Issue date | Title | Topic | |
---|---|---|---|
ML20217D403 | 6 October 1999 | Summarizes Series of Four Revs That Have Been Made to SNEC Emergency Response Procedure & Emergency Plan Since 970408. Revs Include Changes to Reflect Current Site Conditions & Changes in Organizational Structure | |
ML20216J981 | 4 October 1999 | Forwards Insp Rept 50-146/99-202 on 990830-0902.No Violations Noted.Insp Consisted of Selective Exams of Procedures & Representative Records,Interviews with Personnel & Observations of Activities in Progress | |
ML20209B997 | 29 June 1999 | Forwards 1998 Annual Rept for Saxton Nuclear Experimental Corp (Snec).Rept Covers Period Beginning 980101-981231 | |
ML20195E013 | 3 June 1999 | Provides Encl Info as Evidence of Jcp&L,Meed & Penelec Commitment to Assure Continued Financial Support of Decommissioning Efforts of SNEC | |
ML20206G634 | 3 May 1999 | Requests Info on How SNEC Will Show Compliance with Requirements in 10CFR50.75 on How SNEC Will Provide Reasonable Assurance That Funds Will Be Available for Completion of Decommissioning Process for Plant | |
ML20206F645 | 29 April 1999 | Forwards 1998 Annual Radioactive Release Rept for SNEC & Rev 0 to Odcm. Explanations of Attachments 1-9,listed | Offsite Dose Calculation Manual Process Control Program |
ML20206D121 | 27 April 1999 | Informs of Completion of Acceptance Review of Saxton Nuclear Experimental Facility License Termination Plan Submitted on 990203.Concludes That LTP Does Not Contain Sufficient Info at Present Time to Initiate Detailed Review | |
ML20206G035 | 27 April 1999 | Forwards Proprietary 10CFR20.2206(b) Personnel Exposure Rept for Saxton Nuclear Experimental Corp.Rept Contains Info Required to Identify Total Number of Individuals for Whom Personnel Monitoring Was Required.Proprietary Info Withheld | |
ML20205H108 | 31 March 1999 | Forwards Current Funding Status for Decommissioning Funds Established for OCNPP,TMI-1,TMI-2 & SNEC | |
ML20204H785 | 22 March 1999 | Forwards Insp Rept 50-146/99-201 on 990216-18.No Violations Noted.Nrc Questionnaire Re Yr 2000 Concerns Encl | |
ML20198A403 | 10 December 1998 | Forwards Insp Rept 50-146/98-204 on 981013-1106.No Violations Noted.No Response to Ltr Required | |
ML20154K118 | 13 October 1998 | Forwards Insp Rept 50-146/98-203 on 980914-17.No Violations Noted | |
ML20153C424 | 21 September 1998 | Responds to Requesting NRC Review Aspects of 980624 Application from Saxton Nuclear Experimental Corp & Gpu Nuclear,Inc for Regulatory Relief from DOT Shipping Requirements.Srvts Should Be Classified as LSA-III | |
ML20237D995 | 24 August 1998 | Informs That Staff Does Not Object to Blending of Guide Blocks to Lower Core Plate & Determined That Guide Blocks & Plate Permanently Connected | |
ML20236N889 | 24 June 1998 | Submits Two Complete Copies of Gpu Nuclear'S Requests for Exemptions,Re Shipment of Sg,Pressurizer & Reactor Vessel. Detailed Exemption Requests & Supporting Documentation Are Provided in Enclosed Attachments | Coatings Exemption Request |
ML20249A239 | 11 June 1998 | Corrects 980420 Safety Evaluation for Amend 15 to License DPR-04 & 980409 EA & Finding of No Significant Impact.Ea Section 3.2.2 Does Rate Should Be Changed to 200 Msv Per H | Boric Acid |
ML20249A690 | 11 June 1998 | Forwards Insp Rept 50-146/98-202 on 980511-13.No Violations Noted | |
ML20248D698 | 28 May 1998 | Forwards Annual Rept & Radiological Environ Monitoring Rept for 970101-1231 for Saxton Nuclear Experimental Corp | |
ML20216B644 | 8 May 1998 | Forwards Request for Addl Info Re Saxton Nuclear Experimental Facility.Various Facility Components Will Be Shipped off-site for Disposal as Radwaste | |
ML20217A964 | 20 April 1998 | Forwards Amend 15 to License DPR-4 & Safety Evaluation. Amend Allows Decommissioning of Saxton Nuclear Experimental Corp Facility | Offsite Dose Calculation Manual Process Control Program |
ML20217H223 | 17 April 1998 | Forwards Personnel Exposure Rept for Saxton Nuclear Experimental Corp for Calendar Year 1997.W/o Encl | |
ML20216D061 | 9 April 1998 | Forwards Environ Assessment & Finding of No Significant Impact & Being Sent to Office of Federal Register for Publication.Concludes That No Significant Environ Impact Attributable to Proposed Action | |
