IR 05000410/1986052

From kanterella
Jump to navigation Jump to search
Insp Rept 50-410/86-52 on 860826-28 & 0908-12.No Violations Noted.Weaknesses Identified:Qc Hold Points in Maint Procedures & Related QC Checklists Inconsistent.Util 860904 Presentation of Quality First Program Encl
ML17055C661
Person / Time
Site: Nine Mile Point 
Issue date: 11/05/1986
From: Gallo R, Linville J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17055C660 List:
References
50-410-86-52, NUDOCS 8612020292
Download: ML17055C661 (46)


Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report No.

Docket No.

License No.

Licensee:

Facility:

Locations:

Inspection Dates:

Meeting Dates:

50-410/86-52 50-410 CPPR-112 Category B

Niagara Mohawk Power Corporation 300 Erie Boulevard West Syracuse, New York 13202 Nine Mile Point

Scriba, New York King of Prussia, Pennsylvania August 29, 986 and September 4,

1986 August 26-28, 1986 and September 8-12, 1986 Team Leader:

C. Lsnville, C

ef RPS 2C, DRP da e

Inspectors:

Dr.

P.

K. Eapen, Chief, QA Section, DRS R.

Gramm, Senior Resident Inspector J. Stair, Resident Inspector Approved by:

R.

M. Gallo, Chief, Projects Branch

DRP

/I BC date Ins ection Summar

Ins ections on Au ust 26-29 and Se tember 8-12 1986 and Mana ement Meetin s

on Au ust

1986 and Se tember

1986 Re ort No. 50-410/86-52 Special announced team inspection to evaluate the licensee's position that the programmatic quality assurance (QA) issues identified by Quality First Program (Q1P) concerns 86-64 A to G have not resulted in hardware deficiencies or im-peded the ability of QA department personnel to identify or correct hardware deficiencies.

The inspection involved review of licensee records and inter-views with QA department personnel.

'It included 140 hour0.00162 days <br />0.0389 hours <br />2.314815e-4 weeks <br />5.327e-5 months <br /> s on site by 2 section chiefs, one senior resident inspector and one resident inspector.

ggg11~

@6120202~2 gggpR10 PDR AOt3CV o pDR

I

1. 0 In s ection Conclusions 1.1 The following programmatic QA weaknesses were identified by the NRC in addition to those identified by the Q1P investigation:

(1)

QlP review of QA concerns lacked active independent management involvement similar to that normally provided by offsite review committees (Section 4.0).

(2)

Bypassed QC hold points were not trended for frequency, repeat offenders, or repeat by discipline (Section 6.6).

(3)

QC hold points in maintenance procedures and related QC check-listss were not consistent (Section 6.3).

1.2 As a result of NRC reviews the following QA program weaknesses pre-viously identified by the licensee's Q1P investigation were clarified and confirmed:

(1)

Limits on troubleshooting activities performed under Deficiency Reports (DRs)

and Work Requests (WRs) are not well defined, and QA Engineering is not providing clearly established inspection attributes to QC inspectors.

(Sections 5.0, 6. 1 and 6.2)

(2)

While QA department personnel have been adequately trained on QA procedures, there has been no formal training on implementing policy guidance disseminated by numerous memoranda.

In addit-ion, there is no vehicle in use for continuing training of new contractor personnel or on new policy guidance.

(Section 5.0, 6.6 and 6.9)

1.3 None of the

QA department personnel interviewed by inspection team members knew of any uncorrected hardware deficiencies or believed that they had been impeded from identifying or correcting any hard-ware deficiencies because of programmatic QA weaknesses.

1.4 NRC reviews noted evidence that QA overchecks of QC inspection act-ivities have been identifying and assuring correction of hardware deficiencies.

(Section 7.0)

2.0

~Back round 2. 1 C Ins ector Certification On August 20, 1986 the NRC received allegations, that NMPC had im-properly certified two QC inspectors, that NMPC QC inspectors had performed inspections outside their certified discipline, and that the NMPC Quality First Program had no't been responsive.

NRC Region I conducted an allegation review panel to document recipt of the con-cerns and determine appropriate followup actions.

As a result, on

'l I -i

August 26 and 27 an NRC inspector reviewed NMPC QA procedures, inter-viewed QC personnel, reviewed QA records, and accompanied QC person-nel during the conduct of inspections.

Conclusions reached relative to the allegations are described in section 8.0.

2.2 ualit First Pro ram Concern 86-64 Subsequently, on August 28, an NRC inspector reviewed Quality First Program (QlP) records and noted concerns 86-64 A thru G, which add-ressed the following issues regarding NMPC QC activities:

(1)

Lack of management support.

(2)

Lack of supervisory guidance.

(3)

Lack of procedural training.

(4)

Lack of procedural adherence by Startup and Test, and QA.

(5)

Inconsistent procedural implementation.

(6)

Inadequate QA communication channels.

