IR 05000445/2023003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000445/2023003 and 05000446/2023003
ML23297A249
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/25/2023
From: Greg Werner
NRC/RGN-IV/DORS/PBB
To: Peters K
Vistra Operations Company
References
IR 2023003
Download: ML23297A249 (25)


Text

October 25, 2023

SUBJECT:

COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 -

INTEGRATED INSPECTION REPORT 05000445/2023003 AND 05000446/2023003

Dear Ken Peters:

On September 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Comanche Peak Nuclear Power Plant, Units 1 and 2. On October 12, 2023, the NRC inspectors discussed the results of this inspection with Steven Sewell, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Two of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Comanche Peak Nuclear Power Plant, Units 1 and 2.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Comanche Peak Nuclear Power Plant, Units 1 and 2. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory E. Werner, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket Nos. 05000445, 05000446 License Nos. NPF-87, NPF-89 Enclosure:

As stated cc w/ encl: Distribution via LISTSERV Signed by Werner, Gregory on 10/25/23

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Comanche Peak Nuclear Power Plant,

Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure To Establish Adequate Procedures for Oversight of Vendor Activities on Safety-related Systems.

Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000446/2023003-01 Open/Closed

[H.14] -

Conservative Bias 71111.08P The inspectors identified a Green, non-cited violation of 10 CFR Part 50, Appendix B,

Criterion IX, Control of Special Processes, for failure to establish measures to assure that special processes such as mechanical stress improvement are controlled and accomplished by qualified personnel using qualified procedures in accordance with applicable codes, standards, specifications, criteria, and other special requirements. Contrary to this, the licensee allowed the vendor to make physical changes to contour rings for the mechanical stress improvement process box press units without evaluating these changes to the design control measures commensurate with those applied to the original equipment design.

Inadequate Procedures Lead to Seal Failure on A Filter Housing Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000445/2023003-02 Open/Closed

[P.5] -

Operating Experience 71152A The inspector identified a finding and associated Green, non-cited violation of Technical Specification 5.4.1 for failing to have a procedure(s) appropriate to the circumstances for replacing a filter and restoring a reactor coolant pump seal cooling filter to service.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period ascending to 100 percent power from 78 percent power following repair of main feedpump 1-02. Unit 2 operated at or near 100 percent power for the entire inspection report.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Unit 2, train B diesel generator starting air system on August 23.
(2) Unit 2, turbine driven auxiliary feedwater pump and train B motor driven auxiliary feedwater pump on August 30, 2023.
(3) Unit 1, train A safety injection system on September 7, 2023
(4) Unit 1, train B safety chiller system on September 18, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1, auxiliary building charging pump rooms on July 6, 2023
(2) Unit 2, auxiliary building charging pump rooms on July 6, 2023
(3) Unit 1, safeguards building elevation 773 on September 5, 2023
(4) Unit 2, auxiliary building on September 5, 2023
(5) Unit 2, cable spreading room on September 8, 2023

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an unannounced fire drill on July 20, 2023.

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in both Units 1 and 2 for the safety chiller system located within rooms 115A and 115B.

===71111.08P - Inservice Inspection Activities (PWR) The inspectors verified that the reactor coolant system (RCS) boundary, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from May 1 to 11, 2023.

PWR Inservice Inspection Activities Sample - Nondestructive Examination and Welding Activities (IP Section 03.01)===

The inspectors verified that the following nondestructive examination and welding activities were performed appropriately:

(1) Ultrasonic Examination
  • safety injection, TCX-1-4301-9, pipe to elbow
  • safety injection, TCX-1-4301-10, pipe to elbow
  • steam generator 4, TCX-2-1100-4-11, nozzle to vessel Dye Penetrant Examination

Activities (IP Section 03.02) (1 Sample)

The inspectors verified that the license conducted the following vessel upper head penetration inspections and addressed any identified defects appropriately:

(1)

  • Reactor vessel upper head, penetration 66 to 73, thermal sleeve wear check PWR Inservice Inspection Activities Sample - Boric Acid Corrosion Control Inspection Activities (IP Section 03.03) (1 Sample)

The inspectors verified the licensee is managing the boric acid corrosion control program through a review of the following evaluations:

(1)

  • 2014-013333
  • 2018-003490
  • 2020-003068
  • 2022-001784
  • 2022-002065
  • 2022-002987
  • 2022-000367
  • 2022-002069
  • 2022-003052
  • 2022-008373
  • 2023-001501
  • 2023-000810 PWR Inservice Inspection Activities Sample - Steam Generator Tube Inspection Activities (Section 03.04) (1 Sample)

The inspectors verified that the licensee is monitoring the steam generator tube integrity appropriately through a review of the following examinations:

(1)

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from August 14, 2023, to September 21, 2023.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator simulator training on steam generator tube rupture on July 18, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)safeguards building ventilation (2)auxiliary building heating, ventilation, air conditioning for exceeding performance criteria on March 11, 2021.

