Information Notice 1997-16, Preconditioning of Plant Structures, Systems, and Components Before ASME Code Inservice Testing or Technical Specification Surveillance Testing

From kanterella
(Redirected from ML031050353)
Jump to navigation Jump to search
Preconditioning of Plant Structures, Systems, and Components Before ASME Code Inservice Testing or Technical Specification Surveillance Testing
ML031050353
Person / Time
Site: Beaver Valley, Millstone, Hatch, Monticello, Calvert Cliffs, Dresden, Davis Besse, Peach Bottom, Browns Ferry, Salem, Oconee, Mcguire, Nine Mile Point, Palisades, Palo Verde, Perry, Indian Point, Fermi, Kewaunee, Catawba, Harris, Wolf Creek, Saint Lucie, Point Beach, Oyster Creek, Watts Bar, Hope Creek, Grand Gulf, Cooper, Sequoyah, Byron, Pilgrim, Arkansas Nuclear, Braidwood, Susquehanna, Summer, Prairie Island, Columbia, Seabrook, Brunswick, Surry, Limerick, North Anna, Turkey Point, River Bend, Vermont Yankee, Crystal River, Haddam Neck, Ginna, Diablo Canyon, Callaway, Vogtle, Waterford, Duane Arnold, Farley, Robinson, Clinton, South Texas, San Onofre, Cook, Comanche Peak, Yankee Rowe, Maine Yankee, Quad Cities, Humboldt Bay, La Crosse, Big Rock Point, Rancho Seco, Zion, Midland, Bellefonte, Fort Calhoun, FitzPatrick, McGuire, LaSalle, Fort Saint Vrain, Shoreham, Satsop, Trojan, Atlantic Nuclear Power Plant, Crane  Entergy icon.png
Issue date: 04/04/1997
From: Martin T
Office of Nuclear Reactor Regulation
To:
References
IN-97-016, NUDOCS 9704010236
Download: ML031050353 (10)


II

UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

WASHINGTON, D.C. 20555-0001

April 4,1997

NRC INFORMATION NOTICE 97-16: PRECONDITIONING OF PLANT STRUCTURES,

SYSTEMS, AND COMPONENTS BEFORE ASME

CODE INSERVICE TESTING OR TECHNICAL

SPECIFICATION SURVEILLANCE TESTING

Addressees

All holders of operating licenses or construction permits for nuclear power reactors.

Purpose

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice to alert

addressees to the potential for maintenance activities performed before surveillance testing

('preconditioning" or "grooming") to adversely affect the validity of the surveillance test results

for structures, systems, and components (SSCs or equipment). It is expected that recipients

will review the information for applicability to their facilities and consider actions, as

appropriate, to avoid similar problems. However, suggestions contained in this information

notice are not NRC requirements; therefore, no specific action or written response is

required.

Background

The NRC has had a longstanding concern about unacceptable preconditioning or grooming of

various SSCs before the performance of Technical Specification (TS) surveillance tests or

testing required by the American Society of Mechanical Engineers Boiler and Pressure

Vessel Code (the ASME Code) and the adverse effect such activity might have on the validity

of the test results.

Description of Circumstances

In recent years, inspection findings and notices of violation have revealed that licensees are

performing unacceptable preconditioning activities. The following examples are summaries of

inspection findings; additional details on each example can be found in the referenced

inspection reports.

Circuit Breakers

NRC Inspection Report (IR) 50-298/94-16 (Accession No. 9409150141) for Cooper Nuclear

Station identified that electrical loads were removed from a number of 480-volt circuit

breakers before surveillance testing was.performed. The NRC staff identified this as an

9D7 EJ AE

,

7-6/6 7 70O

IN 97-16 April 4, 1997 example of unacceptable preconditioning, a concern addressed in NRC Confirmatory Action

Letter issued on July 1, 1994. This concern formed part of the basis for a Severity Level IlIl

violation of 10 CFR Part 50, Appendix B, Criterion Xl, 'Test Control," issued on

December 12, 1994 (Accession No. 9412140006). In addition, IR 50-298/94-16 discussed a

surveillance procedure that contained instructions requiring technicians to inspect, clean, and

lubricate several breakers before performing the "as-found" testing of several breaker

functions. Since these functions (e.g., trip force of the operating mechanism, undervoltage

trip, time delay attachments, etc.) could have been affected by the cleaning and lubrication, the test results did not represent the as-found condition of the breakers.