(7)

Lack of QA management feedback to inspector suggestions or concerns.

(8)

Premature Deficiency Report closure'9)

Bypassed QC witness points.

The Q1P findings had been forwarded to senior NMPC management for resolution.

On August 28, Region I management was informed of the above concerns regarding the NMPC QA/QC program implementation.

After becoming aware of these concerns, management meetings between Region I and NMPC were held on August 29 and September 4.

A list of attendees is included as Attachment 1.

NMPC concluded that while the concerns of the NMP2 employees had raised some valid programmatic concerns which were being addressed, these concerns had not resulted in any unsatisfactory hardware.

These conclusions were based on Q1P interviews with all QC inspec-tors, both NMPC personnel and contractors, which did not identify any unresolved hardware issues.

In addition, NMPC stated that the QC function was overchecked by QA audits, QA survei llances, and QA engineering.

The licensee position was documented in a letter to NRC Region I dated September 1,

1986 and in Attachment 2 to this report which was presented at the September 4,

1986 meeting.

NMPC's initial corrective actions in response to the Q1P concerns included meetings between the Vice President, QA and all levels in the QA department to explain departmental policy relative to the concerns addressed and to direct field involvement of QA engineers in defining inspection criteria for troubleshooting activitie t I

1"

In response to a question during the September 4,

1986 meeting re-garding how the licensee could be sure that QA department personnel were not being impeded from identifying hardware issues by these programmatic weaknesses, the licensee conducted a survey of all QA department personnel with negative results as described in a September 9,

1986 letter to NRC Region I 3.0 Ins ection Method and Sco e

The inspectors independently evaluated the concerns of former Nine Mile Point Unit 2 (NMP2) employees related to programmatic weaknesses in quality control (QC) inspections of preoperational testing and the impact of these concerns on the acceptability of installed and tested hardware.

These concerns had previously been evaluated by the licensee's Quality First Program (Q1P)

as concern 86-64, which concluded that the concerns re-presented valid programmatic quality assurance (QA) program weaknesses but had not adversely affected the quality of the installed hardware.

Also, the inspection evaluated portions of the QA program, other than QC, to determine whether their overcheck functions had been effectively per-formed.

The inspectors reviewed the background information developed by the Q1P investigation, interviewed a

sample of NMP2 QC inspectors including con-tractors, NMPC QC inspectors, supervision and management, and verified the resolution of selected quality issues for which the acceptability could not be determined through the QC interview and records review process.

In addition, the inspectors interviewed a sample of personnel from other QA organizational elements including NMP2 Startup/Operations Surveillance, NMP2 Quality Engineering, and NMP2 QA Audits to determine whether the pro-grammatic weaknesses identified by QlP in the QC group impacted the groups providing the overchecks of the QC program.

4.0 1P Review of Concerns 86-64 A to G

Based on a review of the files and di scussions with the Q1P manager and interviewer, the Q1P review of concerns 86-64 A to G generally proceeded in accordance with QAP 16.70.

The planning of the investigation of the concerns was thorough and the conclusions were sound.

However, several of the QA personnel interviewed by NRC inspectors questioned the independence of Q1P in reviewing concerns relating to the QA program.

The provisions to assure independent management oversight of such concerns by the Adminis-trative Assistant to the President involved merely informing him of such activities rather than active involvement.

It is not evident that the corrective action plan, proposed by the Vice President, QA for the valid Q1P concerns, received the independent manage-ment review and approval required by QAP 16.70 before it was submitted to the NRC by letter dated September 9,

1986.

However, active participation by the President and Senior Vice President in the corrective action plan after the NRC became involved is acknowledged.

The licensee response to this issue will be reviewed during a subsequent inspection.

(50-410/

86-52-01)

n i

5.0 NRC Interviews During this inspection,

QA department personnel were interviewed by the NRC including 12 QC inspectors,

QA Engineers, 2 QA Surveillance in-spectors,

QA Auditors, and

QA management and supervisory personnel.

The interviews included questions in the following areas:

Position Responsibilities Qualifications Training QA Program Effectiveness QC Inspection Activities QA Surveillance Activities QA Audits QA Engineering Activities.

Supervisory Support and Guidance Working relationships with other parts of QA Department Working relationships with other parts of the site organization Work experiences Concerns None of the interviewees knew of any uncorrected hardware deficiencies.

Only one individual believed that there could be hardware deficiencies which were not identified related to the control of troubleshooting and work activities as discussed in Sections 6. 1 and 6.2.

The examples dis-cussed do not represent work on safety-related equipment without any QA/QC oversight because there were Deficiency Reports and Work Requests to cover the work, but the guidance to the workers and the inspection criteria were so non-specific that the acceptability of the work required considerable judgement and continuous QC coverage.

The individual acknowledged that these issues had been appropriately dispositioned, but was concerned that work of unacceptable quality could occur when the work scope and inspec-tion criteria are not clearly defined in troubleshooting activities. Half of the interviewees expressed this general concern without specific exam-ples.

