05-19-2016 | On March 21, 2016, at 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />, with Unit 2 shutdown for refuel outage Q2R23, the as-found local leak rate tests ( LLRT) for the four (4) main steam lines ( MSL) were performed following closure of the main steam isolation valves ( MSIV). The initial as-found LLRT on the "A" and "C" MSL MSIVs exceeded the minimum pathway criteria (lesser leakage in a line) of the Technical Specifications (TS), and the combined total leakage of all MSLs also exceeded the minimum pathway criteria (lesser leakage in each line when combined for all MSIVs) of the TS.
Corrective actions included flushing, disassembling, inspecting, repairing, and retesting the valves. Future corrective actions include installation of an improved spherical nose plug design to the MSIV plug and seat, and installation of an anti-rotation device to the MSIV pilot.
Valves 2-0203-2A and 2-0203-1C were disassembled and inspected. The most likely cause for the higher than expected leakages has been determined to be a valve design that is susceptible to a degraded main plug / seat interface during valve closure. A contributing cause was susceptible pilot plug / seat misalignment, due to pilot disc stem nut wear.
The safety significance of this event was minimal. The total primary containment leakage of 315.866 scfh was well within the allowed leakage limit of 1372.99 scfh (La). However, since the "A", "B", "C" and "D" MSL MSIV as-found leakage exceeded the TS limit, and the combined total leakage of all MSLs exceeded the TS limit, this report is submitted in accordance with the requirements of 10 CFR 50.73(a)(2)(i)(B), which requires the reporting of a past operation or condition which was prohibited by the plant Technical Specifications. |
---|
|
---|
Category:Letter
MONTHYEARIR 05000254/20240112024-11-13013 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000254/2024011 and 05000265/2024011 IR 05000254/20240032024-11-12012 November 2024 Integrated Inspection Report 05000254/2024003, 05000265/2024003 and 07200053/2024001 ML24317A1432024-11-0404 November 2024 Constellation Energy Generation, LLC, 2024 Annual Report - Guarantees of Payment of Deferred Premiums RS-24-101, License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair2024-11-0404 November 2024 License Amendment Request for One-Time Extension of Standby Gas Treatment System Technical Specifications Completion Time to Support Piping Repair RS-24-126, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4)2024-10-31031 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in Accordance with 10 CFR 2.390(b)(4) 05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure SVP-24-065, Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor2024-10-29029 October 2024 Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report 2024-09-04
[Table view] Category:Licensee Event Report (LER)
MONTHYEAR05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing 05000265/LER-2023-001-01, Turbine Trip and Automatic Reactor Scram Due to High Moisture Separator Level2023-11-30030 November 2023 Turbine Trip and Automatic Reactor Scram Due to High Moisture Separator Level 05000265/LER-2023-001, Turbine Trip and Automatic Reactor Scram Due to High Moisture Separator Level2023-10-10010 October 2023 Turbine Trip and Automatic Reactor Scram Due to High Moisture Separator Level SVP-22-072, Manual Scram Due to Feedwater Regulator Valve Failure Increasing Reactor Water Level2022-12-30030 December 2022 Manual Scram Due to Feedwater Regulator Valve Failure Increasing Reactor Water Level 05000265/LER-2022-002, Manual Scram Due to Feedwater Regulator Valve Failure Decreasing Reactor Water Level2022-09-0101 September 2022 Manual Scram Due to Feedwater Regulator Valve Failure Decreasing Reactor Water Level 05000254/LER-2022-003, Both Trains of Standby Gas Treatment Inoperable Due to Blockage in the Common Discharge Line2022-09-0101 September 2022 Both Trains of Standby Gas