|
---|
Category:NRC Information Notice
MONTHYEARInformation Notice 1991-09, Counterfeiting of Crane Valves2007-09-25025 September 2007 Counterfeiting of Crane Valves Information Notice 2003-06, Failure of Safety-Related Linestarter Relays at San Onofre Nuclear Generating Station2003-06-19019 June 2003 Failure of Safety-Related Linestarter Relays at San Onofre Nuclear Generating Station Information Notice 2002-01, Metal Clad Switchgear Failures and Consequent Losses of Offsite Power2002-01-0808 January 2002 Metal Clad Switchgear Failures and Consequent Losses of Offsite Power Information Notice 1999-28, Recall of Star Brand Fire Protection Sprinkler Heads1999-09-30030 September 1999 Recall of Star Brand Fire Protection Sprinkler Heads Information Notice 1999-27, Malfunction of Source Retraction Mechanism in Cobalt-60 Teletherapy Treatment Units1999-09-0202 September 1999 Malfunction of Source Retraction Mechanism in Cobalt-60 Teletherapy Treatment Units Information Notice 1999-26, Safety and Economic Consequences of Misleading Marketing Information1999-08-24024 August 1999 Safety and Economic Consequences of Misleading Marketing Information Information Notice 1999-25, Year 2000 Contingency Planning Activities1999-08-10010 August 1999 Year 2000 Contingency Planning Activities Information Notice 1999-24, Broad-Scope Licensees' Responsibilities for Reviewing and Approving Unregistered Sealed Sources and Devices1999-07-12012 July 1999 Broad-Scope Licensees' Responsibilities for Reviewing and Approving Unregistered Sealed Sources and Devices Information Notice 1999-23, Safety Concerns Related to Repeated Control Unit Failures of the Nucletron Classic Model High-Dose-Rate Remote Afterloading Brachytherapy Devices1999-07-0606 July 1999 Safety Concerns Related to Repeated Control Unit Failures of the Nucletron Classic Model High-Dose-Rate Remote Afterloading Brachytherapy Devices Information Notice 1999-22, 10CFR 34.43(a)(1); Effective Date for Radiographer Certification and Plans for Enforcement Discretion1999-06-25025 June 1999 10CFR 34.43(a)(1); Effective Date for Radiographer Certification and Plans for Enforcement Discretion Information Notice 1999-21, Recent Plant Events Caused by Human Performance Errors1999-06-25025 June 1999 Recent Plant Events Caused by Human Performance Errors Information Notice 1999-20, Contingency Planning for the Year 2000 Computer Problem1999-06-25025 June 1999 Contingency Planning for the Year 2000 Computer Problem Information Notice 1999-19, Rupture of the Shell Side of a Feedwater Heater at the Point Beach Nuclear Plant1999-06-23023 June 1999 Rupture of the Shell Side of a Feedwater Heater at the Point Beach Nuclear Plant Information Notice 1999-18, Update on Nrc'S Year 2000 Activities for Material Licensees and Fuel Cycle Licensees and Certificate Holders1999-06-14014 June 1999 Update on Nrc'S Year 2000 Activities for Material Licensees and Fuel Cycle Licensees and Certificate Holders Information Notice 1999-17, Problems Associated with Post-Fire Safe-Shutdown Circuit Analyses1999-06-0303 June 1999 Problems Associated with Post-Fire Safe-Shutdown Circuit Analyses Information Notice 1999-16, Federal Bureau of Investigation'S Nuclear Site Security Program1999-05-28028 May 1999 Federal Bureau of Investigation'S Nuclear Site Security Program Information Notice 1999-15, Misapplication for 10CFR Part 71 Transportation Shipping Cask Licensing Basis to 10CFR Part 50 Design Basis1999-05-27027 May 1999 Misapplication for 10CFR Part 71 Transportation Shipping Cask Licensing Basis to 10CFR Part 50 Design Basis Information Notice 1999-14, Unanticipated Reactor Water Draindown at Quad Cities Unit 2, Arkansas Nuclear One Unit 2, & FitzPatrick1999-05-0505 May 1999 Unanticipated Reactor Water Draindown at Quad Cities Unit 