The licensees letter of September 9,

1986 addressed the inspection criteria concern by committing to field involvement of Quality Engineers in developing inspection criteria for troubleshooting, but did not add-ress the responsibility of the line organization to place appropriate limits on workers for such work to assure appropriate engineering review

  • (

prior to work completion.

The licensee response to this issue will be reviewed during a subsequent inspection.

(50-410/86-52-02)

While there is evidence of formal training on QA procedures, as discussed in section 6.4, half of the interviewees in the QC group believed that the policy guidance for implementing the QA procedures was inconsistent, poorly communicated and confusing.

This situation has been aggravated by reas-signment of supervisory and management personnel, a reorganization which split the Quality Engineering and Quality Control functions, the turnover of many contractor QC inspectors, the transition from a rigidly defined construction QA program to a very flexible operations QA program, and the replacement of formal QA Instructions for implementing QA procedures by uncontrolled memoranda, verbal guidance or no guidance at all.

Although the licensee corrective action described in the September 9,

1986 letter addressed these concerns, on a one time basi s, there is no continuing program to assure that new employees receive this information or to assure that future policy changes are appropriately communicated.

The licensee response to this issue will be reviewed during a subsequent inspection.

(50-410/86-52-03)

Followup on specific concerns raised during the interviews is discussed in section 6.0.

6.0 NRC Pollowo of IP Concerns and S ecific Interviewee Concerns 6.1 Control of Tr oubleshootin Activities As documented in Q1P concern 86-64F, and discussed with an NRC in-spector during an interview, a Quality Control Inspector discovered individuals cutting a hole in safety related panel No.

028 associated with the high pressure core spray system diesel generator, to install a temporary modification for preoperational testing without any docu-mentation to support that work.

The NRC inspector spoke with one Startup and Test individual and reviewed the Q1P documentation pack-age relative to this concern.

Documentation had been prepared con-cerning this temporary modification in advance in the form of Eng-ineering and Design Coordination Reports (E 8 OCRs)

258352 and 258352A; Deficiency Reports (DRs)

11173, 17823, and 19281; Inter-office Correspondence (IOCs),

ESEG 86-5-12 and 86-5-7; and Problem Report (PR)

0421 A.

DR 18649 which controlled the work had been im-properly signed off as completed prior to work completion leading the QC inspector to believe that no documentation covering the work exis-ted.

Although the work performed in this case was acceptable, it was not clear to the QC inspector that it would have been without his involvement.

While the finally accepted work was adequate, this is an example for which better definition of the work scope and QC inspection require-ments was necessary to assure the quality of safety-related equip-men.2 Control of Work Activities During an interview, the NRC was informed of a concern relating to the improper control of troubleshooting activities on a

RHR service water sample pump 2SWPCAB23B.

The inspector reviewed Work Request (WR) 103572, QCIR 2-86-3862 and Corrective Action Request (CAR)

86-1012.

The extent to which the maintenance personnel could dis-assemble the component was not specified on the WR.

The pump and motor were apparently disassembled without the reference to the associated vendor manual.

This work was an example where direct involvement of Quality Engineers and work scope definition was neces-sary to specify the extent of troubleshooting activities.

Without the involvement of the QC inspector, it was not clear to the con-cerned QC inspector. that the work on the pump would have been accept-ablee.

This is another example of a case where the finally accepted work was adequate, but for which better definition of the work scope and QC inspection requirements was necessary to asure the quality of safety related equipment.

6.3 Inconsistent Hold Points Between C Checklists and Maintenance Procedures During an interview, the NRC was informed that NMPC maintenance pro-cedures and the applicable NMPC QC checklists do not contain consis-tent hold points.

The inspector reviewed the following checklists and procedures:

Title Overhaul of CRD Hydraulic Control Units C Checklist and Maintenance Procedure No.

N2-MMP-30.3 Overhaul of Control Rod Drive N2-MMP-30.8 Maintenance.

of LPCS Pressure Pump Maintenance of HPCS Pump Maintenance of HPCS Pressure Pump N2-MMP-32.2 N2-MMP-33. 1 N2-MMP-33.4 Overhaul of Reactor Core Isolation Cooling Pump N2-MMP-35. 1

n p

I'4 el'

.

The inspector identified the following discrepancies:

QC Checklist MMP-30.8 attributes 1 through 10 did not have asso-ciated QC holdpoints in the maintenance procedure MMP-30.8 data sheet.

Attribute 2 in QC checklists MMP-32.2; 33. 1, and 33.4 was not contained in the associated maintenance procedure data sheet.

QC holdpoints in the maintenance procedure data sheets were not included on the associated QC checklists as exemplified by item 7.26.2 and 7.27.2 of MMP-30.8, and Items 7. 1. 14, 7.3.9, 7.3. 10 and 7.5.6 of MMP-33. 1.