Treatment Inoperable Due to Blockage in the Common Discharge Line 05000254/LER-2022-002, Low Pressure Coolant Injection Manually Isolated Due to Valve Test Equipment Issue2022-07-0808 July 2022 Low Pressure Coolant Injection Manually Isolated Due to Valve Test Equipment Issue 05000265/LER-2022-001, Electromatic Relief Valve 3B Did Not Actuate Due to Incorrectly Oriented Plunger Well Plastic Guides2022-05-20020 May 2022 Electromatic Relief Valve 3B Did Not Actuate Due to Incorrectly Oriented Plunger Well Plastic Guides 05000254/LER-2022-001, Regarding High Pressure Coolant Injection System Inoperable Due to Gland Seal System Malfunction2022-01-26026 January 2022 Regarding High Pressure Coolant Injection System Inoperable Due to Gland Seal System Malfunction 05000254/LER-2021-001, Automatic Actuation of Emergency Diesel Generator Due to Transformer Maintenance2021-05-18018 May 2021 Automatic Actuation of Emergency Diesel Generator Due to Transformer Maintenance 05000254/LER-2020-002, Main Steam Line Drain Valve Declared Inoperable Due to Improper Torque Switch Setting2020-11-10010 November 2020 Main Steam Line Drain Valve Declared Inoperable Due to Improper Torque Switch Setting 05000265/LER-2020-003, Oscillation Power Range Monitors (Oprms) Count Setpoint Discrepancy Due to Inadequate Instructions2020-09-17017 September 2020 Oscillation Power Range Monitors (Oprms) Count Setpoint Discrepancy Due to Inadequate Instructions 05000265/LER-2020-002, Electromatic Relief Valve 3D Did Not Actuate Due to Out of Specification Plunger2020-05-28028 May 2020 Electromatic Relief Valve 3D Did Not Actuate Due to Out of Specification Plunger 05000265/LER-2020-001, Loss of Both Divisions of Residual Heat Removal Low Pressure Coolant Injection Due to Swing Bus Failure to Transfer2020-05-19019 May 2020 Loss of Both Divisions of Residual Heat Removal Low Pressure Coolant Injection Due to Swing Bus Failure to Transfer 05000254/LER-2017-0042018-01-0505 January 2018 Unit 1 HPCI Did Not Trip Due to Wear Debris in the Turbine Stop Valve Oil Resetting Solenoid, LER 17-004-00 For Quad Cities Nuclear Power Station, Unit 1 re: Unit 1 HPCI Did Not Trip Due to Wear Debris in the Turbine Stop Valve Oil Resetting Solenoid 05000254/LER-2017-0032017-11-17017 November 2017 Control Room Emergency Ventilation Air Conditioning Piping Refrigerant Leak Due to High Cycle Fatigue, LER 17-003-00 for Quad Cities, Unit 1, Regarding Control Room Emergency Ventilation Air Conditioning Piping Refrigerant Leak Due to High Cycle Fatigue 05000265/LER-2017-0012017-07-13013 July 2017 High Pressure Coolant Injection Minimum Flow Valve Failed to Open, LER 17-001-00 for Quad Cities, Unit 2, Regarding High Pressure Coolant Injection Minimum Flow Valve Failed to Open 05000254/LER-2017-0022017-05-26026 May 2017 Four Main Steam Isolation Valves (MSIVs) Closure Times Exceeded, LER 17-002-00 for Quad Cities, Unit 1, Regarding Four Main Steam Isolation Valves (MSIVs) Closure Times Exceeded 05000254/LER-2017-0012017-03-22022 March 2017 Secondary Containment Interlock Doors Opened Simultaneously, LER 17-001-00 for Quad Cities, Unit 1, Regarding Secondary Containment Interlock Doors Opened Simultaneously 05000265/LER-2016-0022016-06-24024 June 2016 High Pressure Coolant Injection System Declared Inoperable Due to Valve Packing Leak, LER 16-002-00 for Quad Cities Nuclear Power Station Unit 2 - RE: High Pressure Coolant Injection System Declared Inoperable Due to Valve Packing Leak 05000265/LER-2016-0012016-05-19019 May 2016 Main Steam Isolation Valve Local Leak Rate Tests Exceed Technical Specification Limits, LER 2016-001-00 for Quad Cities Nuclear Power Station, Unit 2 Regarding Main Steam Isolation Valve Local Leak Rate Tests Exceed Technical Specification Limits 05000254/LER-2016-0022016-03-14014 March 2016 Secondary Containment Differential Pressure Momentarily Lost Due to Air Line Failure (RWCU Pump Rm), LER 16-002-00 for Quad Cities Units 1 and 2, Regarding Secondary Containment