Text

May 24, 2002 Dr. Robert C. Mecredy Vice President, Nuclear Operations Rochester Gas and Electric Corporation 89 East Avenue Rochester, NY 14649

SUBJECT:

BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE FOR R.E. GINNA NUCLEAR POWER PLANT (TAC NO. MB4548)

Dear Dr. Mecredy:

On March 18, 2002, the Nuclear Regulatory Commission (NRC) staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements. Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A. through E. within 15 days of the Bulletins issuance, or to provide a written response to the NRC in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they cannot meet the requested completion dates.

You provided your 15-day Bulletin response by letter dated March 22, 2002. The staff finds that you have provided the requested information, and has concluded that your plant does not appear to have conditions similar to those which lead to the degradation at Davis-Besse.

However, the staff may issue questions to confirm or verify the information that was provided in your 15-day response to Bulletin 2002-01.

We will complete a full review of your response to Bulletin 2002-01 after we review your response to Items 2 and 3 of the Bulletin.

Sincerely,

/RA/

Robert Clark, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244 cc: See next page

May 24, 2002 Dr. Robert C. Mecredy Vice President, Nuclear Operations Rochester Gas and Electric Corporation 89 East Avenue Rochester, NY 14649

SUBJECT:

BULLETIN 2002-01, REACTOR PRESSURE VESSEL HEAD DEGRADATION AND REACTOR COOLANT PRESSURE BOUNDARY INTEGRITY, 15-DAY RESPONSE FOR R.E. GINNA NUCLEAR POWER PLANT (TAC NO. MB4548)

Dear Dr. Mecredy:

On March 18, 2002, the Nuclaer Regulatory Commission (NRC) staff issued Bulletin 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure Boundary Integrity, to the industry requesting that addressees provide information related to the structural integrity of the reactor coolant pressure boundary, including the reactor pressure vessel head, and the extent to which inspections have been undertaken to satisfy applicable regulatory requirements. Bulletin 2002-01 also required licensees to provide the basis for concluding that plans for future inspections of the reactor coolant pressure boundary will satisfy applicable regulatory requirements at their respective pressurized-water reactor plants. All addressees were requested to respond to Items 1.A. through E. within 15 days of the Bulletins issuance, or to provide a written response to the NRC in accordance with the provisions of Title 10, Section 50.54(f), of the Code of Federal Regulations (10 CFR 50.54(f)) if they are unable to provide the information or they cannot meet the requested completion dates.

You provided your 15-day Bulletin response by letter dated March 22, 2002. The staff finds that you have provided the requested information, and has concluded that your plant does not appear to have conditions similar to those which lead to the degradation at Davis-Besse.

However, the staff may issue questions to confirm or verify the information that was provided in your 15-day response to Bulletin 2002-01.

We will complete a full review of your response to Bulletin 2002-01 after we review your response to Items 2 and 3 of the Bulletin.

Sincerely,

/RA/

Robert Clark, Project Manager, Section 1 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-244 cc: See next page DISTRIBUTION:

PUBLIC RLaufer OGC WBateman PDI-1 R/F RClark ACRS ALee EMCB R/F SBloom BPlatchek, RGI SCoffin ACCESSION NO. ML021430311 OFFICE PDI-1/PM PDI-1/LA EMCB PDI-1/SC NAME RClark SLittle SBloom PMilano for RLaufer DATE 5/23/02 5/23/02 5/24/02 5/24/02 OFFICIAL RECORD COPY

R.E. Ginna Nuclear Power Plant cc:

Christopher Welch, Sr. Resident Inspector Mr. Paul Eddy R.E. Ginna Plant New York State Department of U.S. Nuclear Regulatory Commission Public Service 1503 Lake Road 3 Empire State Plaza, 10th Floor Ontario, NY 14519 Albany, NY 12223 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Mr. William M. Flynn, President New York State Energy, Research, and Development Authority Corporate Plaza West 286 Washington Avenue Extension Albany, NY 12203-6399 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Daniel F. Stenger Ballard Spahr Andrews & Ingersoll, LLP 601 13th Street, N.W., Suite 1000 South Washington, DC 20005 Ms. Thelma Wideman, Director Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons, NY 14489 Ms. Mary Louise Meisenzahl Administrator, Monroe County Office of Emergency Preparedness 1190 Scottsville Road, Suite 200 Rochester, NY 14624