Information Notice 2019-01, Inadequate Evaluation of Temporary Alterations

From kanterella
(Redirected from Information Notice 2019-01)
Jump to navigation Jump to search
Inadequate Evaluation of Temporary Alterations
ML18115A338
Person / Time
Site: Peach Bottom, Salem, Watts Bar, Sequoyah  PSEG icon.png
Issue date: 03/12/2019
From: Alfred Issa
NRC/NRR/DIRS/IOEB, NRC/NRR/DIRS/IRGB
To:
Benney B
References
IN-19-001
Download: ML18115A338 (5)


UNITED STATES

NUCLEAR REGULATORY COMMISSION

OFFICE OF NUCLEAR REACTOR REGULATION

OFFICE OF NEW REACTORS

WASHINGTON, DC 20555-0001 March 12, 2019 NRC INFORMATION NOTICE 2019-01: INADEQUATE EVALUATION OF TEMPORARY

ALTERATIONS

ADDRESSEES

All holders of an operating license or construction permit for a nuclear power reactor under

Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Domestic Licensing of

Production and Utilization Facilities, except those that have permanently ceased operations

and have certified that fuel has been permanently removed from the reactor vessel.

All holders of and applicants for a combined license under 10 CFR Part 52, Licenses, Certifications, and Approvals for Nuclear Power Plants.

PURPOSE

The U.S. Nuclear Regulatory Commission (NRC) is issuing this information notice (IN) to alert

licensees about recent operating experience at nuclear power facilities where temporary

alterations were installed that either negatively impacted the operability of affected Systems, Structures, and Components or without performing required 10 CFR 50.59 reviews.

The NRC expects that recipients will review the information contained in this IN for applicability

to their facilities and consider actions, as appropriate, to avoid similar issues. INs may not

impose new requirements, and nothing in this IN should be interpreted to require specific action.

DESCRIPTION OF CIRCUMSTANCES

Sequoyah, Units 1 and 2

On November 24, 2018, the licensee for Sequoyah, Units 1 and 2, discovered that a door was

blocked open to allow a hose to be routed from an outside vacuum truck to an ice bin inside the

Unit 2 Additional Equipment Building without meeting the compensatory measures required by

the related breach permit. This condition created a breach of the auxiliary building secondary

containment enclosure (ABSCE) boundary that exceeded the allowed ABSCE breach margin of

three minutes. As a result, Unit 1 entered Technical Specification (TS) Limiting Condition of

Operation 3.7.12, Condition B for two trains of Auxiliary Building Gas Treatment System

(ABGTS) inoperable due to an inoperable ABSCE boundary in MODE 1, 2, 3, or 4, and both

Units entered Condition E for one required ABGTS train inoperable with fuel stored in the spent

fuel pool. The event was caused by a failure to cover in the pre-job brief the ABSCE breach

permit, required compensatory measures and internal and external operating experience.

Corrective actions included closing the door and revising the associated work order to add a

hold point to ensure the ABSCE permit is reviewed, understood, and adhered to prior to and

during the breach. See Licensee Event Report 2018-002-00, Exceeded Breach Margin

Renders Both Trains of the Auxiliary Building Gas Treatment System Inoperable dated January

ML18115A338 22, 2019, (Agencywide Documents Access and Management System (ADAMS) No.

ML19022A040) for more details.

Sequoyah, Units 1 and 2

On March 3, 2017, Door A212 was improperly breached at the Sequoyah nuclear power plant to

facilitate a continuous fire watch. Although a fire protection impairment permit was generated, the permit did not evaluate the impact of the breach on the ABSCE boundary. On March 7,

2017, a senior reactor operator discovered the breach during a walk down of the Auxiliary

Building. The breach resulted in the inoperability of two trains of the ABGTS due to an

inoperable ABSCE boundary. An evaluation determined the cause to be a less than adequate

single barrier breaching standard. A contributing cause was an inconsistent approach to entry

into the barrier breaching process. In addition to restoring operability by closing the door, corrective actions included revising the breaching procedure to address all possible breaches

and to include a matrix for doors and their associated impacts. See Licensee Event Report

2017-001-00 Breached Door Renders Both Trains of the Auxiliary Building Gas Treatment

System Inoperable dated April 26, 2017, (ADAMS No. ML17117A495) for more details.

