IR 05000440/2025002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000440/2025002
ML25218A020
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 08/07/2025
From: Sanchez-Santiago E
NRC/RGN-III/DORS/RPB2
To: Tony Brown
Vistra Operations Company
References
IR 2025002
Download: ML25218A020 (1)


Text

SUBJECT:

PERRY NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000440/2025002

Dear Terry Brown:

On June 30, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Perry Nuclear Power Plant. On July 16, 2025, the NRC inspectors discussed the results of this inspection with D. Benyak, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Elba M. Sanchez Santiago, Chief Reactor Projects Branch 2 Division of Operating Reactor Safety Docket No. 05000440 License No. NPF-58

Enclosure:

As stated

Inspection Report

Docket Number:

05000440

License Number:

NPF-58

Report Number:

05000440/2025002

Enterprise Identifier:

I-2025-002-0050

Licensee:

Vistra Operations Company, LLC

Facility:

Perry Nuclear Power Plant

Location:

Perry, OH

Inspection Dates:

April 01, 2025 to June 30, 2025

Inspectors:

J. Beavers, Senior Resident Inspector

N. Day, Senior Resident Inspector

T. Ospino, Senior Resident Inspector

Approved By:

Elba M. Sanchez Santiago, Chief

Reactor Projects Branch 2

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Perry Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000440/2025 001-00 LER 2025001-00 for Perry Nuclear Power Plant, Automatic Actuation of Division 3 Diesel Generator Resulting from Startup Transformer Testing 71153 Closed

PLANT STATUS

Unit 1 began the inspection period shut down in a refueling outage. On April 14, 2025, the outage was completed and power restored to rated thermal power. On June 28, 2025, the unit was reduced to 65 percent to adjust rod line. On June 30, 2025, the unit was restored to rated thermal power. The plant operated at or near rated thermal power for the remainder of the inspection period with occasional power derates related to heat and humidity.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal hot temperatures for the main steam tunnel ventilation, turbine building chilled water system, and auxiliary building ventilation systems on June 20, 2025.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Control rod drive hydraulic train 'B' before startup operations on April 19, 2025
(2) Reactor core isolation cooling system after maintenance on April 19, 2025
(3) Fuel pool cooling and cleanup system after fuel offload on June 26, 2025

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) High pressure core spray during the week of April 7, 2025

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Unit 1 turbine building on April 2, 2025
(2) Auxiliary building steam tunnel on April 9, 2025

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on May 14, 2025

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during reactor plant startup on April 20 and 21, 2025

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated operator requalification simulator performance on May 5, 2025

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (3 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Outboard main steam isolation valve 'D' failure on April 6, 2025
(2) Reactor recirculation pump 'A' flow control valve failure on April 6, 2025
(3) Reactor recirculation pump 'B' flow control valve failure on April 7, 2025

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Risk associated with the turbine overspeed test malfunction on May 3, 2025
(2) Risk associated with the main transformer 'C' cooling groups 1 and 4 issues on May 8, 2025
(3) Division 1 work week planned activities during the week ending May 16, 2025
(4) Division 2 work week planned activities to include division 1 heating and ventilation outage during the week ending May 23, 2025
(5) Emergency service water system 'A' medium risk activities and associated 72-hour technical specifical limiting conditions of operation during the week ending June 20, 2025

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Operability determination verification of mode restraint list and readiness for entry into Mode 4 on April 10, 2025
(2) Operability determination of intermediate range instruments 'C' and 'E' due to failed linearity checks during reactor plant startup on April 20, 2025
(3) Operability determination of offgas pretreatment radiation monitor on April 22, 2025
(4) Operability determination of division 2 emergency diesel generator during the week ending on May 23, 2025
(5) Operability determination of the offgas pretreat system during the 1R20 outage on June 9, 2025

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Permanent modification of the reactor protection system power selector switch

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage activities from April 1, 2025, to April 21, 2025

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (13 Samples)

