Summary of Conference Call Between Us Nuclear Regulatory Commission and Firstenergy Nuclear Operating Company, Concerning the Impact of Table 8.0-1 Error on the Beaver Valley Severe Accident Mitigation Alternatives Request for Additional In
ML080730116
Person / Time
Site: Beaver Valley  FirstEnergy icon.png
Issue date: 03/21/2008
From: Kent Howard
NRC/NRR/ADRO/DLR
To:
Howard K, NRR/DLR/RLRB, 415-2989
References
Download: ML080730116 (7)


Text

March 21, 2008 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MARCH 03, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE IMPACT OF TABLE 8.0-1 ERROR ON THE BEAVER VALLEY SEVERE ACCIDENT MITIGATION ALTERNATIVES REQUEST FOR ADDITIONAL INFORMATION RESPONSE PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6595 AND MD6596)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on March 03, 2008, to discuss the Impact of Severe Accident Mitigation Alternatives (SAMA) Table 8.0-1 error on the SAMA request for additional information (RAI) response, concerning the Beaver Valley Power Station Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants. Enclosure 2 is a summary of the discussion between FENOC and the NRC staff.

If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard, at 301-415-2989 or KLH1@nrc.gov.

Sincerely,

\RA\

Kent Howard License Renewal Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

As stated

LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Beaver Valley Power Station, Units 1 and 2

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MARCH 03, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE IMPACT OF TABLE 8.0-1 ERROR ON THE BEAVER VALLEY SEVERE ACCIDENT MITIGATION ALTERNATIVES REQUEST FOR ADDITIONAL INFORMATION RESPONSE PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MD6595 AND MD6596)

The U.S. Nuclear Regulatory Commission (NRC or the staff) and representatives of FirstEnergy Nuclear Operating Company (FENOC) held a telephone conference call on March 03, 2008, to discuss the Impact of Severe Accident Mitigation Alternatives (SAMA) Table 8.0-1 error on the SAMA request for additional information (RAI) response, concerning the Beaver Valley Power Station Units 1 and 2, license renewal application. Enclosure 1 is a list of the conference call participants.

Enclosure 2 is a summary of the discussion between FENOC and the NRC staff.

If you have any questions concerning the NRC staffs summary of this telephone conference, please contact Mr. Kent Howard, at 301-415-2989 or KLH1@nrc.gov.

Sincerely,

\RA\

Kent Howard License Renewal Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-334 and 50-412

Enclosures:

As stated Docket Nos. 50-334 and 50-412

Enclosures:

As stated DISTRIBUTION: See next page Adam Accession Nos: ML080730116 OFFICE: LA:DLR PM:DLR:RPB2 PM:DLR:RPB2 BC: DLR:RPB2 NAME: IKing ESayoc w/comment KHoward RFranovich DATE: 3/19/08 3/19/08 3/20/08 3/21/08 OFFICIAL RECORD COPY

LIST OF PARTICIPANTS FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION March 03, 2008 PARTICIPANTS AFFILIATIONS Emmanuel Sayoc U.S. Nuclear Regulatory Commission Cliff Custer FirstEnergy Nuclear Operating Company (FENOC)

Steve Dort FENOC Glenn Ritz FENOC Jeff Jeffries FENOC ENCLOSURE 1

SUMMARY

FOR THE TELEPHONE CONFERENCE CALL FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION March 03, 2008 In this telephone conference call, the U.S. Nuclear Regulatory Commission (the NRC or staff) and representatives from FirstEnergy Nuclear Operating Company (FENOC) discussed the error that was discovered in calculated Upper Bound Benefit (Benefit at UB) in Table 8.0-1, which provides the results of the Beaver Valley Power Station severe accident mitigation alternatives (SAMA) sensitivity evaluation for Units 1 and 2.

FENOC explained that they were notified on Friday, February 29, 2008, that this error existed.