In NRC IR 50-298/94-31 (Accession No. 9506280604) for Cooper station, the NRC staff

evaluated the effectiveness of the licensee's corrective actions in response to the

preconditioning issues identified in IR 50-298/94-16. In order to address this violation, the

licensee had reviewed over 6,400 procedures, including maintenance procedures, and found

approximately 168 procedures that contained potential preconditioning activities. The

inspectors verified that the licensee had revised these procedures to address these concerns.

Emergency Diesel Generators

NRC IR 50-315/316-95010(DRP) (Accession No. 9511280025) for D.C. Cook identified that

the licensee's policy was to use the air start system to turn over (roll) the emergency diesel

generator (EDG) crankshafts with the cylinder petcocks open to purge (blow down) any

accumulated water or oil before the surveillance test was performed. Since this activity was

performed to prevent potential damage caused by hydrolocking during the surveillance test

starts, the safety benefit of rolling the diesels outweighed the benefit of testing in the

as-found condition. However, the staff was concerned that air start valves were used

(unnecessarily) to roll the EDGs when this activity could have been performed manually by

"barring over" the crankshaft. Barring over the crankshaft would have avoided the possibility

of preconditioning the air start valves and would have ensured that they were being tested in

an as-found condition. NRC IR 50-315/316-95013(DRP) (Accession No. 9602200321)

identified the practice of using the air start system to roll the EDGs prior to surveillance

testing as a failure to test safety-related equipment under suitably controlled conditions and in

accordance with design and licensing bases. This failure was cited as a violation of 10 CFR

Part 50, Appendix B, Criterion II, "Quality Assurance Program."

Hydrogen Analyzer Calibration

NRC IR 50-416/95-21 (Accession No. 9602290202) for the Grand Gulf Nuclear Station

identified that the containment and drywell hydrogen analyzer calibration surveillance

procedure required technicians to check reagent gas flow before calibration of the analyzer

and to make an adjustment, if necessary, to the previous test value before obtaining the

"as-found" calibration data. Since adjusting the reagent gas flow could change the as-found

condition of the analyzer and invalidate the surveillance test results, the inspectors

IN 97-16 April 4, 1997 determined that the test procedure was inadequate and cited it as a violation of TS 5.4.1.a.,

which requires that specific written procedures be established for surveillance tests as

described in Regulatory Guide 1.33, "Quality Assurance Program Requirements."

Turbine Driven Auxiliary Feedwater Pumps

NRC IR 50-315/316-95013(DRP) (Accession No. 9602200321) for D.C. Cook Units I and 2 identified the practice of operating the turbine-driven auxiliary feedwater pumps immediately

before performing the surveillance tests and the practice of venting the residual heat removal

pumps immediately before performing surveillance tests as examples of unacceptable

preconditioning. The failure to test safety-related equipment under suitably controlled

conditions and in accordance with design and licernsing bases was cited as a violation of

10 CFR Part 50, Appendix B, Criterion II.

High-Pressure Coolant Injection and Reactor Core Isolation Cooling

NRC IR 50-298/95-04 (Accession No. 9505230003) for Cooper Nuclear Station indicated that

plant operators had recognized that performing a series of different high-pressure coolant

injection system and reactor core isolation cooling surveillance tests in sequence, without

allowing sufficient time for the systems to cool down between tests, would constitute

unacceptable preconditioning. However, the operators did not identify nor document the full

extent of the preconditioning concerns, nor did they initiate appropriate corrective actions to

ensure that preconditioning would not be repeated. The failure of the operators to fully

recognize and initiate action to correct preconditioning concerns was cited as a violation of

10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings."

Motor Operated Valves

NRC IR 50-335/96-11, 50-389/96-11 (Accession No. 9609170377) for the St. Lucie reactor

facility identified that the four containment spray flow control valves (two for each unit) were

being unacceptably preconditioned prior to surveillance testing. Specifically, the valve stems

were being lubricated prior to performing stroke time testing. The failure of the licensee's

administrative procedures to ensure that these stroke time tests were performed under

suitably controlled conditions was cited as a violation of 10 CFR Part 50, Appendix B,

Criterion Xl, 'Test Control."