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)freeze seal for 2-8511B, charging system alternate minimum flow valve on September 13, 2023 (2)planned safety chiller outage on September 19, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (6 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Unit 2, ventilation operability due to elevated ventilation exhaust temperatures in Unit 2 safeguards building
(2) Unit 2, power range nuclear instrument due to step increase in indicted flux (3)component cooling water pump 2-01 with tygon tubing left in bearing oil chamber (4)main steam isolation valves with air blowing out of pneumatic pump (5)emergency core cooling system while impacted by reactor coolant pump (RCP) seal filter failure (6)functionality of main turbine lube oil with a lube oil cooler leak

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Unit 1, train B heater drain pump temporary modification to allow oil to flow on pump trip on September 8, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (2 Samples)

(1) Unit 1, RCP seal injection filter change on July 19, 2023.
(2) Unit 1, safety chiller 1-05 compressor replacement/reinstallation on September 24, 2023.

Inservice Testing (IST) (IP Section 03.01) (2 Samples)

(1) Unit 2, train B safety injection pump inservice test on September 5, 2023
(2) Unit 2, train B residual heat removal pump inservice test on September 7, 2023

71114.01 - Exercise Evaluation

Inspection Review (IP Section 02.01-02.11) (1 Sample)

(1) The inspectors evaluated the biennial emergency plan exercise conducted on July 26, 2023. The exercise scenario simulated a station service water pump motor fire followed by a condensate pump trip, anticipated transient without scam with actions in the control room successful in tripping the unit, and a loss of coolant accident with fuel failure. During the scenario, a subsequent valve failure caused a radiological release. As conditions degraded during the scenario, the licensee developed protective actions recommendations for the public. The licensee completed its critique process for the exercise on August 23, 2023, and the inspectors subsequently evaluated the effectiveness of the critique process to identify performance weaknesses and deficiencies to ensure they were entered into the corrective action program for resolution.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • Emergency Plan Revision 48 - effective July 5, 2023 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (2 Samples)

The inspectors evaluated:

(1) The inspectors observed a simulator training session with emergency action level declaration and notification on September 11, 2023.
(2) The inspectors observed a site wide emergency planning drill on September 27,

RADIATION SAFETY

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (3 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) Unit 1, auxiliary building ventilation system discharge to main plant vent stack
(2) Unit 2, auxiliary building ventilation system discharge to main plant vent stack
(3) Units 1 and 2, liquid waste processing system discharge to circulating water system

Sampling and Analysis (IP Section 03.02) (4 Samples)

Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:

(1) Unit 1, tritium gas sample for plant vent stack on August 8, 2023
(2) Unit 1, noble gas sample for plant vent stack on August 8, 2023
(3) Unit 2, iodine cartridge sample for plant vent stack on August 8, 2023
(4) Unit 2, particulate filter sample for plant vent stack on August 8, 2023

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1) Dose calculations associated with liquid release permits:

L2021-019, L2021-031, L2022-015, L2022-027, L2023-010, and L2023-022

(2) Dose calculations associated with gaseous release permits:

G2021-082, G2021-083, G2022-076, G2022-087, G2023-073, and G2023-086 Abnormal Discharges (IP Section 03.04)

The inspectors evaluated the inspection period and identified no abnormal discharges to review.

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative program to identify incomplete or discontinued program elements.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (July 1, 2022, through June 30, 2023)
(2) Unit 2 (July 1, 2022, through June 30, 2023)

MS07: High Pressure Injection Systems (IP Section 02.06) (2 Samples)

(1) Unit 1 (July 1, 2022, through June 30, 2023)
(2) Unit 2 (July 1, 2022, through June 30, 2023)

MS09: Residual Heat Removal Systems (IP Section 02.08) (2 Samples)

(1) Unit 1 (July 1, 2022, through June 30, 2023)
(2) Unit 2, (July 1, 2022, through June 30, 2023)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (July 1, 2022, through June 30, 2023)
(2) Unit 2 (July 1, 2022, through June 30, 2023)

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 1, 2022, through June 30, 2023 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 1, 2022, through June 30, 2023 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) July 1, 2022, through June 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)

  • The inspectors reviewed failure of an O-ring in a RCP sealing cooling filter that resulted in loss of RCP seal cooling to two RCPs.

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed human performance issues that have occurred during 2023.

The inspectors noted multiple examples of minor deviations in site requirements that included late return of test equipment, failure to secure fire doors and food wrappers in radiologically controlled areas. Although of minor safety significance, these issues reveal lax standards of some licensee staff. In addition, identification of food wrappers in the radiologically controlled area and door were identified by NRC staff. This indicates weaknesses in peer-to-peer coaching or a lack of documenting minor issues.