The inspector's review confirmed the expressed concern that the QC checklists and associated maintenance data sheets are inconsistent.

The licensee corrective actions in this area will be reviewed at a

later date.

(50-410/86-52-04)

6.4 C Personnel Trainin As a followup to Q1P concerns 86-64 C and E, the inspectors inter-viewed site QA and QC personnel and reviewed the adequacy of training and qualification of these personnel.

All these personnel were qualified to ANSI N 45.2.6 Level II'he inspector reviewed the

'raining and qualification records of five QC personnel and verified that their education and experience levels met those specified in ANSI N 45.2.6.

Licensee Procedure QAP 2.10 (Revision 7) establishes the training requirements for QA and QC personnel.

This program requires initial, on-the-job, and continued training as well as periodic reading assign-ments.

Through a review of selected training records and technical discussion with personnel, the inspector determined that the per-sonnel were qualified and trained in accordance with QAP 2. 10, were knowledgeable in the technical requirements of the activities that they monitor, and kept their knowledge level current by completing the required reading of the procedures.

In addition to the initial reading of the procedures, the personnel were required to reread these procedures when revised.

The inspector noted that the reading was required by the supervisors and proficiency was verified by the supervisors or lead personnel.

Adequate time was allocated for the initial reading and rereading.

On the average about six procedures had been read by the personnel.

In addition to the reading, certain key procedures were discussed with personnel during formal classroom training.

The inspector noted that the QC personnel training records reviewed indicated attendance at three or more formal training sessions since June 1986 '

The inspectors determined that the QA and QC personnel were trained on QAPs and that the training records were maintained in accordance with QAP 2. 10.

No discrepancies were identified.

6.5 Closin of Oeficienc Re orts DRs and Polic Guidance Q1P concerns 86-64 8 and G included several examples in which Defici-ency Reports (DRs)

had been prematurely closed.

The following closed ORs were reviewed by the inspector for which no associated inspection was recorded in the QC DR logbook:

OR Startu and Test Com uter Status Ex 1anation 10051 10075 10108 10109 10118 12132 12449 Closed Closed Closed Closed Closed Closed Closed Work performed on WCR 9284 Deficiency Report 11861 issued Cancelled Cancelled QC determined no inspection necessary Worked on multiple DRs QC determined no inspection necessary The inspector reviewed the QC files of open QC checklists for DRs and Mork Requests (MRs).

The following documents were reviewed:

Open OR in gC File 15093 gCIR 2-86-1024 Ex lanation Work previously performed for checklist from EMP-114-1 17088 2-86-1687 Work previously performed with satisfactory checklist Open MR in

~CFi le 3684 100979 Computer Status Closed Closed Ex lanation QCIR 2-85-1012 and NCR 2-86-0036 previously issued QCIR 2-86-2852 and DR 21202 previously issued 103300 Closed Inspector found no leaks so MR was closed without any work

I!

The inspector determined that while the QC logs and files were not consistent making it difficult to verify closure, the DRs and MRs were properly closed in all cases with appropriate QC involvement.

The inspector reviewed Startup Administrative Procedure (SAP)

121A,

"Deficiency Reporting System".

The procedure requires a final QA review of DRs to ensure proper completion.

The inspector discussed the review of DRs with associated Quality Engineering (QE) personnel.

The inspector reviewed several logs that indicated QE personnel were fulfilling the procedure requirements.

Two programmatic concerns were identified:

The QE staff does not maintain a trend history of DRs that are found unsatisfactory during their document review.

For example, instances of bypassed QC holdpoints detected by QE review are not explicitly flagged and trended, although the items are re-solved on a case by case basis.

The inspector was presented QA poli'cy memo 86-001 that described the mechanics of the QE review process.

This memo was an example where the general Quality Assurance Procedures (QAPs) did not contain sufficient implementing direction for QA personnel, which resulted in the issuance of the informal memo and verbal instructions.

The licensee responses and corrective actions to the above concerns will be reviewed at a later date.

(50-410/86-52-05)

6.6 Follow u on Cables with Outer Jackets Cut During an NRC interview, one QC inspector stated that in September 1985 he identified that contractor personnel were cutting into the outer jackets of installed cables while trimming back the fire pro-tection foam from the PGCC cables.

The contractor personnel used sharp knives to trim back the foam and one cable was cut through to the conductor.

DR 05681, EKDCR C 46072 and NMPC NCR 2-85-007 were generated to identify and resolve the concerns associated with cut cables.

QC issued Surveillance Report SR-85-10317 to address this concern.

The QC inspector who originated this surveillance report did not believe that he had all the facts necessary to accept the corrective actions in December 1985.

At that time he believed that the corrective actions were limited to the items discussed in the surveillance report and that an investigation by QC had not been performed to determine the existence of similar problems in other cables.

Based on the above, the QC inspector requested that his supervisor resolve this surveillance report.