Different Pressure Momentarily Lost due to Air Failure (RWCU pump Rm) 05000254/LER-2016-0012016-03-10010 March 2016 Secondary Containment Differential Pressure Momentarily Lost Due to Air Line Failure (RWCU Hx Rm), LER 16-001-00 for Quad Cities, Unit 1, Regarding Secondary Containment Differential Pressure Momentarily Lost Due to Air Line Failure (RWCU Hx Rm) 05000254/LER-2015-0102016-02-0505 February 2016 Loss of Control Room Emergency Ventilation System Due to Differential Pressure Switch Failure, LER 15-010-00 for Quad Cities, Unit 1, Regarding Loss of Control Room Emergency Ventilation System Due to Differential Pressure Switch Failure SVP-03-036, LER 03-S01-00, Security Event Report for Quad Cities, Unescorted Protected Area Access Granted Based on Falsified Information and Inadequate Screening Caused by a Failure of Administrative Controls.2003-03-0303 March 2003 LER 03-S01-00, Security Event Report for Quad Cities, Unescorted Protected Area Access Granted Based on Falsified Information and Inadequate Screening Caused by a Failure of Administrative Controls. ML17252B4771976-09-15015 September 1976 LER 76-059-00 for Dresden, Units 2 and 3 Re Review of Quad-Cities Unusual Event Letter Led to Discovery That Dresden'S Standby Gas Treatment System Deviated from Single Failure Criteria That Disabled the SBGT System ML18348A2401976-08-0606 August 1976 LER 1976-027-00, Reportable Occurrence of Control Rods for Quad-Cities, Unit 1 ML18348A2391976-08-0404 August 1976 LER 1976-026-00, Reportable Occurrence of Control Rods for Quad-Cities, Unit 1 2024-07-22
[Table view] |
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by internet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
3. LER NUMBER
2016 - 00
PLANT AND SYSTEM IDENTIFICATION
General Electric - Boiling Water Reactor, 2957 Megawatts Thermal Rated Core Power Energy Industry Identification System (EIIS) codes are identified in the text as [XX].
EVENT IDENTIFICATION
Main Steam Isolation Valve local leak rate testing resulted in two (2) MSIVs exceeding the individual Technical Specification limit and the combined minimum path MSIV leakage exceeding the Technical Specifications Limit.
A. CONDITION PRIOR TO EVENT
Unit: 2 Reactor Mode: 4 Event Date: March 21, 2016 Event Time: 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br /> Mode Name: Cold Shutdown Power Level: 0%
B. DESCRIPTION OF EVENT
On March 21, 2016, at 2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />, with Unit 2 shutdown for refuel outage Q2R23, the as-found local leak rate tests (LLRT) for the four (4) main steam [SB] lines (MSL) were performed following closure of the main steam isolation valves [ISV] (MSIV). Two (2) MSIV leakage paths; "A" MSL inboard valve 2-0203-1A (65.5 scfh) and "C" MSL outboard valve 2-0203-2C (45 scfh), when tested at 25 psig; exceeded the allowed limit for leakage as specified by Technical Specifications (TS) Surveillance Requirement (SR) 3.6.1.3.10 criteria for the as-found min path (lesser leakage in a line) criteria of 34 scfh at 25 psig. In addition, the combined total leakage of all MSLs, 118.8 scfh at 25 psig, exceeded the allowed limit for leakage as specified by TS SR 3.6.1.3.10 criteria of 5. 86 scfh at 25 psig for all MSIVs combined minimum path leakage limit (i.e., lesser leakage in each line when combined for all MSIVs).
Following the completion of the individual as-found results, the "A", "B", and "D" MSLs were flushed. On March 22, 2016, following the flushing of the MSIVs and the subsequent re-draining of the test volumes, an additional LLRT was performed on each MSL. Post-flushing LLRTs resulted in successful leakage rates on the 2-0203-1A, 2-0203-1B, and 2-0203-2D MSIVs, while the 2-0203-2A MSIV continued to show significant seat leakage. The "C" MSL was not flushed due to the decision to repair valve 2-0203-1C. Valves 2-0203-2A and 2-0203-1C were originally scoped into Q2R23 based on results from the previous Unit 2 refuel outage (Q2R22).