2, Arkansas Nuclear One Unit 2, & FitzPatrick Information Notice 1999-13, Insights from NRC Inspections of Low-and Medium-Voltage Circuit Breaker Maintenance Programs1999-04-29029 April 1999 Insights from NRC Inspections of Low-and Medium-Voltage Circuit Breaker Maintenance Programs Information Notice 1999-12, Year 2000 Computer Systems Readiness Audits1999-04-28028 April 1999 Year 2000 Computer Systems Readiness Audits Information Notice 1999-11, Incidents Involving the Use of Radioactive Iodine-1311999-04-16016 April 1999 Incidents Involving the Use of Radioactive Iodine-131 Information Notice 1999-08, Urine Specimen Adulteration1999-03-26026 March 1999 Urine Specimen Adulteration Information Notice 1999-09, Problems Encountered When Manually Editing Treatment Data on the Nucletron Microselectron-HDR (New) Model 105-9991999-03-24024 March 1999 Problems Encountered When Manually Editing Treatment Data on the Nucletron Microselectron-HDR (New) Model 105-999 Information Notice 1999-07, Failed Fire Protection Deluge Valves & Potential Testing Deficiencies in Preaction Sprinkler Systems1999-03-22022 March 1999 Failed Fire Protection Deluge Valves & Potential Testing Deficiencies in Preaction Sprinkler Systems Information Notice 1999-06, 1998 Enforcement Sanctions as a Result of Deliberate Violations of NRC Employee Protection Requirements1999-03-19019 March 1999 1998 Enforcement Sanctions as a Result of Deliberate Violations of NRC Employee Protection Requirements Information Notice 1999-06, 1998 Enforcement Sanctions As a Result of Deliberate Violations of NRC Employee Protection Requirements1999-03-19019 March 1999 1998 Enforcement Sanctions As a Result of Deliberate Violations of NRC Employee Protection Requirements Information Notice 1999-05, Inadvertent Discharge of Carbon Dioxide Fire Protection System and Gas Migration1999-03-0808 March 1999 Inadvertent Discharge of Carbon Dioxide Fire Protection System and Gas Migration Information Notice 1999-04, Unplanned Radiation Exposures to Radiographers, Resulting from Failures to Follow Proper Radiation Safety Procedures1999-03-0101 March 1999 Unplanned Radiation Exposures to Radiographers, Resulting from Failures to Follow Proper Radiation Safety Procedures Information Notice 1999-03, Exothermic Reactors Involving Dried Uranium Oxide Powder (Yellowcake)1999-01-29029 January 1999 Exothermic Reactors Involving Dried Uranium Oxide Powder (Yellowcake) Information Notice 1999-02, Guidance to Users on the Implementation of a New Single-Source Dose-Calculation Formalism and Revised Air-Kerma Strength Standard for Iodine-125 Sealed Sources1999-01-21021 January 1999 Guidance to Users on the Implementation of a New Single-Source Dose-Calculation Formalism and Revised Air-Kerma Strength Standard for Iodine-125 Sealed Sources Information Notice 1999-01, Deterioration of High-Efficiency Particulate Air Filters in a Pressurized Water Reactor Containment Fan Cooler Unit1999-01-20020 January 1999 Deterioration of High-Efficiency Particulate Air Filters in a Pressurized Water Reactor Containment Fan Cooler Unit Information Notice 1998-45, Cavitation Erosion of Letdown Line Orifices Resulting in Fatigue Cracking of Pipe Welds1998-12-15015 December 1998 Cavitation Erosion of Letdown Line Orifices Resulting in Fatigue Cracking of Pipe Welds Information Notice 1998-44, Ten-Year Inservice Inspection (ISI) Program Update for Licensees That Intend to Implement Risk-Informed ISI of Piping1998-12-10010 December 1998 Ten-Year Inservice Inspection (ISI) Program Update for Licensees That Intend to Implement Risk-Informed ISI of Piping Information Notice 1998-43, Leaks in Emergency Diesel Generator Lubricating Oil & Jacket Cooling Water Piping1998-12-0404 December 1998 Leaks in Emergency Diesel Generator Lubricating