(1) Replacement of hydramotor 1D17F0071B as a result of a failed stroke time close on March 12. 2025
(2) Replacement of the high voltage fuse and the challenges returning transformer LH2A to service on March 27, 2025
(3) Low pressure core spray injection valve work on March 29, 2025
(4) Low pressure core spray and 'A' residual heat removal (RHR) waterleg pump test on March 29, 2025
(5) Drywell airlock test during the 1R20 outage
(6) RHR 'A' to feedwater injection valve leak rate test on April 9,2025
(7) Reactor core isolation cooling steam supply inboard and outboard valves following maintenance on April 10, 2025
(8) Main steam isolation outboard 'A' air drop test after test failure on April 13, 2025
(9) Main steam isolation inboard valve 'A' VT2 during reactor pressure vessel test on April 16, 2025
(10) Reactor recirculating pump suction valve VT2 during reactor pressure vessel test on April 16, 2025
(11) Main steam isolation inboard drain valve VT2 during reactor pressure vessel test on April 16, 2025
(12) Reactor recirculating pump 'B' flow control valve VT2 during reactor pressure vessel test on April 16, 2025
(13) Outboard main steam isolation valve 'A' local leak rate testing (LLRT) and other tests after issues with it on June 11, 2025

Surveillance Testing (IP Section 03.01) (7 Samples)

(1) Division 3 diesel generator start and load on March 28, 2025
(2) Division 1 retest of the loss of offsite power/ loss of coolant accident (LOOP/LOCA)testing on April 1, 2025
(3) Fire suppression valve cycle on April 3, 2025
(4) Leak rate testing for 'A' RHR to feedwater injection valve on April 8, 2025
(5) Unit 2 transformer insulation resistance checks on April 10, 2025
(6) Intermediate range monitoring voltage calibration on April 20, 2025
(7) Unit 2 main transformer double testing on April 23, 2025

Inservice Testing (IST) (IP Section 03.01) (3 Samples)

(1) Shutdown cooling suction isolation valve operability test on March 28, 2025
(2) Low pressure core spray isolation valve leak rate test on March 30, 2025
(3) Reactor coolant system leakage pressure test on April 16, 2025

71114.06 - Drill Evaluation

Required Emergency Preparedness Drill (1 Sample)

(1) Full scale emergency response organization drill on June 11,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) Unit 1 (April 1, 2024 through March 31, 2025)

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) Unit 1 (April 1, 2024 through March 31, 2025)

MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)

(1) Unit 1 (April 1, 2024 through March 31, 2025)

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Onsite storage container radioactive leak

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in equipment reliability that might be indicative of a more significant safety issue.

71153 - Follow-Up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01)

(1) On June 11, 2025, an individual found smoke in warehouse 6, which is located inside the licensee's owner-controlled area but outside the protected area. The control room was immediately notified and Off Normal Instruction ONI-P54, Fire, was entered and 911 was called to initiate offsite firefighting response. The control room directed the starting of the motor fire pump and immediate notification of site personnel including the resident inspectors. The site fire brigade remained on standby as per agreements with local firefighting agencies as this building was outside of the protected area fence and required no special access to mitigate the fire. Licensee personnel remained in contact with the local firefighting agency efforts and were available to deenergize the building as required by the incident commander, which was not requested. Inside the warehouse, a limited area fire was identified and mitigation commenced. Damaged and burned materials were removed to the parking lot and thoroughly wetted. The fire was extinguished within an hour of offsite response.

No personnel were injured during this event, and no ambulance response was required. The same day the off normal instruction was exited and the fire system restored to standby. The affected warehouse contained materials to support plant operation and maintenance activities. No hazardous materials were identified as impacted, and the building contained no radioactive material.

The inspectors determined the event did not meet any emergency action level entry criteria due to the fires location being outside of the protected area, and the fact that the fire did not impact the safety and security of the power plant or its operations.

