IR 05000373/1981041

From kanterella
Jump to navigation Jump to search
IE Insp Rept 50-373/81-41 & 50-374/81-19 on 811103-04.No Noncompliance Noted.Major Areas Inspected:Followup of Licensee Actions on Previously Identified Items
ML20039A787
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 12/04/1981
From: Reimann F, Wescott H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20039A784 List:
References
50-373-81-41, 50-374-81-19, NUDOCS 8112210305
Download: ML20039A787 (3)


Text

.-.

-

.

.

... _

.

_.

-

-

.

.

U.S. h0 CLEAR REGULATORY COMMISSION-REGION III'

Report No. 50-373/81-14; 50-374/81-19 Docket No. 50-373; 50-374 License No. CPPR-99; CPPR-100 Licensee:

Commonwealth' Edison Company P. O. Box 767 Chicago, IL 60690'

,

-Facility Name: La Salle County Station, Unit 1

,

Inspection At: La Salle Site, Marseilles, Illinois

,

Inspection Conducted: Nccent-r 3 and 4,1981 -

l (f C fhey Q

/2/ / b Inspector:

H. M. Wescott F. W. Reim& C ftinf' hief

/

/2/ O:

y e

Approved By:

ann, A f

Projects Section IC

/

Inspection Summary

'

Inspection on November 3 and 4, 1981 (Report No. 50-373/81-41; 50-374/81-19)

Areas Inspected: Routine announced inspection; followup of. licensee actions on previously identified items. The' inspection included a total of 16 inspector-hours onsite by one NRC inspector including 0 inspector-hours

~

,

onsite.during offshifts.

.

Results: Of the area inspected, no apparent items of noncompliance were

'

identified.

8

e

8112210305 8112049 PDR ADOCK 05000373

+

o PDR

=.

. =

-

-

- - -

-

-

-..

- -

.

.

- -.

.

-

l

.

DETAILS 1.

Persons Contacted

  • W. Donaldson, Assistant Project Construction Supervisor
  • D. Skoza, Project Construction Engineer
  • R. Vine, QA Engineer
  • Denotes those attending the exit meeting.

2.

Licensee Action on Previously Identified Items (Closed) 10 CFR 50.55(e) Report No. 50-373/77-01, dated October 14, 1977: Safety Relief Valve (SRV) control system deficiency (SRV re-opening after initial pressure transient from the design basis transient isolation event).

The inspector reviewed the test data and certifications of retest and resetting SRV's S/N 63790-00-0070, 71, 73, 79 received on MRR No. 7485 dated April 17, 1980, and the letter from S&L to CECO dated June 1, 1980 indicating acceptance of test data. The inspector found that the actions taken appear to be in conformance with the licensee's final report to USNRC, RIII, dated January 30, 1979.

This item is considered closed.

(Closed) 10 CFR 50.55(e) Report No. 50-373/80-01, dated August 22, 1980: Main Steam Isolation Vclve (MSIV) deficiency in the leakage control system. The inspector reviewed P&ID (Main Steam) M-55, sheet 8, Revision H, dated October 6, 1981, showing the modification to the MSIV Isolation Valve Leakage Control System. The licensee appears to be in conformance with their final report to RIII dated September 7, 1980.

This item is considered closed.

(Closed) 10 CFR 50.55(e) Report, 50-373/81-05, dated July 20, 1981:

Over pressurization of secondary containment roof. The roof has been repaired / replaced. The inspector reviewed CECO's " Construction Test Procedure Secondary Containment Leak Rate Test" approved November 2, 1981. The inspector finds that the actions taken by the licensee appear to be in conformance with their final report to USNRC, RIII dated August 8, 1981.

This item is considered closed.

(0 pen) 10 CFR 50.55(e) Report, 50-373/81-01, dated February 27, 1981:

HFA relay bobbin assembly cracking problem.

All HFA bobbin assemblies have been replaced. However, material certifications and test results were not available onsite.

-2-

- -

-. -

.

. _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _

___

_

__

. _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ - _ _ _ _ _ _ _ _ -

.

This item remains open pending the RIII inspector's review and acceptance of material certifications and test results.

(Closed) Unresolved Item 50-373/79-41-01:

Zack HVAC hangers are to be welded and inspected to revised standards. The inspector reviewed hanger fabrication details shown in prints M-1537 and M-1538 with respective hanger inspection sheets to verify that hanger details are clarified and inspected according to detail sheets. The inspector further reviewed M-1539 (hanger schedule) which indicates hanger location and references M-1537 and M-1538 for hanger detail.

This item is considered closed.

(Open) Unresolved Item 50-373/81-22-13:

Inadequate fire protection for records storage. The inspector reviewed the FSAR amendment No. 56 dated May, 1981. The last paragraph states that "We comply with the objectives set forth-in the referenced revision of this Regulatory Guide, with the exception that during construction quality assurance records are stored in 2-hour rated facilities."

This item remains open pending NRR's concurrence.

3.

Exit Interview The inspector met with licensee representatives (denoted in Paragraph 1) at the conclusion of the inspection on November 4, 1981. The inspector summarized the scope and findings of the inspection. The licensee representatives acknowledged statements by the inspector.

-3-

-.

- -

-

. -