Oil & Jacket Cooling Water Piping Information Notice 1998-42, Implementation of 10 CFR 55.55a(g) Inservice Inspection Requirements1998-12-0101 December 1998 Implementation of 10 CFR 55.55a(g) Inservice Inspection Requirements Information Notice 1998-41, Spurious Shutdown of Emergency Diesel Generators from Design Oversight1998-11-20020 November 1998 Spurious Shutdown of Emergency Diesel Generators from Design Oversight Information Notice 1998-41, Spurious Shutdown of Emergency Diesel Generators From Design Oversight1998-11-20020 November 1998 Spurious Shutdown of Emergency Diesel Generators From Design Oversight Information Notice 1998-39, Summary of Fitness-for-Duty Program Performance Reports for Calendar Years 1996 and 19971998-10-30030 October 1998 Summary of Fitness-for-Duty Program Performance Reports for Calendar Years 1996 and 1997 Information Notice 1998-40, Design Deficiencies Can Lead to Reduced ECCS Pump Net Positive Suction Head During Design-Basis Accidents1998-10-26026 October 1998 Design Deficiencies Can Lead to Reduced ECCS Pump Net Positive Suction Head During Design-Basis Accidents Information Notice 1990-66, Incomplete Draining and Drying of Shipping Casks1998-10-25025 October 1998 Incomplete Draining and Drying of Shipping Casks Information Notice 1998-38, Metal-Clad Circuit Breaker Maintenance Issues Identified by NRC Inspections1998-10-15015 October 1998 Metal-Clad Circuit Breaker Maintenance Issues Identified by NRC Inspections Information Notice 1998-37, Eligibility of Operator License Applicants1998-10-0101 October 1998 Eligibility of Operator License Applicants Information Notice 1998-36, Inadequate or Poorly Controlled, Non-Safety-Related Maintenance Activities Unnecessarily Challenged Safety Systems1998-09-18018 September 1998 Inadequate or Poorly Controlled, Non-Safety-Related Maintenance Activities Unnecessarily Challenged Safety Systems Information Notice 1998-33, NRC Regulations Prohibit Agreements That Restrict or Discourage an Employee from Participating in Protected Activities1998-08-28028 August 1998 NRC Regulations Prohibit Agreements That Restrict or Discourage an Employee from Participating in Protected Activities Information Notice 1998-34, Configuration Control Errors1998-08-28028 August 1998 Configuration Control Errors Information Notice 1998-31, Fire Protection System Design Deficiencies and Common-Mode Flooding of Emergency Core Cooling System Rooms at Washington Nuclear Project Unit 21998-08-18018 August 1998 Fire Protection System Design Deficiencies and Common-Mode Flooding of Emergency Core Cooling System Rooms at Washington Nuclear Project Unit 2 Information Notice 1998-30, Effect of Year 2000 Computer Problem on NRC Licensees and Certificate Holders1998-08-12012 August 1998 Effect of Year 2000 Computer Problem on NRC Licensees and Certificate Holders Information Notice 1998-29, Predicted Increase in Fuel Rod Cladding Oxidation1998-08-0303 August 1998 Predicted Increase in Fuel Rod Cladding Oxidation Information Notice 1998-28, Development of Systematic Sample Plan for Operator Licensing Examinations1998-07-31031 July 1998 Development of Systematic Sample Plan for Operator Licensing Examinations Information Notice 1998-26, Settlement Monitoring and Inspection of Plant Structures Affected by Degradation of Porous Concrete Subfoundations1998-07-24024 July 1998 Settlement Monitoring and Inspection of Plant Structures Affected by Degradation of Porous Concrete Subfoundations 2007-09-25
[Table view] |
UNITED STATES
NUCLEAR REGULATORY COMMISSION
OFFICE OF NUCLEAR REACTOR REGULATION
WASHINGTON, D. C. 20555-0001 January 8, 2002 NRC INFORMATION NOTICE 2002-01: METALCLAD SWITCHGEAR FAILURES AND
CONSEQUENT LOSSES OF OFFSITE POWER
Addressees
All holders of licenses for nuclear power reactors.