Additionally, no nuclear regulatory reporting actions were required. The inspectors did not identify any issues associated with the licensees response.

Event Report (IP Section 03.02) (1 Sample)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 2025001, Automatic Actuation of Division 3 Diesel Generator Resulting from Startup Transformer Testing. (ADAMS Accession No. ML25141A212)

The inspection conclusions associated with this LER are documented in this report under Inspection Results Section 71153. This LER is Closed.

INSPECTION RESULTS

Observation: Onsite Storage Container Radioactive Leak 71152A The inspectors performed an indepth review of the October 14, 2024, onsite storage container radioactive leak event cause and corrective action progress as of June 30, 2025.

This sample was selected as a timely review of the event with potential public impact and interest previously dispositioned in the Perry Integrated Inspection Report 05000440/2024004 (ML25042A066).

The licensee's analysis determined site personnel made assumptions that the shield container was suitable for outdoor storage without verification in contrast to the requirements of site procedures. This conclusion was supported by: the site not procuring the necessary equipment or plan for how to handle the liner after it was depleted to ensure safe, timely handling, storage, and disposal; inadequate information regarding the suitability of the shield container for outdoor storage in the work order, procedures, or other instructions; and failure to stop in the face of uncertainty when trying the set the shield plug into place. These issues were dispositioned in the aforementioned inspection report.

The licensees corrective actions included the completed immediate actions of securing the leak source and radioactive mitigation of the affected area. The plan to track and clean up the onsite storage container yard has been approved and largely completed with the majority of the contaminated soil shipped offsite and the remainder of the soil and sealed source liner prepared for imminent transport. The documentation and process changes have been largely completed, including the update of 10CFR50.75(g) for use in eventual plant decommissioning activities. The remaining items include the identification and fabrication of a new location for onsite storage of radiological waste awaiting transport.

The inspectors evaluated the licensees onsite storage container radioactive leak cause and corrective action effort and identified no more than minor findings or violations.

Observation: Trend in Equipment Reliability 71152S The inspectors performed a semiannual review of a potential adverse trend in the licensees equipment reliability issues that might be indicative of a more significant safety issue. The following corrective action documents were associated with this review:

1. CR 202501258, Unplanned Reactor Shutdown

2. CR 202501429, Equipment Reliability Challenge Board: Perry is projected to have

incurred INPO Noteworthy Consequential Events in each of the last four months

3. CR 202503352, Perry Escalation - Equipment Reliability

4. CR 202403861, Equipment Reliability Challenge Board: Corrective Action Program

During the inspection period, the inspectors evaluated corrective action program entries related to equipment reliability. They were chosen for inspection sample due to their relation to an increased number of forced outages and down powers. The primary events evaluated were turbine trip on loss of vacuum, forced outage due to circulating water system leak, significant down power to stator cooling water system outage, and recirculating water system flow issues on non-safety systems. These events resulted in significant power transients and initiating event cornerstone challenges, driving abnormal plant configurations and increased risk. The licensee also performed a review of this trend and identified a concern of not leveraging the corrective action program for issue identification may lead to the lack of cross functional team knowledge, understanding, challenge, and correction of equipment reliability issues. The licensee further stated that Relative to the number consequential events that have occurred at Perry, promotion and reinforcement of a lower corrective action program issue initiation threshold may be required. The licensee documented these conclusions in CR202503861.

The inspectors performed their review in accordance with the inspection procedure and trended the behavior to consider potential safety culture weaknesses. Based on their review they noted a trend associated with CO.4 Expectations: Leaders frequently communicate and reinforce the expectation that nuclear safety is the organizations overriding priority.

Specifically, executives and senior managers reinforce the importance of nuclear safety by clearly communicating its relationship to strategic issues including budget, workforce planning, equipment reliability, and business plans, as defined in NUREG 2165, Safety Culture Common Language. The inspectors provided this feedback to the licensee to ensure they were taking the necessary actions to address the identified trend. This review focused on the corrective action program aspects of the issues. No performance deficiencies were identified as a result of this review.