Valves 2-0203-2A and 2-0203-1C were disassembled and inspected, and MSIV pilot and disc stem nut wear associated with the 2-0203-2A and 2-0203-1C MSIVs was identified as causing the seat leakage. Valves 2-0203-2A and 2-0203-1C were subsequently repaired and satisfactorily retested. Valve 2-0203-2C was not worked due to a successful combined as-left LLRT, following 2-0203-1C valve repair. The as-found leakage on valve 2-0203-1C masked 2-0203-2C as-found leakage and as such, repairs to valve 2-0203-2C were not required.
Given the impact that the "A" and "C" MSL isolation valves as-found leakage exceeded the TS limit for minimum path leakage in its MSL, and the combined total leakage of all MSLs exceeded the TS limit for min-path leakage for all MSIVs, this report is submitted in accordance with the requirements of 10 CFR 50.73(a)(2)(i)(B), which requires the reporting of a past operation or condition which was prohibited by the plant Technical Specifications.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
C. CAUSE OF EVENT
Subsequent investigation determined that the apparent cause of the leakage was due to the MSIV design being susceptible to degraded main plug/seat interface during valve closure; a non-optimal valve design. The MSIVs are 20-inch, Crane-Aloyco Y-Pattern globe valves [ISV] that utilize line contact between the valve plug and the seat ring to create a leak tight seal. The line contact is formed by mismatching the angles associated with the plug seat and the seat ring. The resulting line of contact occurs along a sharp edge associated with the seat ring. As the MSIVs are stroked closed, the plug tends to drag across the sharp edge of the seat ring, which creates a potential for a degraded main plug/seat interface. With respect to the MSIV pilots, there is a tight tolerance between the pilot plug and disc stem nut, which allows for proper alignment of the pilot plug and pilot seat. Should the disc stem nut start to wear, the pilot plug will start to shift. The gap created by the disc stem nut wear can allow the pilot to move freely, causing a potential for pilot plug/seat misalignment. When the MSIV pilot closes, without proper alignment with its seat, a potential leakage path develops. This was determined to be a contributing cause.
This apparent cause was previously identified (see LER 265/2012-001-00), and corrective actions to modify the MSIV valve plugs continue to be implemented.
Since MSIVs 2-0203-1A and 2-0203-2C failed their as-found LLRTs, and the combined minimum path leakage rate also failed; and the failures were due to a degraded main plug/seat interface and pilot disc stem nut wear, the extent of condition of this event is limited to these two failure mechanisms of the MSIVs.
The extent of cause is the MSIVs incorporate a non-optimal valve design that allows the plug to become misaligned with the seat ring during closure, and pilot disc stem nut wear. Since this cause is identified by failed or degraded LLRT results of susceptible MSIVs, the corrective actions identified from the apparent cause adequately address this issue.
D. SAFETY ANALYSIS
System Design The design of the MSIVs is to prevent reactor coolant [AD] inventory loss and protect plant personnel in the event of steam line breakage outside the isolation valves, and to complete the containment boundary after a Loss of Coolant Accident (LOCA). The MSIVs are 20-inch air/spring-operated, balanced "Y"-type globe valves mounted inboard and outboard of the containment. The inboard valve air is supplied from the containment drywell pneumatic system. The outboard valve is supplied by the normal instrument air system. This valve combines a full port design with straight- line flow to provide a very good flow pattern. These valves use upstream pressure to aid in closure by tilting the actuator toward the upstream side of the valve.