Purpose
The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to inform
addressees of electrical equipment failure modes and design vulnerabilities identified following
recent transients at the San Onofre Nuclear Generating Station and at a foreign nuclear power
station. The most interesting aspect in both events was propagation of damage from an
electrical fault in one breaker cubicle to other breakers and buswork in the same enclosure. It
is expected that recipients will review the information for applicability to their facilities and
consider actions, as appropriate, to avoid similar problems. However, suggestions contained in
this information notice are not NRC requirements; therefore, no specific actions or written
response is required.
Description of Circumstances
San Onofre Nuclear Generating Station Event
On February 3, 2001, the reactor at the San Onofre Nuclear Generating Station, Unit 3 (SONGS-3), was at 39 percent power following a refueling outage. While shifting loads to the
unit auxiliary transformers, a fault on a 4.16 kV supply circuit breaker from the unit auxiliary
transformer caused a fire and loss of offsite power.
The fault was caused by failure of the 4.16 kV breakers C phase main contacts to close fully.
This resulted in arcing and a production of a thick, dark ionized smoke. The breaker was a
Brown Bovari Type HK three pole, medium-voltage ac power circuit breaker rated for 3000
amps (continuous) and 350 MVA (interrupting). The breaker was approximately 25 years old
and had its last preventive maintenance performed in 1997. Due to the extensive fire damage, the cause of the breakers failure to close could not be definitively established.
Offsite power was lost when ionized smoke (which is conductive) diffused through holes
(through which wires passed) and conduits between adjacent cubicles. This shorted the
energized incoming terminals of the offsite power supply from the reserve auxiliary transformer.
The fault blew open the cubicle door of the offsite supply circuit breaker and blew off an
insulating boot that covered the A phase bus bar. The high voltage supply breakers upstream
of the reserve auxiliary transformer opened to clear the fault. This interrupted non-vital offsite
power to the unit.
As a consequence of the loss of offsite power, neither turbine ac lube oil pump started. Failure
of the ac pumps to start should have initiated an automatic start of the backup emergency dc
turbine lube oil pump; however, the backup dc pump failed to start. This failure to start was
caused by a defect in the trip setting device of the dc lube oil pumps power supply breaker.
The breakers trip setting device (a mechanical device that maintains spring tension and thus
the breakers trip setting) was found damaged and incapable of maintaining spring tension and
thus the trip setting. The dc pump supply breaker is a 250 volt dc General Electric molded case
circuit breaker, Type TBC 400. The dc pump failure led to extensive damage to the unit main
turbine, generator and exciter resulting from inadequate lubrication.
Foreign Nuclear Power Station Event
On March 18, 2001, at a foreign PWR, a fault in a 4.16 kV load center caused a fire and loss of
offsite power while the reactor was shutdown but with significant decay heat. This, combined
with a subsequent independent failure in the onsite standby power supply, resulted in a station
blackout (i.e., a loss of ac power to both redundant safety systems). Recovery from the event
was further complicated by smoke and dependence on ac powered emergency lighting and
ventilation.
This foreign plant is a PWR in commercial operation since the mid 1980s. Offsite power is
provided by two independent circuits from the transmission network (see Attachment 1). The
circuit from the 345 kV transmission network is the normal source of offsite power to each of
the two redundant 4.16 kV safety-related trains. The circuit from 161 kV transmission network
provides a backup offsite source to each train.
For several days prior to the event, foggy, misty weather had caused salt deposition on the
insulators on the 345 kV transmission system and consequent power fluctuations and
interruptions. On March 17, the day prior to the failure, the 345 kV transmission system had
been interrupted, resulting in an automatic reactor shutdown and transfer to the backup 161 kV
offsite source. On March 18, with the reactor shutdown and with off-site power being supplied
to the unit from the 161 kV backup source, the 345 kV source was recovered and the circuit into
the plant re-energized.
After the switchyard 345 kV circuit breaker was closed (energizing the 345/4.16 kV transformer
and the 4.16 kV circuits into the vital load centers while the 4.16 kV supply breakers were still
open), a fault occurred in the A train 4.16 kV load center. The fault was caused by insulator
failure on one phase of the A train 4.16 kV safety-related switchgear on the supply side of the
supply breaker from the 345/4.16 kV transformer. The cause of the insulator failure is
unknown. The resulting fault de-energized the 345 kV offsite source to both the A and B
4.16 kV safety-related switchgear. The fault also produced voluminous smoke and ionized gas.