Minor Performance Deficiency 71153 LER 2025001-00 for Perry Nuclear Power Plant, Automatic Actuation of Division 3 Diesel Generator Resulting from Startup Transformer Testing Minor Performance Deficiency: On March 29, 2025, Unit 1 was in Mode 5 during a refueling outage with a single offsite power source available through the Unit 1 startup transformer.

During testing of the Unit 2 startup transformer, power was disrupted to the available but inoperable division 3 shutdown safety electrical bus. This caused an actuation of the division 3 emergency diesel generator (3DG) system and entries into off normal operating procedures for the following systems: electrical power, non-safety service water, and the plant air system.

Both the licensee and the NRC resident inspectors became aware of the issue immediately.

This event was reported at 1616 on March 29, 2025, as a 10 CFR 50.72(b)(3)(iv)(A) event resulting in a valid actuation of the emergency diesel generator system.

During the investigation process, the licensee identified relay testing associated with a startup transformer tripped a switch interlock on the breaker that had been energizing the 13.8 kV bus feeding the division 3 shutdown safety electrical bus. They also identified they performed insufficient impact and work order reviews of transformer relay testing. Additionally, engineering provided erroneous technical information regarding breaker control schematics and engineering did not perform a review of a work order revision with the tests steps.

Corrective actions included training on electrical interlocks and relay schemes, installing a caution placard on a breaker door, issuing of a night order to operators regarding lessons learned, and incorporating this operating experience into a work order for similar work in the next refueling outage.

The failure to properly review the transformer relay testing impact and work order sufficiently during the planning phase of the work management process was contrary to the licensee's Work Management Process procedure, NOP-WM-0001. The inspectors determined this failure was a performance deficiency. No violation of NRC requirements was identified during this review.

Screening: The inspectors determined the performance deficiency was minor. Though the performance deficiency was associated with the mitigating systems cornerstone attribute of human performance, it did not adversely affect the associated cornerstone objective.

Specifically, the 3DG and its supported high pressure core spray pump system were already inoperable to support maintenance and not needed to meet technical specification (TS)requirements. Additionally, both division 1 and division 2 emergency diesel generators and residual heat removal 'B' and 'C' emergency core cooling systems (ECCS) were operable to satisfy ECCS TS 3.5.2 requirements for Modes

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 16, 2025, the inspectors presented the integrated inspection results to D. Benyak, Plant Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Procedures

IOI0015

Seasonal Variations

VLI-C11 (CRDH)

Control Rod Drive Hydraulic System (CRDH)

VLI-E22A

High Pressure Core Spray

VLI-E51

Reactor Core Isolation Cooling System

71111.04

Procedures

VLI-G41 (FPCC)

Fuel Pool Cooling and Cleanup System

06/26/2025

FPI1ST

Steam Tunnel

04/09/2025

Fire Plans

FPI1TB

Turbine Building Unit 1

71111.05

Procedures

FD 1450051425

MB100 2nd Floor Classroom

05/14/2025

71111.11Q

Procedures

IOI0001

Cold Startup

CR202502066

Recirc Pump 'A' Discharge Valve Handwheel Broken

03/24/2025

CR202502528

MSL 'A' OTBD MSIV Leakage Exceeds Allowable Limit

04/06/2025

CR202502551

FCV 'B' Will Not Stroke Open

04/07/2025

CR202502766

Mounting Screw Snapped During Reinstallation on FCV

'A' RVDT

04/13/2025

Corrective Action

Documents

CR202503227

Abnormal Movement of Flow Control Valve 'A'

