JAFP-94-0228, Responds to NRC Bulletin 93-002,suppl 1 Debris Plugging of Emergency Core Cooling Suction Strainers

From kanterella
(Redirected from JAFP-94-0228)
Jump to navigation Jump to search
Responds to NRC Bulletin 93-002,suppl 1 Debris Plugging of Emergency Core Cooling Suction Strainers
ML20065N046
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 04/19/1994
From: Harry Salmon
POWER AUTHORITY OF THE STATE OF NEW YORK (NEW YORK
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
IEB-93-002, IEB-93-2, JAFP-94-0228, JAFP-94-228, NUDOCS 9404260387
Download: ML20065N046 (7)


Text

'

J mes A. Fit:Psick

', . Nuefear Powsr Plint.

'P.O. Dox 41

  • Lycoming. Now York 13093 31E 342-3840
  1. > NewYorkPower 4# Authority ""1"d"f"*l' "

April 19,1994 JAFP-94-0228 U. S. Nuclear Regulatory Con mission Mail Station F1-137 A'ITN: Document Control Desk Washington, DC 20555

SUBJECT:

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Respmtse to NRC Bulletin No. 93-02 Supplement 1 Debris Pluenine of Emereency Core Cooline Suction Strainers

References:

1) NRC Bulletin No. 93-02 Supplement 1, " Debris Plugging of Emergency Core Cooling Suction Strainers," dated Febmary 18, 1994.
2) Safety Asr ssment, "BWR Emergency Core Cooling System Suction St. tiners", G.E. Nuclear Energy for BWR Owners Group, Dr.ted March,1994.

Attachments: 1) List ef Commitments.

Dear Sir:

This letter describes the actions taken by the New York Power Authority in response to NRC Bulletin No. 93-02 Supplement 1 (Reference 1) at the James A. FitzPatrick Nuclear Power Plant (JAF).

The Bulletin Supplement requests a written report within 60 days of issue stating whether the actions requested have been or will be performed, a description of planned actions,-

and a schedule for completing them. The original bulletin was issued on May 11, 1993 and required Licensees to identify fibrous air Diters and other temporary fibrous materials in the containment and to take prompt action to remove those not designed to . i withstand LOCA conditions. The JAF response to the original Bulletin was accepted by .I the NRC. j kbhIIO{'#

' 9404260387 940419 I PDR ADOCK 05000333 l P PDR

(( .[ f dh [ [ l

4 U. S., Nuclear Regulatory Commission

, Response to NRC Bulli et n No. 9 3-02 Supplement 1 Page 2 The NRC issued Bulletin 93-02 Supplement 1 based on the ECCS Suction Strainer blockage problems at Barsebuck Nuclear Power Plant and the Perry Nuclear Power Plant. The Supplement states that there is potential for common mode failure of the ECCS suction strainers based on studies that indicated that previous assumptions regarding a LOCA and the amount of insulation removed from adjacent pipes, the amount of debris transported to the suppression pool, the amount of debris that ends up on the suction strainers, and the time delay until strainer clogging occurs may have been underestimated. The NRC has requested that BWR licensees take the intetim actions listed in the Supplement to enhance the capability to prevent or mitigate loss of the ECCS following a LOCA.

Actions Requested:

1. Provide training and briefmgs to apprise operators and other emergency response personnel of the information contained herein and in the referenced information notices, JAF Response: l l

The NRC Bulletin was routed for required reading for operations personnel as an I l

immediate action to apprise operators of the concerns of the Bulletin. The Operations Training Group is conducting training in the current licensed operator .

requalification cycl.e, The training will consist of classroom training on the l history, present concerns, possible indications of clogging, and mitigative actions regarding this issue. - The training also includes a simulator scenario which ensures operators can recognize symptoms of a similar event and are able to mitigate consequences using the Emergency Operating Procedures (EOPs) and i supporting procedures. This training began March 28 and will be completed by May 13,1994.

The Engineering Support Personnel (ESP) Program Administrator routed the bulletin to plant engineers, who have Emergency Response Organization responsibilities, for required reading (This will be completed prior to May 18, 1994). During the next ESP Continuing Training cycle the concerns from the bulletin will be discussed with the entire ESP staff. Scheduled to be completed June 30,1994 Actions 2 & 3

2. Assure the emergency operating procedures make the operator aware of possible indications of ECCS stainer clogging and provide guidance on mitigation.

U. S. Nuclear Regulatory Commission

, Response to NRC Bulletin No. 934)2 Supplement 1 Page 3

3. Institute procedures and other measures to provide compensatory actions to prevent, delay, or mitigate a loss of available NPSH margin under LOCA conditions. Such measures should be consistent with providing the design basis emergency system functions for core and containment cooling.

JAF Response to 2 & 3: l JAF EOPs are symptom based and as such address a full spectrum of initial plant  ;

conditions and postulated transients. The EOPs do not unconditionally prioritize  !

the use of one injection source over another. When actions are directed by the l EOPs, operators will use the supporting procedures to manipulate the systems as necessary.

The Supplement suggests that actions to assure sufficient core and containment cooling may include:

l I

e Reduction of flow (consistent with delivering the required ECCS flow) through the strainers to reduce head loss and extend the time for debris deposition.

The RHR and Core Spray systems can be throttled under emergency conditions.