For lines that extend the primary containment boundary, the boundary includes the piping to the last (i.e., outboard) isolation valve. A primary containment pathway must be capable of being isolated and as such is tested in accordance with the Primary Containment Leakage Rate Program. Penetration leak rate testing verifies the capability of the penetrations to maintain overall containment leakage (La) within the limits established by 10 CFR 50 Appendix J. Technical Specification 3.6.1.3 provides the operability requirements for primary containment isolation valves.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
Safety Impact Two (2) MSIV leakage paths "A" MSL inboard valve 2-0203-1A (65.5 scfh) and "C" MSL outboard valve 2-0203-2C (45 scfh), exceeded the allowed limit for leakage as specified by TS SR 3.6.1.3.10 criteria for the as-found minimum path criteria of 5 34 scfh at ?. 25 psig. In addition, the combined leakage of all MSLs, 118.8 scfh at 25 psig, exceeded the allowed limit for leakage as specified by TS SR 3.6.1.3.10 criteria of 5 86 scfh at 25 psig for all MSIVs combined min-path leakage limit (i.e., lesser leakage in each line when combined for all MSIVs). The combined leakage of all main steam lines was 190.436 scfh (calculated at 43.9 psig current accident pressure).
The safety significance of this condition was minimal. The overall Q2R23 primary containment as-found leakage (MSIVs plus all other leak pathways) was 315.866 scfh (calculated at 43.9 psig current accident pressure). The TS allowable limit (0.6 La) for overall Unit 2 primary containment leakage is 823.79 scfh (at 43.9 psig, combined max path limit, allowed as-left), where La is 1372.99 scfh at 43.9 psig. The total primary containment leakage of 315.866 scfh was well within the allowed leakage limit of 1372.99 scfh. Therefore, the safety significance of the "A" and "C" MSLs leakage contribution and the total combined MSL contribution to the overall primary containment leakage was minimal.
This condition has been compared to Updated Final Safety Analysis Report (UFSAR) Section 15.6.5.5.1 (Application of Alternative Source Term Methodology) assumptions, which includes a single failure of an inboard MSIV. Even if a single failure was considered during this condition, a single failure of the inboard MSIV in the line with the worst leakage outboard MSIV (158.70 scfh at 43.9 psig), would result in only a 17% increase in overall containment leakage (315.866 scfh increase to 369.59 scfh), which is still well below the La (1372.99 scfh) overall TS containment leakage criteria.
Risk Insights Considering the impact of this condition on the Plant Probabilistic Risk Assessment (PRA), less than a 5% increase in risk would occur and would therefore have a negligible quantitative impact on the calculated Core Damage Frequency (CDF) and Large Early Release Frequency (LERF).
Since the MSIVs were not required to be operable or available at the time of discovery, this condition did not create any actual plant or safety consequences since the Unit was not in an accident or transient condition requiring use of MSL isolation during this period of time.
In conclusion, the safety significance of this event was minimal. Although this "A" and "C" MSIV line/path leak rate exceeded the as-found TS limit, and the combined MSIV min-path leak rate TS limit was exceeded, the overall containment leakage was maintained within limits. The total as-found leakage was 315.866 scfh at 43.9 psig, which is within La (1372.99 scfh) for overall Unit 2 primary containment leakage.
E. CORRECTIVE ACTIONS
Immediate:
1. Flushed "A", "B", and "D" MSL isolation Valves.
2. 2-0203-1A, 2-0203-1B, and 2-0203-2D maintenance flush LLRTs were satisfactory.
3. 2-0203-2A and 2-0203-1C were repaired during Q2R23. Each of these valves were disassembled, inspected, repaired, and satisfactorily retested.
comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
3. LER NUMBER
2016 - 00 Follow-up:
1. The MSIV plugs have been re-designed to move the plug/seat ring contact interface away from the sharp edge on the seat ring. The new spherical plug modification design incorporates a spherical leading edge that also provides a wider band of contact with the seat ring and is more tolerant of minor misalignment that may occur during closure. This modification has been incorporated into procedure QCMM 0203-53 "Main Steam Isolation Valve Overhaul", which allows installation of the new design during subsequent MSIV overhauls, and will achieve more reliable valve performance. The new design has already been installed on each Unit (Valve 1- 0203-1C on Unit 1 and Valves 2-0203-1C and 2-0203-1D on Unit 2) but the MSIV modification is currently limited until experience shows the design is effective.