Migration of the smoke through the A train 4.16 kV switchgear enclosure resulted in multiple
arcing faults. One of these faults, apparently on the supply side of supply breaker from the
161 kV source caused loss of the 161 kV supply to both the A and B trains. Both trains were affected because they share a common feeder cable downstream of the step-down transformer
from the 161 kV system. Another fault in the internal bus-work of the switchgear caused the A
train EDG supply breaker to trip after the EDG started and came to rated voltage.
These faults resulted in unavailability of power to A train safety systems from either the A train
onsite emergency diesel generator or from either the 345 kV or the 161 kV offsite sources. The
faults inside the A train load center on the supply side of each of the offsite source circuits
tripped and locked out the high voltage supply breakers for both the 345 and 161 kV circuits
and prevented the connection of offsite power to the B train safety systems as well.
The B train onsite emergency diesel generator failed independently. The diesel generator failed
to achieve normal voltage due to a failure in its excitation circuit. Further local starting attempts
were prevented by heavy smoke from the burning insulation in the A load center. The heavy
smoke could not be cleared from the corridors because of lack of ac power to operate either
normal ventilation or emergency blowers; also only very limited emergency lighting was
available in that area.
The remaining ac power supply (a station blackout diesel generator capable of being connected
to either of the two trains) was started but tripped on low lube oil pressure. It was later
determined that the blackout diesel had tripped because the loss of offsite power interrupted
power to the engines keep-warm system.
All primary injection systems were unavailable due to the loss of ac power. The steam-driven
auxiliary feed pump provided sufficient cooling for the primary system. The blackout diesel was
eventually restarted and the B train was energized about two hours after the event and the plant
was stabilized.
Discussion
These electrical events provide insight into possible collateral damage and cascading failures
resulting from a single electrical failure and consequent challenges to plant operation. At
SONGS-3, the event originated with the failure of a single non-safety-related 4.16 kV
switchgear supply breaker. Smoke from the event propagated causing loss of offsite power to
other non-safety-related equipment and partial loss of offsite power to safety-related equipment.
The loss of offsite power resulted in the need for dc backup power to operate the non-safety- related turbine lube oil pump. The failure of the dc supply breaker for the lube oil pump resulted
in significant damage to the main turbine.
At the foreign plant, the event was caused by a single failure of an insulator on the offsite
supply cable to one train of 4.16 kV safety-related switchgear. Smoke from the event spread, causing multiple failures in the switchgear, loss of both sources of offsite power to both trains, and total loss of power to one safety train. An unrelated failure of the other source of onsite
power led to a total loss of power to both trains. In addition, the loss of offsite power disabled
the backup station blackout power supply. An electrical fault occurring in medium voltage switchgear enclosure can cascade, causing
collateral damage within the switchgear and consequent loss of multiple circuits. When both
safety trains are supplied from the same offsite supply with a common upstream circuit breaker
(see Attachment 1), one fault in the supply circuit can disable offsite power to both redundant
trains. Operators ought to be aware of such a vulnerability and to have considered means to
isolate the faulted feeder if both offsite power sources could be affected by a fault in the feeder
circuit.
This information notice requires no specific action or written response. If you have any
questions about the information in this notice, please contact one of the technical contacts
listed below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.