The supervisor closed this surveillance report on December 4,

1985 based on his understanding of planned corrective action in this area which was later documented in a Report of a Problem dated May 27, 1986.

However, the supervisor did not explain his reasons for closing this surveillance report to the QC inspecto I Ti+

The NRC inspector reviewed this issue to assess the adequacy of-licensee actions when a surveillance report was closed out by the initiator's supervisor.

This concern was reported to the licensee's architect engineer for resolution in a Report of a Problem dated May 27, 1986.

An engineering evaluation was performed, and a deci-sion was made to randomly inspect eighty cables from all affected areas.

This inspection was completed on August 12, 1986, and it identified four additional cables that were cut but not through the jacket.

The inspector determined that the cuts identified in these four cables were within the allowables established in the licensee specifications.

The inspector determined that this licensee action was adequate to resolve the concern identified in the QC Surveillance Report.

The inspector furnished a copy of the licensee'

engineering eval-uation and additional cable sampling to the QC inspector who had initiated the original QC Surveillance Report.

The QC inspector reviewed this additional material and stated that the new analysis and sampling inspection were adequate to address his original con-cern.

He also stated that this additional information would enable him to discuss the disposition of this concern in a positive manner.

should the issue surface again.

The inspector had no further quest-ions in this regard.

6.7 Use of Uncalibrated Measurin and Test E ui ment Durin Retests A concern was expressed to the NRC during an interview that Quality Control (QC) inspectors did not verify the use of calibrated measu-ring and test equipment (MME) during retests.

An NRC inspector interviewed the QC supervisor and was informed that the requirement for METE verification applied to retests.

The inspector reviewed the NMPC Quality Control Inspection Report (QCIR) files.

Based upon the review of QCIRS 2-86-1314, 2-86-5180 and 2-86-5462 that documented the use of calibrated MME during retest activities, the review of additional QCIRS, and the statements of QC supervision, this concern was not substantiated.

6.8 Inade uate Verification of Recei t Ins ection One QC inspector expressed a concern during an NRC interview that QC inspectors were directed by letter NM QA 1735 dated December 16, 1985 not to perform the pre-installation verification (PIV) or to verify receipt inspection of parts from ministock.

In addition, he believed that the stockroom had been directed to stop performing receipt in-spection of spare parts.

Discussions with individuals in the Stores Receipt and Inspection department, along with a review of applicable procedures provided assurance that all parts were inspected upon receipt.

In addition, memorandums issued provided direction to verify receipt inspection of parts.

NMPC letter NM QA 1735 dated December 16, 1985, which instructed that the PIV not continue, was issued to prevent redundancy of inspection since the verification would be per-

~

formed at installation under the Niagara Mohawk Quality Program.

In addition, memorandum 9M STQA 85-13 dated December 20, 1985 provided direction to verify receipt inspection of parts.

While this concern was unsubstantiated, it is another example of the need for training on policy guidance.

7.0 Followu on A Overchecks To determine the involvement and effectiveness of NMPC QA overcheck func-tions of the test and maintenance activities, the inspectors reviewed the following documents regarding audits, surveillances and corrective actions and discussed them with appropriate managers and supervisors:

NMPC Audits NM-RE-IN-86005, 86008, 86014, and 86017 NMPC Surveillance Reports 86-10510, 10603, 10626, 10640, 10641, 10677, 10605, 10577, 10594, 10452, 10294, 10131, 10124, 10271, 10368, 10453, and 10445.

Corrective Action Requests 86-1000, 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010 and 1014.

The QA audits were detailed and focused on documented compliance with QA program requirements and Preoperational Test procedure requirements.

While the audits met the requirements of 10 CFR 50, Appendix 8, their usefulness in assessing the effectiveness of program implementation was limited since they involved little in-process observation of work activities or interviews with personnel implementing the programs and focused on after the fact review of records demonstrating compliance with requirements.

The QA surveillance program was well-structured and implemented to assess programmatic effectiveness and identify hardware problems, and assure appropriate corrective action.

The survei llances documented an extensive review of preoperational test results.

In several instances, test eng-ineers had not processed necessary Deficiency Reports (DRs).

As a result of the surveillance program review the DRs were subsequently issued.

The surveillance function also had identified problems in controlling the use of red plastic screws to isolate circuits in the control room ar ea and assured correction of the problem.

The concerns detected and the scope of corrective actions indicated that satisfactory oversight of the field activities has been maintained.

8.0 C Ins ector Certification As discussed in section 2.0, the NRC had previously been informed that NMPC had allegedly improperly certified QC inspectors.

The inspector re-viewed the following documents:

SWEC and NMPC QC certification records.

QAP 2.60, "Qualification and Certification of QA Inspection and Test Personnel".

il I

lp

QAP 2. 10, "Training".

FSAR Table 1.8-1, page 64-67.

NMPC Quality Assurance Topical Report.

Regulatory Guide 1.58, "Qualification of Nuclear Power Plant In-spection, Examination, and Testing Personnel".