Discussion

As illustrated in the above-mentioned examples, some licensees are continuing to perform

maintenance activities or to take other preconditioning actions that were found to be

unacceptable. When performing technical specification surveillance and ASME Code

inservice testing, the equipment is typically tested in the as-found condition. However, experience has demonstrated that some surveillance testing cannot be performed without

disturbing or altering the equipment (e.g., attachment of test leads, pneumatic or hydraulic

supply lines). For example, circuit breakers may be required to be racked out and installed

on a test rig in order to perform some surveillance tests. However, cycling, cleaning, and

IN 97-16 April 4, 1997 lubrication were not necessary in order to perform the surveillance test. Similarly, other

equipment, such as valves, pumps, and motors may require disconnection, realignment, installation of jumpers, or other alterations in order to perform the surveillance tests.

Any such disturbance or alteration would be expected to be limited to the minimum necessary

to perform the test and prevent damage to the equipment.

In certain cases, the safety benefit of some preconditioning activities may outweigh the

benefits of testing in the as-found condition. For example, the staff has approved the

practice of routine checking of EDG cylinders for water accumulation before performing

surveillance tests in order to prevent the damage caused by hydrolocking. In the previously

described EDG example, the concern was that use of the air start valves was not needed to

roll the EDG and purge the cylinders.

The following guidance has been provided to NRC inspectors:

1.

Inspection Procedure (IP) 61726, "Surveilldnce Operations," directs inspectors to

condu.ct a detailed technical review of the licensee's surveillance procedure and

evaluate its adequacy to demonstrate that the system components will function under

design-basis conditions and that any preconditioning required by the procedure is

acceptable.

2.

IP 62707, "Maintenance Observation," cautions inspectors to verify that preventive

maintenance (PM) activities are not routinely being scheduled to "precondition"

equipment before performing surveillance tests in order to ensure that the test is

passed satisfactorily. It directs inspectors to examine the sequence of PM activities to

determine whether the licensee routinely schedules PM activities before surveillance

tests.

3.

NUREG-1482, "Guidelines for Inservice Testing at Nuclear Power Plants," Section 3.5, notes that the as-found condition is generally considered to be the condition of a valve

without pre-stroking or maintenance and that most inservice testing is performed in a

manner that generally represents the condition of a standby component if it were

actuated in the event of an accident (i.e., no preconditioning before actuation).

Related Generic Communications

The NRC staff has addressed the issue of preconditioning in previous generic

communications including Information Notice (IN) 96-24, "Preconditioning of Molded-Case

Circuit Breakers Before Surveillance Testing," and IN 93-63, "Periodic Testing and Preventive

Maintenance of Molded-Case Circuit Breakers."

KJ~

IN 97-16 April 4, 1997 This information notice requires no specific action or written response. If you have any

questions about the information in this notice, please contact the technical contact listed

below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

Thomas T. Martin, Director

Division of Reactor Program Management

Office of Nuclear Reactor Regulation

Technical contact: Charles D. Petrone, NRR

(301) 415-1027 E-mail: cdp@nrc.gov

Attachment: List of Recently Issued NRC Information Notices

14

_

f

A

g

X

Zr

Attachment

IN 97-16

April 4, 1997 LIST OF RECENTLY ISSUED

NRC INFORMATION NOTICES

Information

Date of

Notice No.

Subject

Issuance

Issued to

97-15

Reporting of Errors

and Changes in Large- Break Loss-of-Coolant

Accident Evaluation

Models of Fuel Vendors

and Compliance with

10 CFR 50.46(a)(3)

04/04/97

All holders of OLs

or CPs for nuclear

power reactors and

all reactor fuel

vendors

97-14

97-13

97-12

92-27, Supp. 1

97-11

Assessment of Spent

Fuel Pool Cooling

Deficient Conditions

Associated with Pro- tective Coatings at

Nuclear Power Plants

Potential Armature

Binding in General

Electric Type HGA

Relays

Thermally Induced

Accelerated Aging

and Failure of ITE/

Gould A.C. Relays

Used in Safety-Related

Applications

Cement Erosion from

Containment Subfounda- tions at Nuclear Power

Plants

03/28/97

03/24/97

03/24/97

03/21/97

03/21/97

All holders of OLs

or CPs for nuclear

power reactors

All holders of OLs

or CPs for nuclear

power reactors

All holders of OLs

or CPs for nuclear

power reactors

All holders of OLs

or CPs for nuclear

power reactors

All holders of OLs

or CPs for nuclear

power reactors

OL = Operating License

CP = Construction Permit

I

11* ; .

