ML030730766

From kanterella
Jump to navigation Jump to search
CA004279, Re-open the Evaluation of Sen 174
ML030730766
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 04/11/2002
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
CA004279, FOIA/PA-2003-0094
Download: ML030730766 (4)


Text

-luclearManagement Company Page 1 of'4 STATE CIHANGE HISTORY Work Review & Quality Check Initiate Assign Work 4/11/2002 Assign Conduct Work 4/12/2002 Complete Approval 4/3012002 EZ5 Approved 5/1312002 2 22 07 AM 11:52.53 AM 6 40 15 AM 4 37.57 PM Owner PBNP Owner DUANE by DUANE by DON Owner DUANE by TOM Owner MARK by MARK SCHOON CAP Admin SCHOON ':4 1 SCHOON SHELEY RINZEL RINZEL PETERSON Complete and Close Done 5/13/2002 2:04 47 PM Owner (None) by JULIE .

KREIL SECTION 1 Activity Request Id: CA004279 Corrective Action Submit Date: 4111/2002 11:52:53 Activity Type: AM Site/Unit: Point Beach - Common Activity Requested: Re-Open the evaluation of SEN 174, ensuring that questions about the procedures for ensuring adequate pump flow is maintained, are fully addressed, including pumps other than AFPs Action is out of CA 3982 where CARB (3/5/02) while reviewing RCE 01-69 /ACE 314 requested a reopening of SEN 174 to specifically adress a question if procedures for ensuring adequate pump flow is maintained (possibly this point was not adequatly documented in the SEN) and discuss other pumps other then AFP's TPS D CATPR: N Initiator: MASTERLARK, JAMES ()

PO PB Operations PB Initiator Department: EPN Engineering Responsible Group Code:

Programs Nuclear El Safety Analysis PB Z2 DUANE SCHOON Responsible Department: Assessment Activity Supervisor:

Activity Performer: MARK RINZEL SECTION 2 3 Due Date: 5/10/2002 Priority:

N (None) Management Exception From PI?:

"Mode Change Restraint:

N 0 Licensing Review?:

" QA/Nuclear Oversight?: N N @ NRC Commitment Date:

NRC Commitment?:

0 Significance Level: A SECTION 3 Activity Completed: 3/17/2002 1:59PM - DON PETERSON SEN 174 has six completed actions directed at the need to develop procedures for off- mormal events, to restore power and recover equipment for non-vital 4160 & 480 V busses and was associated MCCs. Action six was closed out to CR 98-0050 action item #43. Action #43

Nuclear Management Company Page 2 of 4 closed to the issuance of AOP-18. Pump flow concerns were not directly identified in the action items for SEN 174.

4/8/2002 3:28PM - DON PETERSON.

The following documents were reviewed. SEN 174 actions items, CR 97-1992, CR 98-0050, AOP-18, AOP-18A and RCE 01-069. Pump flow concerns were not directly identified in any of the above documentation. This concern was discussed with Mr. Mark Rinzel, Corrective Action Liaison for Operations, he was in atgreement, that an action in t-Track should be issued to Operations to revisit the issues of SEN 174 with special focus on adequate pump flows.

4/8/2002 3:31PM - DON PETERSON Issue an action to Operations; Review SEN 174, focusing on "How does PBNP maintain adequate pump flow, under the conditions described in SEN 174. This action was discussed with Mr. Mark Rinzel, he has requested that it be sent to him.

4/30/2002 4:36PM - MARK RINZEL:

Corrective Action (CA) 4279 re-opened an evaluation of INPO SEN 174, "Loss of Non-Vital Bus Causes Dual unit SCRAM and degraded Auxiliary Feedwater System". The evaluation was re-opened based on a CARB request from 3/5/02 review of RCE 01-069, 'Increased CDF in AFW PRA Model Due to Procedural Inadequacies Related to Loss of Instrument Air". The CARB requested this evaluation be re-opened to examine additional pumps, other than the AFW pumps, to ensure that adequate flow or recirculation flow would be maintained via procedures through these pumps to prevent damage.

To re-examine this issue, reviews of AOP-5B, "Loss of Instrument Air", EOP 0.1, "Reactor Trip Response" and EOP 1.3, "Transfer to Containment Sump Recirculation" were performed. In addition, conversation with three Licensed SROs were performed to identify where in the procedures adequate pump flows were addressed The re-examination focused on safety related pumps necessary for unit shutdown or to dissipate decay heat and maintain core cooling. It was discovered that the AFW pump recirculation valves are unique in the fact that their recirculation valves fail closed upon loss of instrument air. (This was an original plant design function to ensure all flow going to the steam generators, and has since been rectified with the addition of a backup nitrogen supply to ensure the valves ability to be opened and stay open. This was done via the modification process).

Safety Injection system recirculation valves are locked to the open position. This is stated in AOP-5B, Attachment D, Part 2, "System Response", which states "Test line valves SI-897A and SI-897B are fail open with IA isolated. This maintains a recirc flow path for the SI pumps."