ANSI N45.2.6, "Qualifications of Inspection, Examination, and Testing Personnel for Nuclear Power Plants.

The inspector reviewed the certifications of 6 QC inspectors and deter-mined that they were in accordance with the applicable requirements.

The inspector accompanied an electrical inspector during the conduct of a megger test on the Division I diesel generator output breaker.

The in-.

spector reviewed the associated work documents and found the QC inspector knowledgeable of the inspection requirements.

The inspector also reviewed approximately 220 QCIRs and identified no in-stances of QC inspectors performing inspections outside the scope of their certification.

The inspector reviewed thirteen additional QCIRs performed by a mechanical QC inspector identified by the alleger as unqualified for some of the inspections he performed and verified that the inspection activities were within the scope of the QC inspector's certification.

The inspector determined that the NMPC certification program is in conformance with commitments and requirements, that NMPC inspectors are properly cert-ified, and that the inspectors are performing work within their capabili-ties.

No discrepancies were identified and allegation RI-86-A-099 is not substantiated.

9.0 Exit Interview The scope and findings summarized on the inspection cover sheet under Inspection Results were discussed with the President, Vice President, QA, and other attendees identified in Attachment 1 at an exit meeting on September 12, 1986.

Based on NRC Region I review of this report and di s-cussion held with licensee management at the exit meeting, it was deter-mined that this report does not contain information subject to 10 CFR 2 '90 restriction ip

ATTACHMENT 1 Meetin Attendees

"Meeting

~ke

2

2

1

4 1234 3 4

4 3 4

3 4

4

4

4

2

4 4.

4

4

3

2

3

2

2

2 W. Donl on C.

Mangan T.

Lempges J.

Perry W.

C.

G.

J.

J.

P

~

Hansen Beckham Doyl e Buckley Shepherd Wilde A. Kovac E.

T.

L.

T.

R.

G.

K.

R.

M.I.

G.

K.

B.

M.

J.

J.

G.

F.

D.

S.

R.

C.

Manning Gamon Fenton Perkins Abbott Afflerbach Dahl berg Mattock Ray Weakley Griffith Ward Hooten Boyl e Beratta Dillon Wilson McCarthy Kerr Wilczek Pasternak Gre sock NMPC President Senior Vice President Vice President, Nuclear Generation Vice President, QA Manager, Nuclear QA Operations QA Engineer Startup Quality Engineer QC Supervisor QC Lead QA Surveillance Supervisor QlP Manager Q1P Interviewer QlP Interviewer QA Auditor lead General Superintendent Station Superintendent Work Control Manager Maintenance Superintendent Deputy Project Director Manager, Special Projects Special Projects Licensing Manager Consultant Nuclear Design Special Consultant Nuclear Compliance and Verification Security Audit/Q1P Senior Supervisor System Attorney Security Corporate Performance Services Manager Nuclear Technology Manager Nuclear Consulting Services Manager Nuclear Design

II 1l

ATTACHMENT. 1

  • Meeting

~ke

2 1234

2

1

2234 234

3 4

4 3 4 OTHER T.

E. Murley J.

Al 1 an W.

F.

Kane ST Ebneter T.

Martin W.

Johnston S.

Collins R.

Gallo J.

Linvi1 1 e P.

K.

Eapen G.

Meyer W.

Cook C.

Marschall W.

Schmidt NRC Regional Administrator Deputy Regional Administrator Director, Division of Reactor Projects (DRP)

Director, Division of Reactor Safety (DRS)

Director, Division of Radiation Safety and Safeguards (DRSS)

Deputy Director, DRS Deputy Director, DRP Chief, Projects Branch 2, DRP Chief, Reactor Projects Section, 2C DRP Chief, Quality Assurance Section, DRS Project Engineer Senior Resident Inspector Resident Inspector Resident Inspector

P.

P.

J.

K.

M.

  • Meetin ke Eddy MacEwan Drake Roenick Wetterhahn PSC Site Representative NYSEG Manager SWEC Startup Special Projects Supervisor PSC Site Representative Attorney, Conner and Wetthahn 1-August 29, 1986 2-September 4,

1986 3-September 8,

1986 4-September 12, 1986 Management Meeting Attendees Management Meeting Attendees Entrance Meeting Attendees Exit Meeting Attendees

1

hg ATTACHMENT 2 NIAGARA MOHAWK QUALITY FIRST PROGRAM ACTIVITIES PRESENTATION TO U.S.

NRC REGION I SEPTEMBER.4, 1986

~

~

3 get e

e l Q1P CONCERNS 86-00064A-G RECEIVED FROM THREE QC CONTRACTORS AT TIME OF TERMINATION CO INVESTIGATION NMPC QC MGT.

PREVENTING NCR ISSUANCE WHEN DR'S OR PR'S ARE NOT APPROVED.

