.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$5,399,612 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF KISSIMMEE Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Kissimmee share (0.6754%) = $2,590,310.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$2,590,310 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF LEESBURG Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Leesburg share (0.8244%) = $3,161,759.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$3,161,759 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3°%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF NEW SMYRNA BEACH Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of New Smyrna Beach share (0.5608%) = $2,150,794.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$2,150,794 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed cost escalation rate is 3.45%.

The assumed earnings rate is 1.704%.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 CITY OF OCALA Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

City of Ocala share (1.3333%) = $5,113,504.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$5,113,504 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed Cost Escalation Rate is 5.3%.

The assumed earnings rate is 7.422% for the portion invested at a guaranteed fixed rate through 2016 (guaranteed by a forward delivery agreement) and 5.00%

for the rest.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 ORLANDO UTILITIES COMMISSION Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

Orlando Utilities Commission share (1.6015%) = $6,142,111.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$6,142,111 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed cost escalation rate is 3.45%.

The assumed earnings rate is 5.0%.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

Trustee transferred from Salem Trust to Regions Bank

United States Nuclear Regulatory Commission RA-09-002 Enclosure Page 1 of 1 SEMINOLE ELECTRIC COOPERATIVE, INC.

Status of Financial Assurance Mechanism Crystal River Plant -- Docket No. 50-302 / License No. DPR-72

1) Amount of decommissioning funds estimated to be required pursuant to 10 CFR 50.75(b) and (c) and NUREG-1307, Rev. 13.

$383.5 million at expiration of current license on December 3, 2016.

Seminole Electric Cooperative, Inc. share (1.6994%) = $6,517,579.

2) Fund Balance for the amount of funds accumulated in the decommissioning trust fund at the end of December 31, 2008:

$6,517,579 (This amount does not include additional funds collected for non-decommissioning activities, such as site restoration)

3) Annual amounts remaining to be collected:

None

4) Assumptions:

The assumed cost escalation rate is 3.45%.

The assumed earnings rate is 8.00%.

5) Contracts upon which the licensee is relying pursuant to 10 CFR 50.75(e)(1)(v):

None

6) Modifications occurring to a licensee's current method of providing financial assurance since the last submitted report:

None

7) Material changes to trust agreements:

None