04/29/2025

Engineering

Changes

251067-001

Reactor Recirculation System Discharge Block Valve

(1B33F0067A) Actuator Motor Replacement

71111.12

Procedures

SVI-B33T1158B

Reactor Recirculation Flow Control Valve 1B33F060B

Functional Test

CR202503401

Turbine Mechanical Overspeed Indicated Test Malfunction 05/03/2025

Corrective Action

Documents

CR202503449

Main Transformer 'C' Cooler 1 and 4 Trouble

05/06/2025

20080220-00006

TDUN 251094-001001

2080151-00399

Turbine Cntrl Emergency Trip Sys

2080220-00006

Power Transformers

R

Drawings

2090220-00020

Temporary Drawing Update Notice 251094-001003

Engineering

Changes

ECP 250194

Temporary Power Set up for the F1A12 Transformer

05/08/2025

ARI-

S11S001C0001A5

Cooler No. 1 Trouble

71111.13

Procedures

ARI-

S11S001C0001A7

Cooler No. 4 Trouble

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

PAP1925

Shutdown Defense in Depth Assessment and

Management

200517736

Cable Diagnostic Withstand Tests

06/16/2025

200872933

Deenergized/Energized Motor Analysis-LR

06/16/2025

Work Orders

200933745

Inspect/Tighten ESW 'A' Pump Packing

06/16/2025

CR202305197

Div. 2 DG Exhaust Louver is Dusty and Needs Cleaned

06/29/2023

CR202406674

Div. 2 Diesel exhaust Damper Screen Dirty

08/19/2024

CR202503056

Offgas Pretreat Sample Selector Panel Doesn't Have

Power

06/09/2025

CR202503056

Offgas Pretreat Sample Selector Panel Doesn't Have

Power

04/22/2025

Corrective Action

Documents

CR202503793

Div 2 Diesel Generator Exhaust Screen Need Cleaned

05/19/2025

Miscellaneous

Perry Open Mode Hold and PCR Forms Mode Restraint

List

04/08/2025

71111.15

Procedures

ICI-C-C513

Intermediate Range Monitoring (IRM) Voltage Preamplifier

Calibration

71111.18

Work Orders

200922062

RPS Power Transfer Switch Replacement

04/17/2025

CR202409654

Low Pressure Core Spray Waterleg Pump Oil Seals

Leaking

2/18/2024

CR202501189

Drywell Radiation Monitor Inboard Suction Isolation Failed

Stroke Time Close Per SVI-D17T2001

2/23/2025

CR202501917

Ability to Complete Cable Testing on LH2A is Challenged

Due to Inprocessing and Accessing Issues

03/19/2025

CR202502009

Outboard Main Steam Isolation Valve 'A' Stroke Time Was

Fast for SVI-B21T2001

03/22/2025

CR202502094

Pre Fab Does Not Match AsFound Condition for LPCS

Waterleg Pump to RHR A Discharge Check Valve

03/25/2025

CR202502192

Phasing Checks Failed on LH2A

03/27/2025

CR202502212

RHR Shutdown Cooling Suction Line Min Path Leakage

Limit Exceeded

03/27/2025

CR202502265

Loss of L20 Bus During Breaker Trip Check Testing

03/29/2025

CR202502338

Plant Computer Failover During Div 1 Diesel Test

03/31/2025

71111.24

Corrective Action

Documents

CR202502339

1R20 SVI-R43T7000A Division 1 Integrated Test Data

04/01/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR202502655

Main Steam Line 'A' Outboard MSIV AsFound Inspection

Results

04/10/2025

Corrective Action

Documents

Resulting from

Inspection

CR202501985

NRC Identified: Methods for Crediting Systems for

Shutdown Defense in Depth Not Clear

03/21/2025

Engineering

Changes

ECP 210194-002

PDUN 210194-001002

Engineering

Evaluations

601486502

MSIV Spring Cap, Guide Lug Interference

04/11/2025

FTI-F0038

Hydrostatic Pump Testing Instruction

GEI0001

Performing Insulation Resistance Checks

ICI-B120001

ITT NH90 Series Milliampere Proportional/OnOff

Hydramotor Actuator Calibration

ICI-C513

IRM Voltage Preamplifier Calibration

ISI-B21T13001

Reactor Coolant System Leakage Pressure Test

PMI0061

Overhaul of NH95 Hydramotors

PTI-P54P3200

Fire Suppression Valve Cycle and Position Switch

Functional Test

03/25/2025

SOI-G33

Reactor Water Cleanup System

SVI-B21T2001

MSIV Full Stroke Operability Test

SVI-B21T9000

Type C Local Rate Test of 1B21 MSL Penetration (P122,

P124, P415 and P416)

