SUBJECT:

PERRY NUCLEAR POWER PLANT - SECURITY BASELINE INSPECTION REPORT 05000440/2025403

Dear Terry Brown:

On August 28, 2025, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Perry Nuclear Power Plant and discussed the results of this inspection with Darin Benyak and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Michael E. Ziolkowski, Chief Security, Emergency Preparedness, and Incident Response Branch Division of Radiological Safety and Security Docket No. 05000440 License No. NPF-58

Enclosure:

As stated

Inspection Report

Docket Number:

05000440

License Number:

NPF-58

Report Number:

05000440/2025403

Enterprise Identifier:

I-2025-403-0031

Licensee:

Vistra Operations Company, LLC

Facility:

Perry Nuclear Power Plant

Location:

Perry, OH

Inspection Dates:

May 19, 2025, to August 28, 2025

Inspectors:

N. Egan, Sr Physical Security Inspector

Approved By:

Michael E. Ziolkowski, Chief

Security, Emergency Preparedness, and Incident Response Branch

Division of Radiological Safety and Security

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a security baseline inspection at Perry Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

SAFEGUARDS

71130.02 - Access Control

The inspector evaluated the access control program through completion of the following

inspection elements: Access Control

(1)

  • 02.01 c; 02.02 c-f; 02.04 a-e; 02.05 a; 02.06 a-d; 02.08 f, i; 02.09; 02.10 a

71130.07 - Security Training

The inspector evaluated the security training program through completion of the following

procedure elements: Security Training

(1)

  • Tier I: All Requirements
  • Tier II: 02.05 a-d, 02.09 a-b
  • Tier III: 02.11 a, 02.12 a-b, 02.13 a, c

71130.09 - Security Plan Changes

The inspector evaluated the security plan changes through completion of the following procedure elements:

Security Plan Changes (1 Partial)

(1)

(Partial)

The opportunity to apply this procedure was not available in accordance with IMC 0306. This sample was not available because the licensee did not conduct the activity covered by this IP. Specifically, the licensee has not initiated a physical security plan change in accordance with 10 CFR 50.54(p(2) since the last performance of this IP.

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspector verified licensee performance indicators submittals listed below:

PP01: Protected Area Security Equipment Performance Index Sample (IP Section 02.17)

=

(1) October 1, 2024 through April 30,

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 28, 2025, the inspectors presented the security baseline inspection results to Darin Benyak and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

FLY-SY-0001

Physical Security Event and Suspicious Activity Notifications

NOBP-LP-1003

Unescorted Access In-Processing

NOBP-LP-1303

Safeguards Information Central Repository Control

NOP-LP-1102

Protection of Safeguards Information

NOP-LP-1104

Security-Related Access Control Devices

NOP-LP-1202

Vehicle and Material Access Control

NOP-LP-1203

Security Badge Control

NOP-LP-1204

Primary Access Facility Controls

NOP-LP-1205

Visitor Control to Protected and Vital Areas

PYBP-FMSS-

1003

Perry Site Access Security Controls

PYBP-SPS-0008

Material Search at the Warehouse

Procedures

SPI-0023

Site Evacuation/Personnel Accountability and Access Control

Measures

ATA-2025-9291

Analysis of Security Access Control Program

07/23/2025

71130.02

Self-Assessments

MS-C-25-05-19

Security and Cyber Audit

06/26/2025

ATA-2025-7478

05/22/2025

ATA-2025-7480

05/22/2025

ATA-2025-7481

05/22/2025

Corrective Action

Documents

Resulting from

Inspection

ATA-2025-7483

05/22/2025

National Rifle Association Law Enforcement Course of Fire

Review & Approval Application for Reduced Light Rifle

01/08/2025

National Rifle Association Law Enforcement Course of Fire

Review & Approval Application for Rifle Daylight Qualification

01/08/2025

Current Firearm Instructor Certifications for All Site Firearm

Instructors

71130.07

Miscellaneous

Select Security Personnel Training & Qualification Records

from 2023 to 2025

FELP Task 22

Comply with Physical Fitness Performance Requirements

NOBP-LP-1304

Security On the Job Training Program

NOP-LP-1401

Security Training Program

Procedures

SC-2131-20

Tactical Qualification Course

ATL-2025-0216-

ATA-01

Security Training Self-Assessment

71130.07

Self-Assessments

MS-C-24-09-19

Fleet Nuclear Oversight Audit Report - Site Protection

10/31/2024

71130.09

Miscellaneous

Perry Nuclear Power Plant Physical Security Plan

17