2. Add anti-rotation device to MSIV pilot plug.
F. PREVIOUS OCCURRENCES
The station events database, LERs, and INPO Consolidated Event System (ICES) were reviewed for similar events at Quad Cities Nuclear Power Station. This event was the initial as-found combined LLRT of all main steam lines exceeded the combined min-path leakage limit (i.e., lesser leakage in each line when combined for all MSIVs) of the TS Surveillance (86 scfh); and the initial as-found LLRT on the "A" and "C" MSL inboard and outboard isolation valves exceeded the minimum pathway criteria (lesser leakage in a line) of the TS Surveillance (34 scfh). Based on the conditions of this event, causes, and associated corrective actions, the events listed below, although similar in topic, are not considered significant station experiences that would have directly contributed to preventing this event.
- Station Events Database — Previous LLRT failure investigations have been performed at Quad Cities [Root Cause 36958 (2000 LER), Equipment Apparent Cause Evaluation 130565 (2003), Common Cause Analysis 203885 (2004), and Apparent Cause Evaluation 747103 (2008)] that have concluded that ineffective guidance of the MSIV plug (an inherent design flaw) causes the seats to experience localized, accelerated wear as the plug drags across the sealing edge of the seat. There have been several cases where individual MSIVs have exceeded the acceptable leakage limits, however, between 2001 and 2012 the min-path leakage in these cases was within the TS values. Actions have been taken to minimize the number of valve strokes, modify seat and plug angles to improve the seating interface, and to eliminate closure of the MSIVs when MSL steam pressure is above 0 psig.
To mitigate the overall design issue, the MSIV internals are currently being upgraded to improve the guidance of the plug (radius nose plug design). This design issue was identified in 2004 and 2012 (see 2012 LER below), and the resulting actions, although still in process of being implemented, are further addressed in this LER.
- LER 265/2012-001-00, 05/18/12, Main Steam Isolation Valve Local Leak Rate Testing Exceeds Technical Specifications Limits (03/19/12) - The initial as-found LLRT on the "B" MSL MSIVs exceeded the minimum pathway criteria (lesser leakage in a line) of the Technical Specification (TS) Surveillance (34 standard cubic feet/hour (scfh)). The apparent cause of the higher than expected leakage was determined to be a valve design that allowed for minor seat ring wear to degrade the LLRT performance which may also have resulted in misalignment between the plug and the seat ring. Corrective actions included repairing the valves. Future corrective actions included pursuing a new plug and seat design, as well as improved trending methodology for predicting MSIV LLRT failures. This 2012 design issue and the resulting actions, although still in process of being implemented, are further addressed in this LER.
- LER 254/2015-003-00, 04/29/15, Main Steam Isolation Valve Local Leak Rate Testing Exceeds Technical Specifications Limits (03/02/15) - The initial as-found LLRT on the "D" MSL MSIVs exceeded the minimum pathway criteria (lesser leakage in a line) of the Technical Specification (TS) Surveillance (34 standard cubic feet/hour (scfh)) and the combined total leakage of all MSLs also exceeded the minimum pathway criteria (smaller leakage in each line when combined for all MSIVs) of the Technical Specifications. The apparent cause of the higher than expected leakage was determined to be a valve design that allowed for minor seat ring wear to comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by intemet e-mail to used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.
3. LER NUMBER
2016 - 00 degrade the LLRT performance which may also have resulted in misalignment between the plug and the seat ring. Corrective actions included repairing the valves. Future corrective actions included pursuing a new plug and seat design, as well as improved trending methodology for predicting MSIV LLRT failures. This 2015 design issue and the resulting actions, although still in process of being implemented, are further addressed in this LER.
G. COMPONENT FAILURE DATA
Failed Equipment: MSIVs (inboard - 2-0302-1A, outboard - 2-0302-2A, inboard - 2-0302-1B, inboard - 2-0203-1C, outboard - 2-0203-2C, and outboard - 2-0203-2D) Component Manufacturer: Crane Nuclear, Inc.
Component Model Number: Model 20-inch "Y"-Pattern Globe Valve Component Part Number: N/A This event has been reported to ICES as Failure Report No. 322335, Main Steam Isolation Valves Exceeded the Technical Specifications for As-found Local Leak Rate Testing.