SVI-B21T9000

Type 'C' Local leak Rate Test of 1B21 MSL Penetrations

(P122, P124, P415, and P416)

SVI-C71T0038E

MSIV 1B21F028A Closure Channel Calibration for

1C71N702A and 1C71N703A

SVI-E12T2200

RHR Shutdown Cooling Suction Isolation Valve

Operability Test

SVI-E12T2210

Leak Rate Test for RHR to FDW Injection Valves

1E12F050A and 1E12F053A

Procedures

SVI-E21T2004

LPCS and RHR 'A' Waterleg Pump and Associated Valve

Cold Shutdown Operability Test

03/29/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

SVI-E21T2200

Low Pressure Core Spray Isolation Valve Leak Rate Test

SVI-E22T1319

Diesel Generator Start and Load Division 3

SVI-E51T9422

Type C Local Leak Rate Test of 1E51 Penetration P422

SVI-E51T9422

Type C Local Rate Test of 1E51 Penetration P422

SVI-P53T9024

Drywell Airlock in Between Seals Test

SVI-R43T7000A

Division 1 ECCS Integrated Test

04/01/2025

SVI-T23T1022

Drywell Airlock Interlock Verification

200242803

MSIV-CPLO Rebuild OB MSIV 'A'

04/13/2025

200242803

MSIV-CPLO Rebuild OB MSIV 'A'

04/25/2025

200679637

1E12F0084A Dresser Valve Replacement

04/05/2025

200859641

Perry S2 Bus Backup Bus Diff-U2S/U - ECP 210194-002

04/10/2025

200903818

Replace High Voltage XFMR Fuse

03/27/2025

200906321

Static MOV Test (ASME OM Code) & PM Ins

03/29/2025

200906342

Gen. Insp. / Double Complete Test 1PUY-T XFMR A0,

B0, C0

04/23/2025

200909389

SVI-B21T2201 MSIV Full Strike OPER PiCal

03/22/2025

200910660

SVI-C71T0038E OTBD MSIV Closure CH 'A'

04/16/2025

200911995

SVI-B21T900 1B21 MSL Penetration LLRT

03/24/2025

200946729

Blast Shield Door to be Opened Closed in the Normal

Course. Defeat/Restore DW Interlocks on DW Airlock

Hatch. Of IOI17, Drywell Entry

04/18/2025

200967423

Replace Hydramotor 1D17F0071B

04/12/2025

Work Orders

SVI-D17T9201

Type C Local Leak Rate of 1D17 Penetration P201

Miscellaneous

Perry ERO Integrated Drill Scenario Guide

06/11/2025

EMA 0083 7/22

State of Ohio Supplemental Action Default Actions - PNPP

06/11/2025

NOP-LP550309

Perry Emergency Notification Cover Sheet

71114.06

Procedures

NOP-LP550312

Industry Event Notification

MS05 Performance

Indicator Data

Safety System Functional Failures

03/31/2025

MS06 Performance

Indicator Data

Emergency AC Power Systems

03/31/2025

71151

Miscellaneous

MS07 Performance

Indicator Data

High Pressure Injection Systems

03/31/2025

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71152A

Corrective Action

Documents

CR202408053

Container in the Outside Radiological Controlled Area

Leaked Radioactive Water

10/14/2024

71153

Corrective Action

Documents

CR202504315

Fire in Warehouse #6

06/11/2025