Salem, Unit 2

On August 26, 2015 and again on or about September 10, 2015, NRC inspectors conducting

walkdowns at the Salem, Unit 2 while in Mode 1, noted that the boric acid evaporator rooms

interior wall had been removed while two watertight doors were fully open. Given Salem TS 3.7.7 requires that auxiliary building differential pressure be slightly negative in Mode 1, the

inspectors made the control room aware of concerns regarding operability of the auxiliary

building differential pressure as well as the impairment of the barrier. The licensee closed the

outer watertight doors and subsequently, confirmed the doors classification as high energy line

break (HELB) and flooding doors. The impairment required a plant barrier impairment (PBI)

which had not been previously completed. In addition, the licensee determined that removing

the interior wall made the evaporator room part of the auxiliary building contiguous zone

envelope. The licensees investigation and causal evaluation determined that technicians had

breached the metal panel that formed the interior wall of the evaporator room on or around

November 11, 2014, and that the outer doors had been opened on numerous occasions from

that time through September 2015. The licensee determined that one apparent cause was

inadequate procedural guidance that resulted in work planners not requesting a PBI, personnel

not meeting the intent of the attendant requirement, and departments not requiring proof that the

Technical Specifications would be met prior to opening the doors. Corrective actions included

properly implementing barrier controls that included compensatory actions for the flooding and

occupational radiation barrier aspects of the program.

As a result, the NRC inspectors issued a non-cited violation for the improper implementation of

barrier controls while performing maintenance that could affect the performance of the auxiliary

building envelope. NRC Inspection Report 05000272/2015004 and 05000311/2015004, dated

February 10, 2016 (ADAMS No. ML16043A169), provides more details about this finding.

Salem, Units 1 and 2

On October 3, 2013, an NRC Resident Inspector observed that the Turbine Driven Auxiliary

Feedwater (TDAFW) pump room enclosure HELB barrier door was being held open for an

extended period by an assigned door attendant. The Motor Driven Auxiliary Feedwater

(MDAFW) pumps are located adjacent to the enclosure such that if a secondary steam HELB

event were to occur in the TDAFW pump room while its door was open or disabled, the steam

ML18115A338 plume from the room could render both MDAFW pumps inoperable. The cause of this event is

attributed to an organizational failure to ensure that guidance provided in plant HELB program

procedures contained sufficient justification for compensatory actions used for barrier

impairments. Corrective actions taken by the licensee included: a plant-wide communication

was made describing the HELB event and its impact on operability of plant equipment; a

revision to the Operability Assessment and Equipment Control Program procedure was made to

ensure it conforms to the guidance of NRC Regulatory Issue Summary 2001-09, Control of

Hazard Barriers; and permanent signs were installed on all HELB barrier doors prohibiting them

from being blocked open without authorization from Salem Operations. See Licensee Event

Report 2014-001-00, High Energy Line Break Door Blocked Open During Maintenance Activity

dated March 10, 2014 (ADAMS No. ML14069A245), for more details.

Watts Bar, Unit 1

On July 9, 2012, inspectors from the NRC identified a finding related to a failure to correctly

translate the design basis related to onsite flooding into the instructions for a plant design

change temporary alteration. Specifically, a procedure provided a means to erect a temporary, water-tight flood barrier around both trains of the Thermal Barrier Booster Pumps (TBBP). This

barrier was designed to be sealed with a sealant that would not prevent water intrusion as

required. Additional design issues were identified by the inspectors on July 14, 2012, that

included: (1) the lack of adequate preparation/cleaning of surfaces as recommended by the

sealant manufacturer prior to applying the sealant; (2) failure to perform load calculations for

panel deformation; and (3) failure to include provisions in the design and installation to support

the temporary panels to resist deflection from hydrostatic pressure/force and potential uplift

forces, since the panels were not anchored to the floor. As a result, the TBBP flood barrier

would have failed during a probable maximum flood event, thereby submerging the TBBPs and

rendering the equipment inoperable. Corrective actions included the removal of the installed

panel assembly and its replacement. The replacement activity included the preparation/

cleaning of surfaces to be sealed and the use of an approved sealant primer, as recommended

by the sealant manufacturer, prior to applying the sealant. A vertical brace was also installed to

resist potential uplift forces. NRC Inspection Report 05000390/2012009, dated March 12, 2013 (ADAMS No. ML13071A289), provides more details about this finding.