The on-site core damage frequency (CDF) contribution was inadvertently omitted from the calculation, and correcting the calculation for this error increased the Upper Bound Benefit value by some 5-10% (generally) for Unit 1. A row by row review was performed for Table 8.0-1 (page C.1-122), and this review validated the fact that none of the SAMA conclusions were affected, i.e., the results of the evaluations remain the same.

Furthermore, FENOC explained that during the initial review of the sensitivity analysis problem, it was also noted that the CDF95/CDF ratio for Unit 1 had been inadvertently used for the Unit 2 calculation; this had the effect of actually lowering the Benefit at UB for Unit 2 by some 10-15%

(generally). Again, the results of the SAMA evaluations did not change.

FENOC articulated that because the specific problems of the sensitivity analysis were initially not well-defined, they placed request for additional information (RAI) development on-hold until the details and potential overall impact could be determined. FENOC believes that the problem has been adequately characterized and they requested a two-day delay in their previous commitment for providing responses to the RAI, i.e., from March 5, 2008, until March 7, 2008.

NRC staff deemed this to be acceptable.

FENOC agreed to correct Table 8.0-1 for both units by submitting errata to the Environmental Report by March 18, 2008. FENOC also stated that a condition report would be generated to document this occurrence within the corrective action program.

ENCLOSURE 2

Letter to FirstEnergy from K. Howard dated March 21, 2008

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL HELD ON MARCH 03, 2008, BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION AND FIRSTENERGY NUCLEAR OPERATING COMPANY, CONCERNING THE IMPACT OF TABLE 8.0-1 ERROR ON THE BEAVER VALLEY SEVERE ACCIDENT MITIGATION ALTERNATIVES REQUEST FOR ADDITIONAL INFORMATION RESPONSE PERTAINING TO THE REFURBISHMENT ACTIVITIES AT THE BEAVER VALLEY POWER STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSbwb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter KHoward ESayoc PBuckberg NMorgan MModes, RI PCataldo, RI DWerkheiser, RI

Beaver Valley Power Station, Units 1 and 2 cc:

Joseph J. Hagan Ohio EPA-DERR President and Chief Nuclear Officer ATTN: Zack A. Clayton FirstEnergy Nuclear Operating P.O. Box 1049 Company Columbus, OH 43266-0149 Mail Stop A-GO-19 76 South Main Street Director, Fleet Regulatory Affairs Akron, OH 44308 FirstEnergy Nuclear Operating Company James H. Lash Mail Stop A-GO-2 Senior Vice President of Operations 76 South Main Street and Chief Operating Officer Akron, OH 44308 FirstEnergy Nuclear Operating Company Manager, Site Regulatory Compliance Mail Stop A-GO-14 FirstEnergy Nuclear Operating 76 South Main Street Company Akron, OH 44308 Beaver Valley Power Station Mail Stop A-BV-A Danny L. Pace P.O. Box 4, Route 168 Senior Vice President, Shippingport, PA 15077 Fleet Engineering FirstEnergy Nuclear Operating Commissioner James R. Lewis Company West Virginia Division of Labor Mail Stop A-GO-14 749-B, Building No. 6 76 South Main Street Capitol Complex Akron, OH 44308 Charleston, WV 25305 Jeannie M. Rinckel Director, Utilities Department Vice President, Fleet Oversight Public Utilities Commission FirstEnergy Nuclear Operating 180 East Broad Street Company Columbus, OH 43266-0573 Mail Stop A-GO-14 76 South Main Street Director, Pennsylvania Emergency Akron, OH 44308 Management Agency 2605 Interstate Drive David W. Jenkins, Attorney Harrisburg, PA 17110-9364 FirstEnergy Nuclear Operating Company Dr. Judith Johnsrud Mail Stop A-GO-15 Environmental Coalition on Nuclear 76 South Main Street Power Akron, OH 44308 Sierra Club 433 Orlando Avenue State College, PA 16803

Beaver Valley Power Station, Units 1 and 2 cc:

Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 Cliff Custer FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Mike Banko FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Julie Firestone FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077