MONTHYEARIR 05000280/20244032024-10-0303 October 2024 Cyber Security Inspection Report 05000280-2024403 and 05000281-2024403 Cover Letter (Public) IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 IR 05000395/20240012024-05-10010 May 2024 Integrated Inspection Report 05000395/2024001 IR 05000395/20240402024-05-0101 May 2024 95001 Supplemental Inspection Report 05000395/2024040 and Follow-Up Assessment Letter IR 05000280/20240012024-04-30030 April 2024 Integrated Inspection Report 05000280-2024001 and 05000281-2024001 IR 05000280/20244022024-04-29029 April 2024 Security Baseline Inspection Report 05000280/2024402 and 05000281/2024402 ML24095A2172024-04-12012 April 2024 – Review of the Spring 2023 Steam Generator Tube Inspection Report IR 05000280/20230062024-02-28028 February 2024 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2023006 and 05000281/2023006 IR 05000395/20230062024-02-28028 February 2024 Annual Assessment Letter for Virgil C. Summer Nuclear Station - Report 05000395/2023006 IR 05000395/20244032024-02-27027 February 2024 Security Baseline Inspection Report 05000395/2024403 IR 05000280/20230042024-02-0909 February 2024 Integrated Inspection Report 05000280/2023004 and 05000281/2023004 IR 05000395/20244012024-02-0808 February 2024 Security Baseline Inspection Report 05000395/2024401 IR 05000280/20244012024-02-0606 February 2024 Security Baseline Inspection Report 05000280/2024401, 05000281/2024401 and 07200002/2024401 IR 05000395/20230042024-01-31031 January 2024 Integrated Inspection Report 05000395/2023004 IR 05000280/20230102024-01-18018 January 2024 – Age Related Degradation Inspection Report 05000280-2023010 and 05000281-2023010 IR 05000280/20233012023-12-28028 December 2023 – NRC Operator License Examination Report 05000280/2023301 and 05000281/2023301 IR 05000395/20230912023-12-21021 December 2023 Final Significance Determination of a White Finding and Notice of Violation and Assessment Followup Letter–Nrc Inspection Report 05000395/2023091 IR 05000395/20234032023-11-0101 November 2023 Material Control and Accounting Program Inspection Report 05000395/2023403 Cover IR 05000395/20230032023-11-0101 November 2023 Integrated Inspection Report 05000395/2023003 IR 05000280/20230032023-10-25025 October 2023 Integrated Inspection Report 05000280/2023003 and 05000281/2023003 IR 05000395/20230902023-10-0404 October 2023 NRC Inspection Report 05000395/2023090 and Preliminary Yellow Finding and Apparent Violation IR 05000395/20230112023-09-27027 September 2023 Focused Engineering Inspection Report 05000395/2023011 ML23256A2672023-09-21021 September 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000280/20220042023-09-0101 September 2023 Reissue - Surry Power Station - Integrated Inspection Report 05000280/2022004 and 05000281/2022004 IR 05000395/20234012023-08-30030 August 2023 Security Baseline Inspection Report 05000395/2023401 IR 05000280/20230052023-08-23023 August 2023 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2023005 and 05000281/2023005) IR 05000395/20230052023-08-23023 August 2023 Updated Inspection Plan for Virgil C. Summer Nuclear Station (Report 05000395 2023005) IR 05000395/20230022023-08-14014 August 2023 Integrated Inspection Report - Integrated Inspection Report 05000395/2023002 and Apparent Violation IR 05000395/20230102023-08-12012 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000395/2023010 IR 05000280/20230022023-08-0404 August 2023 Integrated Inspection Report 05000280/2023002 and 05000281/2023002 IR 05000395/20234412023-07-17017 July 2023 95001 Supplemental Inspection Report 05000395/2023441 and Follow Up Assessment Letter ML23131A3512023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000395/20230012023-05-12012 May 2023 Integrated Inspection Report 05000395/2023001 IR 05000280/20230012023-05-0505 May 2023 Integrated Inspection Report 05000280/2023001 and 05000281/2023001 IR 05000395/20230402023-05-0101 May 2023 95001 Supplemental Inspection Supplemental Report 05000395/2023040 and Follow-Up Assessment Letter IR 05000280/20234012023-04-21021 April 2023 Security Baseline Inspection Report 05000280 2023401 and 05000281 2023401 ML23086B9172023-03-24024 March 2023 Steam Generator Tube Inspection Report for the Fall 2022 Refueling Outage ML23075A1702023-03-21021 March 2023 Security Baseline Inspection Report 05000395/2023420 IR 05000395/20234202023-03-21021 March 2023 Letter - Virgil C. Summer Nuclear Station, Unit 1 Security Baseline Inspection Report 05000395/2023420 IR 05000280/20220062023-03-0101 March 2023 Annual Assessment Letter for Surry Power Station, Units 1 and 2 - NRC Inspection Reports 05000280/2022006 and 05000281/2022006 IR 05000395/20220062023-03-0101 March 2023 Annual Assessment Letter for Virgil C. Summer Nuclear Station (Report 05000395/2022006) ML23041A0232023-02-13013 February 2023 Integrated Inspection Report 05000280/2022004 and 05000281/2022004 2024-09-26