/RA/
William D. Beckner, Program Director
Operating Reactor Improvements Program
Division of Regulatory Improvement Programs
Office of Nuclear Reactor Regulation
Technical contacts: Thomas Koshy, NRR James Lazevnick, NRR
(301) 415-1176 (301) 415-2782 E-mail: txk@nrc.gov E-mail: jjl@nrc.gov
Attachments:
1. AC Power Distribution System Figure
2. List of Recently Issued NRC Information Notices
ML013540193 Template No.: NRR-052 To receive a copy of this document, indicate in the box C=Copy w/o attachment/enclosure E=Copy with attachment/enclosure N = No copy
OFFICE REXB Tech Editor* C:EEIB RORP C RORP/DRIP
NAME EGoodwin* JCalvo* TKoshy /TK/ WBeckner /WDB/
DATE 01/02/02 7 / 31 /01 01/04/02 01/04/02 01/07/02
Attachment 1 AC Power
Distribution System
with Y Connection
to Safety Buses
VVVVVV 161 KV
VV VV Startup
VVVVVV
VV VV 345 KV Transformer
Startup
Transformer
Swing D/G
17 15 12 25 03 05 08 25
4.16 KV Safety Bus A EDG A 4.16 KV Safety Bus B EDG B
Attachment 2 LIST OF RECENTLY ISSUED
NRC INFORMATION NOTICES
_____________________________________________________________________________________
Information Date of
Notice No. Subject Issuance Issued to
_____________________________________________________________________________________
2001-19 Improper Maintenance and 12/17/2001 All holders of operating licenses
Reassembly of Automatic Oil for nuclear power reactors, Bubblers except those who have
permanently ceased operations
and have certified that fuel has
been permanently removed from
the reactor vessel.
2001-18 Degraded or Failed Automated 12/14/2001 All uranium fuel conversion, Electronic Monitoring, Control, enrichment, and fabrication
Alarming, Response, and licensees and certificate holders
Communications Needed for authorized to receive safeguards
Safety and/or Safeguards information. Information notice is
not available to the public
because it contains safeguards
information.
2001-17 Degraded and Failed 12/14/2001 All uranium fuel conversion, Performance of Essential enrichment, and fabrication
Utilities Needed for Safety and licensees and certificate holders
Safeguards authorized to receive safeguards
information. Information notice is
not available to the public
because it contains safeguards
information.
2001-08, Update on Radiation Therapy 11/20/2001 All medical licensees.
2001-16 Recent Foreign and Domestic 10/31/2001 All holders of operating licenses
Experience with Degradation of for pressurized-water reactors
steam Generator Tubes and (PWR), except those who have
Internals permanently ceased operations
and have certified that fuel has
been permanently removed from
the reactor.
______________________________________________________________________________________
OL = Operating License
CP = Construction Permit
|
---|
|
list | - Information Notice 2002-01, Metal Clad Switchgear Failures and Consequent Losses of Offsite Power (8 January 2002, Topic: Emergency Lighting, Overexposure)
- Information Notice 2002-02, Recent Experience with Plugged Steam Generator Tubes (17 July 2002)
- Information Notice 2002-03, Highly Radioactive Particle Control Problems During Spent Fuel Pool Cleanout (10 January 2002, Topic: Significance Determination Process, Overexposure, Regulatory Conference)
- Information Notice 2002-04, Wire Degradation at Breaker Cubicle Door Hinges (10 January 2002)
- Information Notice 2002-06, Design Vulnerability in BWR Reactor Vessel Level Instrumentation Backfill Modification (18 January 2002, Topic: Reactor Vessel Water Level)
- Information Notice 2002-07, Use of Sodium Hypochlorite for Cleaning Diesel Fuel Oil Supply Tanks (28 January 2002)
- Information Notice 2002-09, Potential for Top Nozzle Separation and Dropping of a Certain Type of Westinghouse Fuel Assembly (13 February 2002)
- Information Notice 2002-10, Manual Reactor Trip and Steam Generator Water Level Setpoint Uncertainties (28 June 2002, Topic: Safe Shutdown, Unanalyzed Condition, Operability Determination, Operability Assessment)
- Information Notice 2002-11, Recent Experience with Degradation of Reactor Pressure Vessel Head (12 March 2002, Topic: Boric Acid, Stress corrosion cracking, Pressure Boundary Leakage)