INSPECTION RESULTS

Failure To Establish Adequate Procedures for Oversight of Vendor Activities on Safety-related Systems.

Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000446/2023003-01 Open/Closed

[H.14] -

Conservative Bias 71111.08P The inspectors identified a Green, non-cited violation of 10 CFR Part 50, Appendix B, Criterion IX, Control of Special Processes, for failure to establish measures to assure that special processes such as mechanical stress improvement are controlled and accomplished by qualified personnel using qualified procedures in accordance with applicable codes, standards, specifications, criteria, and other special requirements. Contrary to this, the licensee allowed the vendor to make physical changes to contour rings for the mechanical stress improvement process (MSIP) box press units without evaluating these changes to the design control measures commensurate with those applied to the original equipment design.

Description:

During the Fall 2021 refueling outage, the licensee attempted to perform the MSIP on the Unit 2 reactor vessel nozzles. This process used hydraulic box presses to apply circumferential pressure on the RCS hot and cold legs sufficient to compress the pipe at the nozzle. To achieve proper compression, hydraulic rams are pressurized to tens of thousands of pounds per square inch to apply compressive forces to the pipe in the vicinity of the weld.

During the attempt on hot leg 2 on October 20, 2021, both legs of the box press frame failed catastrophically resulting in numerous gouges/indentations on the hot leg piping. Contract workers had pressurized the hydraulics to near full pressure when both legs of the box press failed. The resulting release of pressure severely damaged the tooling and created multiple gouges on the hot leg. As part of recovery, the licensee evaluated each of the damaged areas and remediated the indentations to ensure removal of any stress risers. Post remediation measurement and analysis of the pipe revealed a substantial reduction in margin to the ASME code required minimum wall thickness. The licensee performed an operability determination, including engineering stress analysis to establish a basis for operability. The licensee stopped MSIP evolutions while evaluating the impact of the failure and considering potential causes of the failure. Although the licensee could not determine a cause in the near term, the licensee decided to proceed with MSIP on the cold leg nozzles under the rationale that the cold leg equipment was more robust than the equipment that had failed during the hot leg MSIP.

On October 23, 2021, during MSIP on cold leg 1, another box press failed. At the time of the failure, the licensee had attained about 90 percent of full hydraulic pressure. Review of the failure revealed the box press failed in a similar location/manner to the hot leg failure. With the multiple box press failures, the licensee opted to end further MSIP activities until the cause of the failures could be determined.

To implement MSIP, the vendor modified a clamp design that had been used effectively at other facilities. The redesigned contour rings offset the MSIP application plane inside the clamp assembly to within required parameters developed in the finite element analysis. The vendor modeled the new designs, independent of the overall assembly, and performed a fatigue analysis to confirm both would withstand the typical loads during MSIP application.

However, the vendor determined that this approach failed to evaluate all the interactions among the various components and piping used as part of MSIP. Although the vendors Quality Manual and procedures provided guidance on design preparation and verification including design, analysis, and testing requirements for safety related equipment, the vendor failed to apply them to the redesign of the contour rings. The vendor determined that the MSIP design changes were implemented using deficient processes and procedures to evaluate and document the impact. Because the licensee was not providing the required oversight of the vendors involved, the inadequate processes and procedures enabled these design changes that directly caused the failure of the MSIP presses and damage to the RCS.

Subsequent modeling using finite element analysis predicted a failure of the tooling consistent with the observed failure. Therefore, a robust design review, as required by the vendor procedures would have predicted stresses exceeding allowable values, thus providing insight that could have prevented these failures from occurring. By not requiring the vendor to follow their design review process, the licensee failed to meet the requirements of the Comanche Peak Nuclear Power Plant Quality Assurance Manual, revision 24, section 9.1 which states that the licensee shall establish measures to control special processes. These special processes shall be accomplished under specified and controlled conditions by qualified personnel using qualified procedures and equipment in accordance with applicable codes, standards, specifications, criteria, or other special requirements. A robust design review, as required by the licensee's quality assurance manual and the vendor's procedures would have predicted stresses exceeding allowable values, thus providing insight that could have prevented these failures from occurring. Additionally, the redesigned MSIP equipment was only tested to the application procedural limit, \\ leaving no margin between qualification and application limits and no tolerance for instrument uncertainties. The licensee elected to continue with the MSIP process without understanding the cause of the first MSIP press failure, resulting in the failure of the second MSIP and additional damage to the RCS.

A finite element analysis model performed as part of the root cause investigation indicated that the offset contour ring design caused the clamp to rotate, generating an unanticipated and unanalyzed acentric load through the MSIP tooling assembly. The reaction applied an unanalyzed load to the other parts of the MSIP tooling assembly contributing to the failure.

Significant engineering analysis was required to demonstrate that the RCS remained operable. The actual loads due to the failed MSIP exceeded the code allowable stress limit but were less than the allowable faulted loads for the reactor vessel design specification per Westinghouse Specification 952540, revision 1.