[Table view] Category:Letter
MONTHYEARML24250A0782024-10-22022 October 2024 Relief Request RR-5-V1 Regarding Service Water Return Header Check Valves ML24255A3152024-10-22022 October 2024 Relief Request RR-5-V2 Regarding Pressure Isolation Valves ML24256A2322024-10-22022 October 2024 Relief Request RR-5-P1 Charging/Safety Injection Pumps 05000395/LER-2024-002, Loss of Control Room Emergency Filtration System2024-10-15015 October 2024 Loss of Control Room Emergency Filtration System ML24290A1052024-10-0707 October 2024 Core Operating Limits Report VCSNS Unit 1 Cycle 29, Revision 0 ML24283A0702024-10-0707 October 2024 Annual Submittal of Technical Specifications Bases Changes Pursuant to Technical Specification 6.4.J IR 05000280/20244032024-10-0303 October 2024 Cyber Security Inspection Report 05000280-2024403 and 05000281-2024403 Cover Letter (Public) IR 05000280/20240102024-10-0202 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000280/2024010 and 05000281/2024010 ML24274A1942024-09-26026 September 2024 (Vcsns), Unit 1 Subsequent License Renewal Application (SLRA) First 10 CFR 54.21(b) Annual Amendment IR 05000395/20244042024-09-26026 September 2024 Cyber Security Inspection Report 05000395-2024404 - Public ML24270A0022024-09-25025 September 2024 Inservice Inspection Owners Activity Report (OAR) ML24221A2112024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0592024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0542024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0642024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) ML24267A0552024-09-23023 September 2024 Clarification Regarding Area of Potential Effect for the Subsequent Operating License Renewal for Virgil C. Summer Nuclear Station Fairfield County, South Carolina (SHPO Project Number: 22-EJ0147) (Docket Number: 50-395) IR 05000395/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000395/2024402 ML24248A1712024-09-0303 September 2024 Proposed License Amendment Request - Temporary Service Water Supply to the Component Cooling Heat Exchangers IR 05000280/20240052024-08-26026 August 2024 Updated Inspection Plan for Surry Power Station, Units 1 and 2 (Report 05000280/2024005 and 05000281-2024005), Rev 1 ML24219A2372024-08-23023 August 2024 Issuance of Amendment Nos. 319 and 319, Adoption of TSTF-577, Rev. 1, Revised Frequencies for Steam Generator Tube Inspection, IR 05000395/20240052024-08-22022 August 2024 Updated Inspection Plan for Virgil C. Summer Nuclear Station - Report 05000395/2024005 ML24207A0402024-08-21021 August 2024 Summary of July 17, 2024, Public Meeting - TS 3.7/3.14 AOT for SW Piping Maintenance ML24190A4012024-08-19019 August 2024 Request for Withholding Information from Public Disclosure Regarding the Subsequent License Renewal Application - Dominion Energy Letter Dated May 30, 2024 IR 05000280/20240112024-08-13013 August 2024 Comprehensive Engineering Team Inspection Report 05000280/2024011 and 05000281/2024011 ML24164A0012024-08-12012 August 2024 Proposed Alternative Relief Request V-1 Inservice Testing of Pressure Isolation Valves (EPID l-2023-LLR-0060) IR 05000395/20240022024-08-12012 August 2024 Integrated Inspection Report 05000395/2024002 ML24180A0062024-08-0505 August 2024 Issuance of Amendment No. 227 to Modify Technical Specification 3.8.3.1 to Increase Completion Time for 120-Volt A.C. Vital Busses ML24218A3002024-08-0101 August 2024 Environmental Review Response to NRC Requests for Additional Information and Response to NRC Requests for Confirmation of Information Set 1 IR 05000280/20240022024-08-0101 August 2024 Integrated Inspection Report 05000280/2024002 and 05000281/2024002 ML24158A3882024-07-31031 July 2024 Issuance of Amendment No. 226 to Change Emergency Plan Staff Augmentation Times and Relocate Emergency Operations Facility 05000280/LER-2024-001, Troubleshooting Initiated Unknown Turbine Trip Feature in Control System2024-07-30030 July 2024 Troubleshooting Initiated Unknown Turbine Trip Feature in Control System ML24165A2782024-07-17017 July 2024 Issuance of Amendment Nos. 318 and 318, Reclassification of Regulatory Guide 1.97 Variable for Low Head Safety Injection ML24165A1232024-07-17017 July 2024 Proposed Alternative Relief Request P-1, P-2 Inservice Testing of Residual Heat and Containment Spray Pumps (EPID l-2023-LLR-0058) ML24190A4192024-07-0808 July 2024 Inservice Testing (IST) Program for Pumps and Valves Revised Sixth IST Interval Start Date and Updated Technical Specifications References for Alternative Request V-1 ML24162A3292024-07-0505 July 2024 Letter to E Carr - V.C. Summer Unit 1 - Summary of the May 2024 Audit Regarding the Environmental Review of the Subsequent