- Information Notice 2002-12, Submerged Safety-Related Electrical Cables (21 March 2002)
- Information Notice 2002-13, E-mail from H. Nieh, Oedo to A. Levin, Ocm, Et Al., Issuance of Information Notice 2002-13, Fwd: E-mail from D. Pickett T Davis-Besse Communication Plan (4 April 2002, Topic: Boric Acid, Unidentified leakage)
- Information Notice 2002-14, Ensuring a Capability to Evacuate Individuals, Including Members of the Public, from the Owner-Controlled Area (8 April 2002, Topic: Siren, Potassium iodide)
- Information Notice 2002-15, Hydrogen Combustion Events in Foreign BWR Piping (12 April 2002, Topic: Water hammer)
- Information Notice 2002-17, Attachment: Recent Misadministrations Caused by Incorrect Calibrations of STRONTIUM-90 Eye Applicators (30 May 2002, Topic: Brachytherapy)
- Information Notice 2002-18, Effect of Adding Gas Into Water Storage Tanks on the Net Positive Suction Head for Pumps (6 June 2002, Topic: Brachytherapy)
- Information Notice 2002-19, Medical Misadministrations Caused by Failure to Properly Perform Tests on Dose Calibrators for Beta-and-Low-Energy Photon-Emitting Radionuclides (14 June 2002, Topic: Brachytherapy, Overexposure)
- Information Notice 2002-21, Axial Outside-Diameter Crackling Affecting Thermally Treated Alloy 600 Steam Generator Tubing (1 April 2003, Topic: Boric Acid, Stress corrosion cracking)
- Information Notice 2002-22, Degraded Bearing Surfaces in Gm/Emd Emergency Diesel Generators (28 June 2002, Topic: Brachytherapy)
- Information Notice 2002-23, Unauthorized Administration of Byproduct Material for Medical Use (21 March 2006)
- Information Notice 2002-24, Potential Problems with Heat Collectors on Fire Protection Sprinklers (19 July 2002, Topic: Fire Protection Program, Brachytherapy)
- Information Notice 2002-25, Challenges to Licensees' Ability to Provide Prompt Public Notification and Information During An Emergency Preparedness Event (26 August 2002, Topic: Inadvertent Siren Activation, Siren, ANS Design Report)
- Information Notice 2002-25, Challenges to Licensees' Ability to Provide Prompt Public Notification and Information During an Emergency Preparedness Event (26 August 2002, Topic: Inadvertent Siren Activation, Siren, ANS Design Report)
- Information Notice 2002-26, Vermont Yankee July 2008 Evidentiary Hearing - Intervenor Exhibit NEC-JH 56, NRC Information Notice 2002-26, Supplement 2: Additional Flow-Induced Vibration Failures After a Recent Power Uprate (9 January 2004, Topic: Safe Shutdown, Power Uprate)
- Information Notice 2002-27, Recent Fires at Commercial Nuclear Power Plants in the United States (20 September 2002, Topic: Safe Shutdown, Temporary Modification)
- Information Notice 2002-28, Appointment of Radiation Safety Officers and Authorized Users Under 10 CFR Part 35 (27 September 2002, Topic: Brachytherapy)
- Information Notice 2002-29, (Errata): Recent Design Problems in Safety Functions of Pneumatic Systems (6 November 2002, Topic: Uranium Hexafluoride)
- Information Notice 2002-30, Control and Surveillance of Portable Gauges During Field Operations (30 October 2002, Topic: Brachytherapy, Moisture Density Gauge, Moisture-Density Gauge, Stolen)
- Information Notice 2002-31, Potentially Defective UF6 Cylinder Valves (1-inch) (24 March 2003, Topic: Uranium Hexafluoride)
- Information Notice 2002-31, Potentially Defective Uf6 Cylinder Valves (1-inch) (24 March 2003, Topic: Uranium Hexafluoride)
- Information Notice 2002-32, Electromigration on Semiconductor Integrated Circuits (31 October 2002)
- Information Notice 2002-33, Notification of Permanent Injunction Against Neutron Products Incorporated of Dickerson, Maryland (22 November 2002, Topic: Uranium Hexafluoride)
- Information Notice 2002-34, Failure of Safety-Related Circuit Breaker External Auxiliary Switches at Columbia Generating Station (25 November 2002, Topic: Uranium Hexafluoride)
- Information Notice 2002-35, Changes to 10 CFR Parts 71 and 72 Quality Assurance Programs (20 December 2002, Topic: Uranium Hexafluoride)
- Information Notice 2002-36, Incomplete or Inaccurate Information Provided to the Licensee And/Or NRC by Any Contractor or Subcontractor Employees (27 December 2002, Topic: Uranium Hexafluoride)
|
---|