VALID PR'S*

AND DR'S CLOSED WITHOUT PROPER RESOLUTION OF OUTSTANDING IR'ST SU&T PERFORMING UNAUTHORIZED SIGNOFF OF DR'S.

VALID

  • (INVALID)

LACK OF SUPPORT FROM NM QC MGT. TO SUPPORT QC PEOPLE IMPLEMENTING QC PROGRAM.

VALID QCIR NO. 2-86-0044 CLASSXFZED CAT 1, UNSAT.

ITEMS IDENTIFIED.

QCIR IMPROPERLY CLASSED CAT II TO ELIMINATE REINSPECTION.

INVALZD NM QC PEOPLE UNAWARE OF CHANGES IN SAP '

AND QAP'* (i.e.

SAP 1. 21A)

VALID

  • (INVALID)

SU&T GIVING VERBAL DIRECTION AND/OR XSSUING MEMOS TO GIVE ENGINEERING DIRECTION AND RESOLUTION OF PR'S AND DR'S AND TEMPORARY MODS. (i.e.

2FPM-PNL129)

~

INVALID

C

C 0 OLOGY OF CONCERN 86-64 MECH 7/2&3 RECEIVED VERBAL CONCERNS FROM THREE CONTRACTOR QC PEOPLE DURING TERMINATION.

'Cn PROGRAMMATIC & IDLED AS FOLLOWS SU&T DOMINATES QC ACTIVITIES LACK OF COMMUNICATION PROCEDURES HARD TO WORK TO NO JOB DEFINITIONS 7/3-8 RECEIVED ANONYMOUS CALLS THAT INFORMATION GIVEN BY THREE QC PEOPLE WAS LEGITIMATE.

DECIDED TO INTERVIEW MORE PEOPLE QUESTIONS AT INTERVIEW RELATE TO CONCERNS DECIDED TO USE 2 INTERVIEWERS/INTERVIEW 7/10 INTERVIEWED 22 PEOPLE.

7/11-31 INTERVIEWED REMAINING PEOPLE.

ALLOWED INTERVIEWEES TO DISCUSS ANYTHING.

IF RELATED TO CONCERNS ASKED IF AWARE OF PROBLEMS IN AREA.

IF CONVERSATION, DID NOT ADDRESS CONCERNS THEN QUESTIONS ASKED.

FOLLOWING INTERVIEWS INTERVIEWERS SHARED NOTES'DEAS, AND CLASSIFIED THEIR PERCEPTION OF INTERVIEW.

TOTAL 29 PEOPLE INTERVIEWED, 17 WERE CONTRACT AND 12 WERE NMPC DIRECT EMPLOYEES.

7/14-8/16 Q1P INITIALINTERVIEWER & INVESTIGATORS ARRIVE AT PLAN OF ACTION TO VALIDATE CONCERNS.

START INVESTIGATIONS TALK TO PEOPLE, REVIEW OBJECTIVE EVIDENCE (DOCUMENTS),

CONDUCT INTERVIEW ARRIVE AT CONCLUSIONS WRITE INVESTIGATIVE REPORTS AND RESULTS VALID OR INVALID.

8/19 MGR. Q1P

& INTERVIEWED MET VICE PRESIDENT-Q-A.

&

VERBALLY PRESENTED RESULTS AND BACKGROUND MATERIAL FOR V.P.-Q.A.'S ACTIO l

'h

C RONOLOG

CO CE N 86-64 co t'd.

EVNS 8/2 1 Q1P FORMAL TRANSMITTAL OF ALL CONCERNS TO V.P.-Q.A.

FOR RESPONSE ON Ag Bg C~ E

& G 8/21 V.P.-Q.A.

MET WITH MGR.

NUCLEAR QA OPERATIONS AND QC SUPERVISOR.

DISCUSSED EACH CONCERN, BRAINSTORMED EACH AND DRAFTED RESPONSES.

8/25 DRAFT LETTER AND REVISED RESPONSES FROM MGR.

NUCLEAR QA OPERATIONS RECEIVED BY V.P.-Q.A.

8/26&27 LETTER AND RESPONSES STRENGTHENED AND FIRMED UP.

8/28 LETTER WITH RESPONSE DATED 8/27 SIGNED BY V.P.-Q.A.

AND DISTRIBUTED.

8/28 NRC RESIDENT REVIEWED Q1P FILE MATERIAL.

8/29 NRC REGION I MEETING WITH NMPC SENIOR MANAGEMENT REGARDING Q1P CONCERN.

8/31 V.P.-Q.A.

LETTER TO MANAGER LICENSING AND RESPONSE RECEIVED ON REPORTABILITY AND IMPACT ON CERTIFICATION OF COMPLETION OF UNIT 2.

9/1 V.P.-Q.A.

ISSUED RESPONSE SUPPLEMENT LETTER TO Q1P.

9/1 NM PRESIDENT SIGNED LETTER TO MR.

KANE ON QlP ACTIVITIES.