Corrective Actions: A root cause analysis was performed by the vendor, and an organization effectiveness investigation was performed by the licensee to evaluate and address shortfalls in the process controls, design, training, and decision making. This included a review and necessary updates to engineering guidance related to vendor oversight for major plant initiatives. To improve safety, quality and schedule execution in future outages, the station will use a team approach to investigate these issues. This review included a look at the licensee's use of industry operating experience when preparing for outages and how the station looks at preparation, proficiency and mitigation strategies with vendors and provides the guidance for vendor oversight.

Corrective Action References: CR-2021-006952, CR-2021-007070, CR-2021-7061, TR-2023-000211

Performance Assessment:

Performance Deficiency: The licensees failure to establish measures to assure that the mechanical stress improvement process is controlled and accomplished using properly qualified equipment as required by Comanche Peak Nuclear Power Plant Quality Assurance Manual, revision 24 is a performance deficiency. Specifically, section 9.1 requires that special processes shall be accomplished under specified and controlled conditions by qualified personnel using qualified procedures and equipment in accordance with applicable codes, standards, specifications, criteria, or other special requirements.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, equipment not qualified and tested in accordance with the licensees quality assurance manual and the vendors quality assurance program was used to perform MSIP on the RCS nozzles. Failure of the tooling resulted in damage to the class 1 pressure boundary and subjected the RCS to stress that exceeded ASME code general allowed load limits.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined the finding was of very low safety significance (Green) because:

(1) it was not a design deficiency;
(2) it did not represent a loss of system and/or function;
(3) it did not represent an actual loss of function of at least a single train for longer than its technical specification allowed outage time; and
(4) it did not result in the loss of a high safety significant non-technical specification train.

Cross-Cutting Aspect: H.14 - Conservative Bias: Individuals use decision making-practices that emphasize prudent choices over those that are simply allowable. A proposed action is determined to be safe to proceed, rather than unsafe to stop. Contrary to this, the licensee allowed the vendor to proceed with redesign and deployment of the new contour rings and continue MSIP evolutions with inadequate testing and understanding of the failure mechanism. This resulted in damage to the RCS and reduction in margin to minimum allowable wall thickness on the affected hot and cold leg piping of the RCS.

Enforcement:

Violation: Title 10 CFR Part 50, Appendix B, Criterion IX, Control of Special Processes, requires, in part, that the licensee establish measures to assure that special processes are controlled and accomplished by qualified personnel using qualified procedures in accordance with applicable codes, standards, specifications, criteria, and other special requirements.

Comanche Peak Nuclear Power Plant Quality Assurance Manual, revision 24, section 9.1 requires that special processes shall be accomplished under specified and controlled conditions by qualified personnel using qualified procedures and equipment in accordance with applicable codes, standards, specifications, criteria, or other special requirements.

Contrary to the above, prior to October 23, 2021, the licensee failed to maintain measures to assure that the design changes to the tooling used to perform the MSIP were controlled and accomplished by qualified personnel using qualified procedures in accordance with applicable codes, standards, specifications, criteria, and other special requirements. Specifically, the licensee failed to assure that the design changes that modified MSIP press used in the special process were properly controlled and accomplished in accordance with the design change control requirements.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Inadequate Procedures Lead to Seal Failure on A Filter Housing Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000445/2023003-02 Open/Closed

[P.5] -

Operating Experience 71152A The inspector identified a finding and associated Green non-cited violation of Technical Specification 5.4.1 for failing to have a procedure(s) appropriate to the circumstances for replacing a filter and restoring a RCP seal cooling filter to service.

Description:

On July 18, 2023, the licensee replaced filter 1-02 in the RCP seal water injection line due to rising differential pressure across the filter. Following replacement, the operators began restoration of the filter to service using procedure SOP-103A, "Chemical Volume Control System." Upon opening the inlet valve to the filter housing, control room operators noted seal injection flow lowering and could not recover seal flow via adjusting of 1C-0182, RCP water pressure controller. The reactor operator noted a drop in pressurizer level as well. The reactor operators called the field nuclear equipment operator (NEO) and directed the NEO to close the filter vent valve. About 30 seconds later, the reactor operator directed the NEO to close the filter inlet valve and ensure the outlet and drain vales were closed. The NEO isolated the filter and stopped inventory transient. During this event, RCS inventory lost about 170 gallons, pressurizer level dropped 60 percent to 57 percent and RCP seal flow dropped to less than 1 gallon per minute per pump. Procedure SOP-103A did not have steps in the procedure to verify leak tightness of the filter housing when returning to service.

The licensee determined that the leak resulted from failure of the filter lid O-ring. The mechanics stated that during installation the O-ring can become misaligned during reassembly and that alignment cannot be easily checked during the reassembly process, resulting on leakage. When asked by the inspectors, the mechanics indicated that leaks have happened during previous filter replacements that also required rework and replacement of the O-ring.

