IR 05000315/1986021

From kanterella
Jump to navigation Jump to search
Mgt Meeting Repts 50-315/86-21 & 50-316/86-21 on 860508. Major Areas Discussed:Licensee Corrective Action Plan
ML20205Q299
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/21/1986
From: Hawkins F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20205Q285 List:
References
50-315-86-21-MM, 50-316-86-21, NUDOCS 8605280252
Download: ML20205Q299 (2)


Text

..

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Reports No. 50-315/86021(DRS); 50-316/86021(DRS)

-

Docket Nos. 50-315; 50-316 Licenses No. DPR-58; DPR-74 Licensee: American Electric Power Service

. Corporation Indiana and Michigan Power Company 1 Riverside Plaza Columbus, OH 43216 Facility Name:

D. C. Cook Nuclear Plant, Units 1 and 2 Meeting Conducted: NPC Region III, Glen Ellyn, Illinois-t Report Approved By:

F. Hawkins, Chief f/2 l / 863 Quality Assurance Programs Date

'

Section Meeting Summary Meeting on May 8, 1986 (Reports No. 50-315/86021(DRS); 50-316/86021(DRS))

Areas Discussed:

This was a management meeting held to discuss the D. C. Cook Corrective Action Plan.

8605280252 860521 PDR ADOCK 05000315 O

PDR

_ _

_

.. _

_

_

_

_

_

.-

.

DETAILS 1.

Attendees American Electric Power Service Corporation M. P. Alexich,-Vice-President, Nuclear Operations P. A. Barrett, Lead Compliance Engineer J. G. Feinstein, Manager, Nuclear Safety and Licensing F. F. Kroeger, Manager, Quality Assurance Indiana and Michigan Electric Company J. E. Rutkowski, Operations Staff Assistant B. A. Svensson, Assistant Plant Manager - Operations W. G. Smith, Jr., Plant Manager US - NRC

N. J. Chrissotimos, Deputy Director, Division of Reactor Safety

'

J. J. Harrison, Chief, Engineering Branch, DRS C. W. Hehl, Chief, Operations Branch, DRS F. C. Hawkins, Chief, Quality Assurance Programs Section, DRS H. A. Walker, Reactor Inspector, Quality Assurance Programs Section J. F. Suermann, Reactor Inspector, Section 2A, Division of Reactor Projects J. K. Heller, Resident Inspector, DRP D. L. Wigginton, Licensing Project Manager, Nuclear Reactor Regulation 2.

Management Meeting A management meeting was held on May 8, 1986, at the NRC Region III offices in Glen Ellyn, Illinois. NRC representatives opened the meeting with introductory remarks and a brief presentation of NRC concerns regarding the licensee's corrective action system.

Licensee representatives then presented their proposals to address those concerns. Specifically, i

representatives from both organizations discussed the licensee's new Corrective Action Plan, which consists of a corrective action procedure and a consolidated trends program. Both organizations agreed that the P'.an would be fully implemented by October 1, 1986, i

l

_,. _ _.

-

-

__

. - _ _... _,,.. _ _ _ _ _ _ _ _ _ _.

_. _ _.. _, _.