Feed and Condensate pumps and valves are covered in AOP-5B Attachment T.

"CS-21 80, CS-2188, Main Feed Pump mini-recirc valves fail open, if doesn't go open, instructed to use the manual gag override to open the valve" "CS-2252, Condensate Pump mini-recirc valve fails open, instructed to use the manual gag override to open the valve if it doesn't go open."

RCP Thermal Barriers are covered in AOP-5B Attachment H, Component Cooling "RCP thermal barrier isolation valves fail open to maintain thermal barrier cooling" AOP-5B, Attachment E covers the RHR system discharge and recirculation valves. These also fail open upon loss of instrument air. This will ensure adequate cooling to the pumps, however, creates a different issue. Due to the RH-624 and RH-625 (RHR Heat Exchanger Outlet valves) failing open, the potential exists for the RHR pumps to go into a runout condition when Containment Sump recirculation is put into operation. This is because of the supplies to and discharges from the Spray and SI pumps, as well as the RHR pumps, being maximized.

This has been a known issue for some time and has been addressed within both the AOP-5B and EOP-1.3 procedures To ensure that the RHR pumps do not go into a runout condition, the RH-624 and RH-625 outlet isolation valves, RH-716A and RH-716B are throttled to ensure a miximum RHR ilow of 2200 gpm In addition, in EOP 1.3, the SI to RHR supply valve, SI 857 (either A or B depending on the RHR train being used/lined up for sump recirc) is throttled

Nuclear Management Company Page 3 of 4 to maintain RHR pump discharge pressure less than 130 psig Therefore, the AOPs and EOPs address the issues of RHR and SI pump having inadequate flow, as well as preventing pump runout conditions, to ensure no damage to the pumps Based on what was discovered through these reviews and conversations, it appears that the AFW pumps were in a unique situation, which has since been resolved. All other safety related/high profile pumps are protected from low or no flow damage, or pump runout, through steps built into the current EOPs and AOPs Based on this information, the SEN and CARB concerns are believed adequately addressed No further actions are recommended at this time, and this action item may be closed.

4/30/2002 4:37PM - MARK RINZEL:

Evaluation completed, see above update.

5/13/2002 2:22:07 AM - DUANE SCHOON.

Action complete. Closed.

5/13/2002 2:04:47 PM - JULIE KREIL:

SEN 174 evaluation was re-evaluated. Based on what was discovered through these reviews and conversations, it appears that the AFW pumps were in a unique situation, which has since been resolved. All other safety related/high profile pumps are protected from low or no flow damage, or pump runout, through steps built into the current EOPs and AOPs. The SEN and CARB concerns are believed adequately addressed. No further actions are recommended.

CLOSED CA004279 to completion of Requested Activity.

SECTION 4 (None) Licensing Supervisor: (None)

GA Supervisor:

SECTION 5 0 Project: CAP Activities & Actions Done 0 Active/Inactive: Inactive 0 State:

AR Type: Parent 0 Owner: (None)

" Submitter: DON PETERSON ( Assigned Date: 4/12/2002 JULIE KREIL

" Last Modified Date: 5/13/2002 2:04"47 PM 0 Last Modifier:

JULIE KREIL Q Last State Change Date: 5/13/2002 2.04:47 PM 0 Last State Changer:

"0Close Date: 5/13/2002 2:04 47 PM

" One Line

Description:

Probabilistic Risk Assessment PRA For Auxiliary Feedwater System AFW NUTRK ID: CR 01-3595 Child Number: 0

References:

CR 01-2278 RCE 01-069 GOOD CATCH SEN 174 CR 97-1992 CR 98-0050 AOP 18 AOP 18A EOP 0.1 EOP 1.3 AOP 5B Update: L\\(20011204 PB2171 JMK1) Operability Determination (OD) Part I, Revision 0, of CR 01 3595 was approved on 11/30/01. Operable But Degraded - or Operable But Nonconforming -

Nuclear Management Company Page 4 of 4 meets the minimum required level of performances, compensatory measures ARE required

\\Operability Determination (OD) Part I, Revision 1 of CR 01-3595 was approved on 12/01101.

Operable But Degraded - or Operable But Nonconforming - meets the minimum required level of performances, compensatory measures ARE required.

Accepted into group and assigned priority 3. This questions the adequacy of an SEN applicability determination and evaluation. Per NP 5.4.1, SEN are to be priority 3 Priority = This is a reflash question towards the adquacy of a SEN closure from engineering TPS Import Memo Field:

CAP Admin: PBNP CAP Admin Site: Point Beach OLDACTION_NUM:

Cartridge and Frame:

ATTACHMENTS AND PARENT/CHILD LINKS SCA003982 Probabilistic Risk Assessment PRA For Auxiliary Feedwater System AFW SCAP001415" Probabilistic Risk Assessment PRA For Auxiliarv Feedwater System AFW