The inspectors searched the licensee's corrective action program and non-cap tracking database but could not located documentation that O-rings had previously become misaligned. The licensee conducted a similar search with the same results. The inspectors reviewed vendor documentation as well as site procedures for post-work testing requirements. The inspectors identified that both documents specified a visual inspection for leaks at the flange, however, the work order 23-2777278 did not include the visual inspection; therefore, the instruction was not adequate. The seal filters are in a floor vault that is covered by a removable concrete plug and during the replacement, the licensee installed the concrete plug over the filter assembly thus preventing a visual inspection of the filter housing for leaks.

The inspectors determined that the licensee failed to enter the previous O-ring failures into the corrective action program as required by procedure STA-421, "Control of Issue Reports."

Corrective Actions: The licensee immediate actions included isolation of the filter and replacement of the failed O-ring. Subsequent actions included adding this event to the pre-job brief database and entering the event into the corrective action program.

Corrective Action References: CR-2023-5124, CR-2023-51531

Performance Assessment:

Performance Deficiency: The licensee failure to implement and maintain procedures for replacement and returning to service RCP seal water filters was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, work order 23-277278, and procedure SOP-103A collectively failed to prevent losses of RCS inventory and RCP seal flow.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors screened the finding using IMC 0609 exhibit 1, dated, November 30, 2020.

Because the finding challenged the RCP seals, which is a loss of coolant accident initiator, and the finding impacted a system used to mitigate a loss of coolant accident, the inspectors determined a detailed risk evaluation was required. A regional senior reactor analyst performed the detailed risk evaluation and assumed that a maintenance error led to a total loss of RCP seal injection and that the maintenance error was recoverable 50 percent of the time. Using the Comanche Peak SPAR model, version 8.81, ran on SAPHIRE, version 8.2.8, the analyst added and logically "ANDed" 2 basic events under fault tree LOSC-1, "Seal Injection is Unavailable," to model the occurrence of a maintenance error and the ability to recover from that maintenance error. The analyst conservatively assumed that the exposure time for the error was 1 day. Applying these assumptions yielded an estimate of the increase in core damage frequency of 1.4E-8/year, making the safety significance very low (Green).

Events where component cooling water was lost comprised the dominant core damage sequences in the high-pressure injection and auxiliary feedwater systems remained available for mitigation.

Cross-Cutting Aspect: P.5 - Operating Experience: The organization systematically and effectively collects, evaluates, and implements relevant internal and external operating experience in a timely manner. The inspectors determined that internal operating experience indicated that the O-ring has failed on several previous filter changes; however, this experience had not been entered into the corrective action program.

Enforcement:

Violation: Technical Specification 5.4.1 requires that written procedures shall be established, implemented, and maintained covering applicable procedures recommended in Regulatory Guide 1.33, revision 2, appendix A, February 1978. Regulatory Guide 1.33 requires, in part, that maintenance that can affect the performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances.

Contrary to this requirement, work order 23-2777278, and procedure SOP-103A collectively were not appropriate to the circumstances. Specifically, on July 18, 2023, when restoring the RCP seal injection filter to a normal lineup, the work order and the procedure being used did not have appropriate written instructions, resulting in losses of RCS inventory and RCP seal flow.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 10, 2023, the inspectors presented the public radiation safety inspection results to Steven Sewell, Site Vice President, and other members of the licensee staff.
  • On October 4, 2023, the inspectors presented the Comanche Peak Unit 2 Inservice Inspection results to J. Lloyd, Senior Director, Engineering & Regulatory Affairs, and other members of the licensee staff.
  • On October 5, 2023, the inspectors presented the biennial emergency preparedness exercise inspection results to Al Marzloff, Plant Manager, and other members of the licensee staff.
  • On October 12, 2023, the inspectors presented the integrated inspection results to Steven Sewell, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

SOP-201B

Safety Injection System

71111.04

Procedures

SOP-304B

Auxiliary Feedwater System

71111.04

Procedures

SOP-304B-AF-

V02

Train B MDAFW Pump Lineup

71111.04

Procedures

SOP-304B-AF-

V03

TDAFWP Lineup

71111.04

Procedures

SOP-609B-DG-

V02

Train B DG Air System Valve Lineup

71111.04

Procedures

SOP-815B

Safety Chilled Water System

71111.05

Miscellaneous

Drill 23-15-02 Scenario

07/20/2023

71111.05

Procedures

CPNPP/FPR

Comanche Peak Nuclear Power Plant Fire Protection Report

Unit 1 and Unit 2

71111.05

Procedures

FPI 101A

Unit 1 Safeguards Building Elevation 790

71111.05

Procedures

FPI-101A

Unit 1 Safeguards building elevation 773'-0" Train A & B -

RHR, SI & CS pump rooms

71111.05

Procedures

FPI-101B

Unit 2 Safeguards building elevation 773'-0" A & B RHR, SI

and Containment Spray Pump Rooms

71111.05

Procedures

FPI-102B

Unit 2 Safeguards Building Elevation 790

71111.05

Procedures

FPI-403

Auxiliary Building Elevation 810'-6"