Also, if water level in the vessel is being maintained the Shift Supervisor can alternate the use of ECCS trains by securing of individual ECCS trains until they are required again to maintain RPV level or cooling. Support procedures are I

'I being revised to ensure operators are aware of the concern of possible ECCS strainer clogging and to throttle flow consistent with required needs. (Scheduled j completion date: May 18, 1994) l

  • Operator realignment of existing systems to allow backflushing of clogged strainers.

Under present design configurations there are no means to effectively backflush the ECCS system suction strainers. NYPA staff is actively involved with the' BWR Owners Group on this issue and is awaiting final generic resolution. In the interim, NYPA believes the low probability of the postulated event, leak-before-break considerations, and that the EOPs lead the operators through responses to any declining reactor water level with utilization of all available alternate water sources (discussed below), will assure safe operation. This position is consistent with the BWR Owners Group approved safety assessment (Reference 2).

U. S. Nuclear Regulatory Commission Responw to NRC Bulletin No. 93-02 Supplement I  ;

Page 4 i

e Operator realignment of existing systems to allow injection to the core  !

from water sources other than the suppression pool. j Sources of RPV injection from water sources other than the suppression pool include the feed and condensate system, CRD, HPCI, RCIC, SLC, RHR service water cross-tie, fire water cross-tie, and condensate transfer. The EOP for RPV control directs operation of alternate sources of injection if operators determine that RPV water level cannot be maintained above the top of active fuel (TAF).

The use of the RHR service water cross-tie can supply an inexhaustible amount of water to the reactor from Ide Ontario. The fire water cross-tie provides an alternate method for injecting water into the RPV or primary containment for containment cooling by utilizing the fire protection pumps as the motive force.

The use of this system would allow a diesel fire pump to provide approximately 1000 gpm of low pressure water to the reactor via the RHRSW unlimited make-up cross tie to RHR in the event of a sustained loss of AC power (Station Blackout). The use of other alternate systems will provide operators with additional time to mitigate this event.

e Intermittent operation of the containment sprays, when possible, to reduce the transport of debris to the strainers.

JAF EOPs require intermittent operation of containment sprays. The Operators are directed to initiate drywell spray when containment pressure exceeds 16 psig (note: other considerations are required prior to initiation of spray) and are directed to secure drywell spray when pressure drops below 2.7 psig. The downcomers at JAF have missile deflection shields and are located 18 inches off the containment floor. This configuration will minimize debris transport to the suppression pool from containment spray actuation.

Based on the above, NYPA has determined that the EOPs do not require revision.

However, the following supporting procedures will be revised to include a caution or note to notify operators of the potential for strainer clogging and to adjust flow consistent with required needs to mitigate the clogging:

e OP-13 Residual Heat Removal System o OP-14 Core Spray System o OP-15 High Pressure Coolant Injection System o OP-19 Reactor Core Isolation Cooling System Procedure revisions will be completed by May 18, 1994.  !

t e l U. S, Nuclear Regulatory Commission

. Response to NRC Bulletin No. 93-02 Supplement 1 Page 5 Additional mitigating activities / conditions are:

e During February,1992, divers inspected and cleaned the torus. This inspection included visual verification the ECCS pump suction strainers were intact and not blocked.

  • A 360' inspection of the torus for sunken debris was conducted in October,1992, by divers. Foreign material encountered during the inspection was removed.
  • As part of JAFs torus coating program the torus is routinely de-sludged and inspected. The torus is scheduled to be de-sludged during the next refueling outage (Iiovember,1994).

NYPA is actively participating in the BWR Owners Group effort to obtain a final resolution to this issue. These actions being taken by NYPA are consistent with the recommendations of the BWR Owners Group and actions taken by other BWRs in the industry.

If you have any questions, please contact Mr. A. Zaremba, of my staff.

Very truly yours,

/ & (V Harry P. Salmon, Jr. ]

Resident Manager i STATE OF NEW YORK COUNTY OF OSWEGO Subscribed and sworn to before me this W" day of April 1994.

TAMMY L DANN 4985563  !

Notary Pubhc, State of New York Quahfied in Oswego Co

/gj Q Commission Expires 8/191gty<

Notar/ Putilic cc: See next page ,

4 cc: Regional Administrator U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Resident Inspector

'U.S. Nuclear Regulatory Commission P.O. Box 136 Lycoming, NY 13093 Mr. Brian C. McCabe Project Directorate I-l Division of Reactor Projects - I/II U.S. Nuclear Regulatory Commission Mail Stop 14 B2 Washington, D.C. 20555 l

l l

1 l

l l

i 1

m . _ . .

.s Attachment 1 List of Commitments JAFP-94-0228 Number Commitment Due Date JAFP-94-0228-01 All JAF operations personnel will read NRCB May 18,1994 93-02 Supplement 1.

JAFP-94-0228-02 All JAF operations personnel will attend May 18,1994 classroom and simulator training regardirig NRCB 93-02 Supplement 1.

JAFP-94-0228-03 Engineering Support Personnel wN have May 18,1994 Emergency Response Organization responsibilitics will read NRCB 93-02 Supplement 1.

JAFP-94-022844 Operations department will revise the following May 18,1994 operating procedures:

OP-13 Residual Heat Remtval OP-14 Core Spray System OP-15 High Prestare Coolard Irjection System OP-19 Reactor Core Cooling Isolation System The revision will include a caution or note to notify operators or the potential for strainer clogging and to adjust flow consistent with required needs to mitigate the clogging.

JAFP-94-0228-05 All engineering support personnel will attend June 30,1994 classroom training regarding NRCB 93-02 Supplement 1.

)

i I

1

. .. - . _ _ - _ ______