9/2 LETTER TO MR.

KANE RECEIVED AT REGION ~

k

KEY FACTORS FORMING BASIS FOR USION REGARDING NO IMPACT ON PHYSICAL PLANT QUALITY vs.

ELE TSOF THE INVESTIGATION REPORT ELEMENTS OF INVESTIGATION REPORT FACTORS C/I EDI-IJJ 4-I CIJ C

Ctl I-

C/I C7 a

~g I-CIJO

/CJ CIJ I

C/I ~

eo CJ I

~

C/J

L I/l CL Clt.'CO CT C)

I LCJ CL C/I lCJ I/l C/l O CIJ r I

O D

CIJ I CJ M O

C/J I-C Q M C/l lDI-CJ C)

LJ O

O

'I I

4J I/l O

w gCJ CJ wg C/l CIJ I

~g C/I O

CL C/l CIJ 4X C7l

~g

~p ICJII-IO CL C/I O

ICJ CJ 8O OH IO CIJ EJ O

ICJ CL CIJ O

I CIJ CL 1. Persons inter viewed stated

"no hardware problems".

2. Not reportable 50.55(e)

X X

3.

Item not directly hardware related.

4.

Item indirectly hardware related.

X 5.

QC Inspection overchecks X

J e 4 r

ATTAC59G~NT Revision

9/2/8 6 (Ref. Concerns 86-00064)

1.

The Quality First program investigation shoved that each concernee and every other person intervieved specifically stated that they knev of no hardvare problem which vas not supported for correction by QC Supervision.

2.

All items identified were determined not reportable per

CFR 50. 55 (e).

3.

QC inspection activity is overchecked by many specific programs.

a.

Audits - Since June, 1985, 12 audits have been performed that are test and hardware oriented.

b..Surveillances -

Since January, 1986, approximately 700 surveillances have been performed of testing and quality control activities.

c.

There are reviews of completed inspection documents performed routinely.

d.

Quality Engineering reviews DR's and WR's to verify'hat any required inspections were performed consistent with the work description.

e.

Some specific components received functional tests.

f.

Preoperational/Acceptance tests were often used to verify the individual components/equipment integrity on a system basis following inspection activities.

g.

Work documentation such as DR's routinely require

"retest" of some conditions following completion of work and inspection activities.

h.

Start Up personnel are certified per ANSI N45.2.6 to perform testing functions.

i.

Component and system acceptance is based on recorded data and evaluated by a certified Level IXI Test Enginee l lt

NMPC NUCLEAR UESTIONNAIRE ITEMS 27-QA

& OTHER DEPARTMENTS WORK AS TEAM TO RESOLVE QUALITY PROBLEMS.

4-NUCLEAR DIVISION GIVES PROPER ATTENTION TO QUALITY/SAFETY RELATED ISSUES.

21-QlP PROVIDES ADEQUATE CONFIDENTIALITY.

7.

OPEN AND HONEST COMMUNICATIONS REGARDING QUALITY AND SAFETY CONCERNS.

20.

IF SUPERVISOR DOES NOT RESOLVE CONCERN, WOULD USE Q1P.

33.

DURING OUTAGES RELUCTANT TO REPORT CONCERNS TO NMPC.

24.

Qlp ADMINISTERED PROPERLY.

12.

MY SUPERVISOR SUPPORTED BY BOSS TO RESOLVE PROBLEMS.

14.

IF SUPERVISOR DOES NOT RESOLVE-CONCERN, FEEL FREE TO GO TO OTHER MANAGEMENT LEVELS.

23-I FEEL PEER PRESSURE IF I USE Q1P.

11-MY SUPERVISOR GIVES ME FEEDBACK ON RESOLUTION OF PROBLEMS.

13-MY SUPERVISOR RESPONSIVE TO SAFETY/QUALITY RELATED IDEAS.

NQA OPS.

SECTION LOWER 4 POSITIVE RESPONSE 9Ml 9M2 X

X X

X X

10 ~

WHEN CALLED TO SUPERVISOR S ATTENTIONi SUPERVISOR TAKES ACTION ON SAFETY/QUALITY ISSUES.

8-MY SUPERVISOR ENCOURAGES IDENTIFICATION OF PROBLEMS-X X

~

I C

c CO 86-00064C GA N

V P.

Q A RESPONSE OF 8/27/86 1 ~

DOMINATION BY START UP 1C 2I

2.

LANGUAGE NOT MENTIONED*

3.

SYSTEM COMPLEX/CONFUSING 1, 2, 3,

4.

POOR COMMUNICATIONS 1,

2, 3, 4,

  • NOTE-V P.

Q A. LETTER DATED 9/1/86 TO MANAGER Q1P SUBJECTS RESPONSE SUPPLEMENT, ADDRESSES THIS SPECIFIC ISSU ~~

Ie+

~

=V I

~ l~

'll

~

~

I I

~

~

IS 1'