71111.08P

Corrective Action

Documents

CR-YYYY-NNNN

TR-YYYY-NNNN

2004-001456, 2009-000794, 2020-008364, 2022-002987,

21-006774, 2022-003052, 2021-006832, 2022-000786,

21-006859, 2022-001391, 2020-006898, 2022-002769,

22-003783, 2022-004216, 2021-008097, 2021-007550,

22-000367, 2022-005376, 2021-006299, 2022-002559,

22-004896, 2022-004630, 2022-005029, 2021-007806,

22-002065, 2022-000787, 2021-006607, 2021-008291,

22-002069, 2021-008067, 2022-003295, 2022-000786,

22-006938, 2022-007500, 2022-006559, 2022-008555,

22-008373, 2022-006936, 2023-000810, 2023-001501,

23-001699, CR-2023-002755,

TR-2022-006827, TR-2022-008643, TR-2022-000165,

TR-2022-001241, TR-2023-000211,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

IR-YYYY-NNNN

23-002755, 2020-006898

71111.08P

Corrective Action

Documents

Resulting from

Inspection

CR-YYYY-NNNN

IR-YYYY-NNNN

TR-YYYY-NNNN

23-005185,

23-003711, 2023-003715, 2023-003716, 2023-003717,

23-003718, 2023-003719, 2023-003720, 2023-003722,

23-000211

71111.08P

Engineering

Evaluations

EV-CR-2009-

000794-00-2

Engineering discovered a coffee colored stain in the reactor

cavity tell-tale trough

04/29/2009

71111.08P

Engineering

Evaluations

EV-TR-2023-

000211-1

Response to NRC Question on U2 MSIP Tool Event &

Analyses

01/13/2023

71111.08P

Miscellaneous

Associated work

order: 21-373898,

Procedure: TX-

ISI-8, Report No:

2RF19-VT-234

VT-3-Visual Examination of Pipe Hanger, Support of

Restraint

71111.08P

Miscellaneous

LTR-SDA-21-084

Comanche Peak Unit 2 Reactor Vessel Hot Leg and Cold

Leg Dissimilar Metal Welds PWSCC Operability Based on

MSIP Application and Inspections per Code Case N-770-5

10/31/2021

71111.08P

Miscellaneous

TCX-PP000-CN-

PX-000002

Comanche Peak Unit 2 Operability Assessment of the

Reactor Coolant Piping and Support System Due to the

MSIP Tool Failures

71111.08P

Procedures

TX-ISI-IWE

Metal containment visual Examination

71111.08P

Work Orders

21-582757

PD CHRG PMP 2-01 SUCT VNT CHK VLV

Welding documents 220208, 220209,220210,220211

05/03/2023

71111.12

Corrective Action

Documents

CR-YYYY-NNNN

23-4574, 2021-1820

71111.13

Corrective Action

Documents

CR-YYYY-NNNN

23-04763

71111.15

Corrective Action

Documents

CR-YYYY-NNNN

23-4378, 2023-5791,2023-5576

71111.15

Corrective Action

Documents

IR-YYYY-NNNN

23-5522

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Corrective Action

Documents

TR-YYYY-NNNN

23-5981

71111.15

Drawings

M2-0302

Flow Diagram-Ventilation Safeguards and Electrical Area

71111.18

Engineering

Changes

FDA-2023-

000043

Provide connection to heater drain pump 1-02 to allow for

flow if pump trips

71111.20

Miscellaneous

Work schedule report for 2RF20 for shift operations and

maintenance team 1.