License Renewal Application ML24179A2932024-07-0101 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000395/20240112024-06-26026 June 2024 – Comprehensive Engineering Team Inspection Report 05000395/2024011 ML24185A1902024-06-25025 June 2024 Submittal of Updated Final Safety Analysis Report, Revision 24 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 ML24178A1192024-06-25025 June 2024 Update to License Amendment Request- Inverter Allowed Outage Time (AOT) Extension ML24177A1382024-06-25025 June 2024 Aging Management Audit Report- VC Summer, Unit 1 - Subsequent License Renewal Application ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24166A0622024-06-18018 June 2024 – Proposed Alternative Relief Request P-3, P-4 Inservice Testing of Boric Acid, Component Cooling Water Pumps ML24171A0152024-06-17017 June 2024 Update to Subsequent License Renewal Application (SLRA) Response to NRC Request for Additional Information Set 2 Safety Review ML24157A0542024-06-13013 June 2024 Audit Summary in Support of License Amendment Request for Proposed Reclassification of Low Head Safety Injection Flow Instrumentation Related to Regulatory Guide 1.97 ML24143A1622024-06-12012 June 2024 – Correction to Issuance of Amendment Nos. 297 and 280 and Surry Units 1 and 2, Correction to Issuance of Amendment Nos. 317 and 317, to Change Emergency Plan Staff Augmentation Times ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 2024-09-03
[Table view] |
Text
UNITED STATES ber 31, 2019
SUBJECT:
SURRY POWER STATION, UNITS 1 AND 2 - U.S. NUCLEAR REGULATORY COMMISSION SECURITY INSPECTION REPORT 05000280/2019413 AND 05000281/2019413
Dear Mr. Stoddard:
On October 3, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Surry Power Station Units 1 and 2 and discussed the results of this inspection with Mr.
R. Jones and other members of your staff. The results of this inspection are documented in the enclosed report.
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Binoy Desai, Chief Plant Support Branch Division of Reactor Safety Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37
Enclosure:
NRC IR 05000280/2019413 and 05000281/2019413
Inspection Report
Docket Nos: 05000280 and 05000281 License Nos: DPR-32 and DPR-37 Report Nos: 05000280/2019413 and 05000281/2019413 Enterprise Identifier: I-2019-413-0000 Licensee: Virginia Electric and Power Company Facility: Surry Power Station, Units 1 and 2 Location: Surry, VA Dates: September 23-October 3, 2019 Inspectors: Jon Wallo, Senior Physical Security Inspector Randy Patterson, Physical Security Inspector Jonathan Brown, Physical Security Inspector Approved by: Binoy Desai, Chief Plant Support Branch Division of Reactor Safety Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Baseline Security Inspection at Surry Power Station Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations No findings were identified.
INSPECTION SCOPE
Inspection was conducted using the appropriate portions of the inspection procedure (IP) in effect at the beginning of the inspection unless otherwise noted. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2201, Security Inspection Program for Commercial Nuclear Power Reactors. The inspector reviewed selected procedure and records and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES - BASELINE
==71130.05 - Protective Strategy Evaluation The inspectors evaluated the Protective Strategy and Security Performance Evaluation Program. The following elements were evaluated:
Protective Strategy Evaluation==
Main article: IP 71130.05
- Tier II: 02.05 (a); 02.06 (a-d), (f), (I), (j), (k), (k); 02.07 (a), (b), (c), (e)
- Tier III: 02.08; 02.09 (b), (c); 02.11
- (a) The inspectors observed the performance of a licensee conducted exercise.
EXIT MEETINGS AND DEBRIEFS
The inspectors confirmed that proprietary information was controlled to protect from public disclosure.
On October 3, 2019, the inspector presented the inspection results to Mr. R. Jones and other members of the licensee staff.
LIST OF
DOCUMENTS REVIEWED
Inspection Type Designation Description of Title Revision No.
Procedure
71130.05 Procedures SY-AA-TR-201 Security Drill and Exercise-Revision 11 11
SY-AA-TR-203 Composite Adversary Team- Revision 4 3
SY-AA-TR-202 Target Set Development and Identification- Revision 11 8
SY-AA-SCPIP-017 Waterborne Threat-Revision 0 10
SY-AA-SCPIP-004 PA & VA Intrusion Alarm Response-Revision 0 6
SY-AA-SCPIP-001 Malevolent Use of Vehicle-Revision 0 5
SY-AA-SCPIP-025 Threat of an Airborne Attack-Revision 0 4
Initial Force on Force Controller Training Lesson Plan-
Revision 0 3
Various Officer Drill & Exercise Records 4
17-1078406 19-1124558
Condition 18-1100667 19-1132375
Reports 18-1104415 18-1105469
18-1104417 18-1105858
18-1104428 18-1107770
18-1105467 19-1125762
19-1114545
3