Peach Bottom, Unit 3

Between January 21, 2009 and September 9, 2009, the licensee for Peach Bottom, Unit 3 declared the E Wide Range Neutron Monitor (WRNM) inoperable and installed a jumper that

bypassed its trip feature instead of using the WRNM bypass switch as is described in their

plant's Final Safety Analysis Report. Since only 3 of 4 WRNMs were required by Technical

Specifications, no action statement was entered and installing the jumper was thought to be

acceptable. However, installing the jumper was done without performing a 10 CFR 50.59 review. This installation involved a facility change that likely would have required a license

amendment before its implementation. Corrective actions included entering the issue into the

licensees Corrective Action Program and the removal of the jumper restoring the system to its

configuration. For more details, see NRC Inspection Report 05000277/2009004 and

05000278/2009004, Peach Bottom Atomic Power Station - NRC Integrated Inspection Report

dated November 12, 2009 (ADAMS No. ML093160608).

DISCUSSION

The above events highlight the need to adequately establish and implement procedural controls

for temporary alterations to insure their compliance with the requirements of all NRC regulations

ML18115A338 such as 10 CFR 50.59, Changes, tests and experiments and 10 CFR 50.65, Requirements for

monitoring the effectiveness of maintenance at nuclear power plants. The first five events

resulted in equipment inoperability while the sixth event resulted in a violation of 10 CFR 50.59 requirements.

NRC Regulatory Guide 1.187, Guidance for Implementation of 10 CFR 50.59, Changes, Tests, and Experiments, endorses the Nuclear Energy Institute (NEI) document NEI 96-07, Guidelines for 10 CFR 50.59 Evaluations, Revision 1 ADAMS No. ML003771157). Temporary

alterations include jumpering terminals, lifting leads, placing temporary lead shielding on pipes

and equipment, removal of barriers, and use of temporary blocks, bypasses, scaffolding and

supports. Although the requirements of 10 CFR 50.59 do not generally apply to temporary

alterations, there are some exceptions that are listed in NEI 96-07. Exceptions include

compensatory actions to address degraded or nonconforming conditions, and temporary

alterations expected to be in effect during at-power operations for more than 90 days. In

addition, regardless of whether the requirements of 10 CFR 50.59 apply, Section 4.1.2, Maintenance Activities of NEI 96-07, requires licensees to ensure equipment operability in

accordance with the technical specifications is maintained as a result of maintenance activities

and to assess and manage their risk impact per 10 CFR 50.65(a)(4). Note that maintenance

activities include temporary alterations.

Related NRC Generic Communications

The NRC has previously issued the following two related generic communications:

Information Notice 2007-29, Temporary Scaffolding Affects Operability of Safety-Related

Equipment, dated September 17, 2007, describes similar issues to the ones discussed in this

IN as they relate to scaffolding. Events discussed include scaffolding that: interferes with the

operation of equipment, blocks access to fire protection equipment, is improperly braced to

prevent sliding during use or during a seismic event, or is attached to instrument racks or piping

supports without adequate justification.

Regulatory Issue Summary 2001-09, Control of Hazard Barriers, dated April 2, 2001, clarifies

the NRC position on the temporary removal of hazard barriers.

CONTACT

S

Please direct any questions about this matter to the technical contact listed below.

Christopher G. Miller, Director Timothy J. McGinty, Director

Division of Inspection and Regional Division of Construction Inspection and

Support Operational Programs

Office of Nuclear Reactor Regulation Office of New Reactors

Technical Contacts: Alfred Issa, NRR Brian Benney, NRR

301-415-5342 301-415-2767 E-mail: Alfred.Issa@nrc.gov Email: Brian.Benney@nrc.gov

Note: NRC generic communications may be found on the NRC public Web site, http://www.nrc.gov, under NRC Library.

ML18115A338

ML18115A338 OFFICE NRR/DIRS/IOEB QTE RES/DE/RGGIB NRO/DCIP/CIPB

NAME AIssa JDougherty TBoyce VHall

DATE 2/26/2019 9/26/2018 9/28/2018 2/13/19 OFFICE NRR/DIRS/IOEB NRR/DIRS/IRGB NRR/DIRS/IRGB NRO/DCIP

NAME RElliott BBenney TInverso TMcGinty

DATE 2/4/2019 2/26/2019 2/26/2019 02/27/2019 OFFICE NRR/DIRS

CMiller

NAME

/RA by B. Dickson for/

DATE 03/12/2019