IN 97-16 April 4, 1997 This information notice requires no specific action or written response. If you have any

questions about the information in this notice, please contact the technical contact listed

below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

original signed by T.R. Quay

Thomas T. Martin, Director

Division of Reactor Program Management

Office of Nuclear Reactor Regulation

Technical contact: Charles D. Petrone, NRR

(301) 415-1027 E-mail: cdp@nrc.gov

Attachment: List of Recently Issued NRC Information Notices

Tech Editor has reviewed and concurred on 03/09/97

  • SEE PREVIOUS CONCURRENCE

DOCUMENT NAME: 97-16.IN

To receive a copy of this document. hkdceate In the box: 'C'

- Copy w/o

attachmentlenclosure

E' -

Copy w/attachment/enblosure

N -

No copy

OFFICE

TECH CONT

I

C:PECB

D:DRPI

NAME

CPetrone*

AChaffee*

TMartin

krN'-f

DATE

03/14/97

03/24/97

3/31 /97

OFFICIAL RECORD COP

IN 97-xx

March,

1997 This information notice requires no specific action or written response. If you have any

questions about the information in this notice, please contact the technical contact(s) listed

below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

Thomas T. Martin, Director

Division of Reactor Program Management

Office of Nuclear Reactor Regulation

Technical contact: Charles D. Petrone, NRR

(301) 415-1027 E-mail: cdp@nrc.gov

Attachment: List of Recently Issued NRC Information Notices

  • SEE PREVIOUS CONCURRENCE

DOCUMENT NAME: G:ICDP\\PRECONDT.006 To receive a copy of this document, Indicate in the box C=Copy wlo attachment/enclosure E=Copy with attachment/enclosure N = No copy

lOFFICE

PECB*

l

EELB*

lJ

EMEB*

lZ 1 D:_DRPM

l

NAME

CPetrone:jkd

JCalvo

RWessman

1 TMartin

II

-9A

I

I

2- DAT

3/14/97

13/11197

3/05/97

34~ff97

31 /97

.Ar

%

WaA

-~

vrr%.IPIAL MCLPMU %Vurl

440-Y311 0 -/

IN 97-xx

March , 1997 This information notice requires no specific action or written response. If you have any

questions about the information in this notice, please contact the technical contact(s) listed

below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

Thomas T. Martin, Director

Division of Reactor Program Management

Office of Nuclear Reactor Regulation

Technical contact:

Charles D. Petrone, NRR

(301) 415-1027 E-mail: cdp@nrc.gov

Attachment: List of Recently Issued NRC Information Notices

  • SEE PREVIOUS CONCURRENCE

DOCUMENT NAME: G:ACDPPRECONDT.OO6 To receive a copy of this document, indicate in the box C=Copy wlo attachment/endosure E=Copy with attachnentlendosure N = No copy

l FIE

PECB*

l

EELB*

l

EMEB*

l

C:PECB

L

D:DRPM

l1 NAME

CPetrone:jkd

JCalvo

RWessman

AChaffee

TMartin

DATE

3/14/97

13/11/97

13/05/97

2/ /97

12//97

'rM

i vrflfl

A

I DV

OFFILPIAL MCtoVMU %o!rT

-

'

-1)

'3\\

IN 97-xx

March , 1997 This information notice requires no specific action or written response. If you have any

questions about the information in this notice, please contact the technical contact(s) listed

below or the appropriate Office of Nuclear Reactor Regulation (NRR) project manager.

Thomas T. Martin, D ctor

Division of React

rogram Management

Office of Nucde

Reactor Regulation

Technical contact:

Charles D. Petrone, NRR

(301) 415-1027 E-mail: cdpenrc.gov

Attachment: List of Recently Issued NRC Informati Notices

DOCUMENT NAME: GACDPPRECONDT.O

To receive a copy of this document, indicate In the box d=dopy wo chment/endosure E=Copy with attachment/endosure N = No copy

[

OFFICE

PECB

[

j

j

7jEELB

ZiAIJ

EMEB

D:DRPM

NAME

CPetrone:jkd

JCalvo

n'

/

J

AChaffee

TMartin

l DATE

3?i

7

11119_7

/__197_21

1

97 21197

-

OFFICAL RECORD COPY