April and

May 2023

71111.20

Miscellaneous

Work force reports of hours worked for Westinghouse

April 17 thru

May 27,

23

71111.24

Drawings

m1-0255

Chemical and Volume Control System Charging and Positive

Displacement Pump Trains

CP-37

71111.24

Procedures

OPT-203B

Residual Heat Removal System Testing

71111.24

Procedures

OPT-204B

Safety Injection System Testing

71111.24

Work Orders

23-277278

71111.24

Work Orders

WO 5999400

Unit 1 safety chiller 1-05 compressor replacement

71114.01

Corrective Action

Documents

CR-YYYY-NNNN

21-001627, 2021-003405, 2021-003396, 2021-003398,

21-005340, 2021-008501, 2021-008503, 2022-004836,

22-005181, 2022-006005, 2022-006007, 2022-006006,

22-007168, 2023-001209, 2023-001437, 2023-001394,

21-005512, 2021-008514, 2021-003239, 2021-003715,

21-005014, 2023-001620, 2022-007495, 2022-007693,

23-001395, 2022-008803,

71114.01

Corrective Action

Documents

CR-YYYY-NNNN

22-008975, 2022-008715, 2023-004166, 2023-003562,

23-002780, 2023-002761, 2023-004348, 2022-008144,

23-003960, 2023-004840, 2023-007340

71114.01

Corrective Action

Documents

TR-YYYY-NNNN

23-002377, 2023-002380, 2023-002381, 2023-002383

71114.01

Corrective Action

Documents

Resulting from

Inspection

IR-YYYY-NNNN

23-006923

71114.01

Procedures

Exercise Report 11-06-2019

07/12/2022

71114.01

Procedures

Exercise Report Red Team 12/15/2021

07/12/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.01

Procedures

Exercise Report Blue Team 08/04/2021

2/22/2021

71114.01

Procedures

Exercise Report Green Team 05/12/2021

07/08/2021

71114.01

Procedures

Exercise Report Gold Team 03/03/2021

07/12/2022

71114.01

Procedures

Exercise Report Gold Team 02/16/2022

07/12/2022

71114.01

Procedures

Exercise Report Green Team 06/22/2022

10/12/2022

71114.01

Procedures

Exercise Report Green Team 07/27/2022

10/12/2022

71114.01

Procedures

Exercise Report Red Team 11/30/2022

01/11/2023

71114.01

Procedures

Exercise Report Blue Team 02/22/2023

05/04/2023

71114.01

Procedures

Comanche Peak Nuclear Power Plant Emergency Plan

71114.01

Procedures

EPP-109

Duties and Responsibilities of the Emergency

Coordinator/Recovery Manager

71114.01

Procedures

EPP-201

Assessment of Emergency Action Levels Emergency

Classification and Plan Activation

71114.01

Procedures

EPP-202

Emergency Communications Systems and Equipment

71114.01

Procedures

EPP-203

Notifications

EPP-203

71114.01

Procedures

EPP-204

Activation and Operation of the Technical Support Center

(TSC)

71114.01

Procedures

EPP-205

Activation and Operation of the Operations Support Center

(OSC)

71114.01

Procedures

EPP-206

Activation and Operation of the Emergency Operations

Facility (EOF)

71114.01

Procedures

EPP-303

Operation of Computer Based Emergency Dose Assessment

System

71114.01

Procedures

EPP-304

Protective Action Recommendations

71114.01

Procedures

EPP-306

Use of Thyroid Blocking Agents

71114.01

Procedures

EPP-309

Onsite/In-Plant Radiological Surveys and Offsite

Radiological Monitoring

71114.01

Procedures

EPP-314

Evacuation and Accountability

71114.04

Miscellaneous

50.54(q) Screening and Evaluation Documents for

Emergency Plan Revision

71114.04

Miscellaneous

50.54(q) Screening and Evaluation Documents for

Emergency Plan Revision 48

71114.04

Procedures

Comanche Peak Nuclear Power Plant Emergency Plan

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71114.04

Procedures

Comanche Peak Nuclear Power Plant Emergency Plan

71114.04

Procedures

EPP-123

CFR 50.54(q) Screening and Evaluation of Changes to

Emergency Plan Documentation

71114.06

Miscellaneous

Notification Message Form

0946

09/11/2023

71114.06

Miscellaneous

Notification Message Form

0750

09/11/2023

71114.06

Miscellaneous

LO46.E23.PRA

Cycle 23-5 Practice Scenario

71124.06

Corrective Action

Documents

CR-YYYY-NNNN

21-003323, 2022-007381

71124.06

Corrective Action

Documents

TR-YYYY-NNNN

20-007580, 2021-000682, 2021-000846, 2022-000027,

22-000622, 2022-001065, 2022-001442, 2023-000039,

23-001105, 2023-004906

71124.06

Corrective Action

Documents

Resulting from

Inspection

IR-YYYY-NNNN

23-005672, 2023-0005681, 2023-005683

71124.06

Miscellaneous

20

Annual Radioactive Effluent Release Report

03/29/2021

71124.06

Miscellaneous

21

Annual Radioactive Effluent Release Report

04/09/2022

71124.06

Miscellaneous

22

Annual Radioactive Effluent Release Report

03/30/2023

71124.06

Miscellaneous

23

Land Use Census

06/08/2023

71124.06

Miscellaneous

4th Quarter 2021

Results of Radiochemistry Cross Check Program

04/19/2022

71124.06

Miscellaneous

ODCM

Offsite Dose Calculation Manual

71124.06

Procedures

CHM-170

Liquid and Gaseous Effluent Program

71124.06

Procedures

CLI-741

Setpoint Modification and DRMS Pre-Release Surveillance

71124.06

Procedures

CLI-745

Radioactive Effluent Post-Release Permit Processing and

Surveillance Tracking

71124.06

Procedures

CLI-774

Wide Range Gas Monitor Filter Replacement

71124.06

Procedures

CLI-777

Use of Gaseous Waste Sampling Equipment

71124.06

Procedures

COP-816

Plant Ventilation

71124.06

Procedures

PPT-SX-7509A

ESF Filter Unit Test - CPX-VAFUPK-15

71124.06

Procedures

STA-603

Control of Station Radioactive Effluents

71124.06

Radiation

Surveys

Gaseous Effluent

Permits

G2021-007, G2021-008, G2021-045, G2021-073,

G2021-082, G2021-083, G2021-122, G2021-123,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

G2021-139, G2021-190, G2021-191, G2021-206,

G2021-212, G2022-024, G2022-047, G2022-048,

G2022-074, G2022-076, G2022-087, G2022-108,

G2022-109, G2022-139, G2022-183, G2022-184,

G2022-219, G2023-031, G2023-032, G2023-034,

G2023-061, G2023-073, G2023-086, G2023-091,

G2023-092

71124.06

Radiation

Surveys

Liquid Effluent

Permits

L2021-005, L2022-010, L2023-005, L2021-019, L2022-015,

L2023-010, L2021-031, L2022-027, L2023-022, L2021-047,

L2022-045, L2023-033, L2021-057, L2022-055, L2021-062,

L2022-062

71124.06

Radiation

Surveys

M-20230702-1

CCW heat exchanger room, auxiliary building 790' elevation

07/02/2023

71124.06

Self-Assessments EVAL-2021-006

Chemistry/ Environmental/ Effluent/Radioactive Waste Audit

04/25/2022

71124.07

Corrective Action

Documents

CR-YYYY-NNNN

21-003323, 2020-001474, 2022-008211, 2021-007878

71124.07

Corrective Action

Documents

TR-YYYY-NNNN

20-002247, 2020-004597, 2021-000581, 2022-000484,

21-003892, 2022-003827, 2020-001878, 2020-001904,

22-001873, 2022-003871

71124.07

Miscellaneous

21

Annual Radiological Environmental Operating Report

04/12/2022

71124.07

Miscellaneous

22

Annual Radiological Environmental Operating Report

03/28/2023

71124.07

Miscellaneous

23

GPI Plan and Status

07/01/2023

71124.07

Procedures

INC-4923X

Channel Calibration Backup Tower Air Ambient Temperature

Channel 4134

71124.07

Procedures

INC-7682X

Channel Calibration Primary 60M Tower Wind Speed

Channel 4117

71124.07

Procedures

INC-7685X

Channel Calibration Primary 60m Tower Wind Direction

Channel 4115

71124.07

Procedures

RPI-710

Radiological Environmental Monitoring, Sampling, and

Analysis Program

71124.07

Procedures

RPI-713

Collection, Preparation, and Shipment of Radiological

Environmental Samples

71124.07

Procedures

RPI-714

Land Use Census

71124.07

Procedures

STA-654

Groundwater Protection Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.07

Radiation

Surveys

549194

Soil Sediment Gamma Isotopic

08/06/2021

71124.07

Radiation

Surveys

564474

Food Product Gamma Isotopic

01/05/2022

71124.07

Radiation

Surveys

566896

Fish Tritium Sample

01/13/2022

71124.07

Radiation

Surveys

605457

Broad Leaf Gamma Isotopic and Iodine

01/27/2023

71124.07

Radiation

Surveys

609143

Quarterly Gamma Isotopic of Air Samples

2/22/2023

71124.07

Self-Assessments 2019

EPRI Groundwater Protection Program

06/23/2020

71124.07

Self-Assessments 2022

On-Site Assessment Report for Radiation Detection

Company

05/21/2023

71124.07

Self-Assessments Eval-2021-006

Chemistry/ Environmental/ Effluent/Radioactive Waste Audit

03/03/2022

71124.07

Work Orders

2-465494

Meteorological Data System Backup Tower 10 Meter

Elevation Wind Speed Loop 4128

03/27/2023

71124.07

Work Orders

2-465656

Meteorological Data System Backup Tower 10 Meter Level

Wind Direction Loop 4126

03/27/2023

71151

Miscellaneous

Alert and Notification Test Data 3Q2022 - 2Q2023

71151

Miscellaneous

Key Emergency Response Organization Personnel Drill

Participation Data 3Q2022 - 2Q2023

71151

Miscellaneous

Drill and Exercise Performance Data 3Q2022 - 2Q2023

71151

Procedures

SG-20

Staff Guideline 20 NRC Performance Indicators

71152A

Corrective Action

Documents

CR-YYYY-NNNN

21-3228

71152S

Corrective Action

Documents

CR-YYYY-NNNN

23-2947

71152S

Work Orders

2-07855