ML20217P770 | 31 March 1998 | Provides Results of Calculations Performed to Evaluate Dose to Public to Be Expected from Hypothetical Spill of Tritiated Water Being Stored in SNEC Facility Containment Vessel.Scenarios Found to Have No Significant Public Health | |
ML20217P418 | 3 March 1998 | Provides Response to Question 7 of RAI Dtd 980128.Response Will Be Incorporated as Suppl 1 to Facility Decommissioning Environ Rept | |
ML20203A577 | 9 February 1998 | Forwards RAI Re Amend Request for License DPR-4 Submitted 981125.Response Requested to Be Provided within 30 Days of Date of Ltr | |
ML20202F696 | 9 February 1998 | Provides Response to Questions Re Apparent Undocumented Changes to Saxton Nuclear Experimental Corp Decommissioning QA Plan | |
ML20202B235 | 3 February 1998 | Responds to 980128 RAI Re TS Change Request 59.Response Includes Proposed Revised Pages to Facility License,Ts, Updated Sar,Decommissioning QA Plan & Figures to Post Shutdown Activities Rept.W/Certificate of Svc | |
ML20199F232 | 27 January 1998 | Forwards Request for Addl Info Re Amend to License DPR-4. Responses Requested to Be Provided within 30 Days of Dtd Ltr | |
ML20217J775 | 9 October 1997 | Submits Reply to Discussing Decommissioning Activities at Facility.Decommissioning Requested to Be Delayed for 25 Yrs to Allow for Addl Radioactive Decay | |
ML20211C237 | 16 September 1997 | Forwards Rev 0 to Procedure 6575-PLN-4542.09, SNEC Facility Process Control Program, for Review & Approval.Activities Will Be Initiated Starting W/Item 1.2.2.3 of Figure 2.2-4 of Decommissioning Plan When Approval of Tscr 59 Is Obtained | Process Control Program |
ML20210Q221 | 21 August 1997 | Forwards Response to Requests for Addl Info & 0806.Info Suppls Previous Responses to Questions,Addresses Recent Questions on ODCM & Incorporates Editorial Comments Commited by Telcon.Revised TS & Updated SAR Encl | Process Control Program |
ML20217H429 | 6 August 1997 | Forwards RAI Re Amend Request for License DPR-4.Reply Requested within 30 Days of Dtd Ltr | Offsite Dose Calculation Manual Process Control Program Backfit |
ML20217G927 | 5 August 1997 | Informs That Responsibility for Non-Power Reactor Insp Program Has Been Transfered from Regional Ofc to Nrr.All Activities Re Non-Power Reactors Including Licensing,Insp & Operator Licensing Will Be Responsibility of NRR | |
ML20141C654 | 16 June 1997 | Clarifies Statements in Safety Insp Rept 50-146/97-01 for Saxton Nuclear Experimental Corp Facility,That Do Not Reflect Utils Practices or Intentions | Offsite Dose Calculation Manual |
ML20141C400 | 16 June 1997 | Forwards Procedure 6575-ADM-4500.06, Emergency Response Procedure & Emergency Plan, That Was Inadvertently Overlooked & Not Included as Attachment in Submittal, | |
ML20217Q587 | 11 June 1997 | Provides Concerns & Suggestions Re Gpu Decommissioning Plan | |
ML20140C127 | 30 May 1997 | Forwards Response to 970408 RAI Re TS Change Request 59 & Revised Pages to Change Request Which Includes Rev to Original Text Based Upon Response Provided | Offsite Dose Calculation Manual Process Control Program Fire Protection Program |
ML20140C926 | 30 May 1997 | Forwards Responses to 970424 RAI Re Questions Resulting from Review of SNEC Decommissioning QA Program | Incorporated by reference |
ML20138B626 | 24 April 1997 | Forwards Request for Addl Info Re Amend Request for License DPR-4.Response Requested within 30 Days of Ltr Date | |
ML20137R791 | 9 April 1997 | Forwards RAI Re Request for Amend to Facility License DPR-4 | Process Control Program Fire Protection Program |
ML20140D376 | 3 April 1997 | Forwards 10CFR20.2206(b) 1996 Personnel Exposure Rept for Snec,Containing Info Required to Identify Total Number of Individuals for Whom Personnel Monitoring Was Required & Statistical Summary of Personnel Monitoring Info.W/O Encl | |
ML20140B713 | 18 March 1997 | Forwards Insp Rept 50-146/97-01 on 970127-29.No Violations Noted | |
ML20136E204 | 6 March 1997 | Forwards Notice of Consideration of Issuance of Amend to Facility License & Proposed NSHC Determination & Opportunity for Hearing Re 961125 Request to Amend Facility License DPR-4 | Process Control Program |
ML20134K196 | 11 February 1997 | Expresses Appreciation for Participation in 970128 Public Meeting on Post-Shutdown Decommissioning Activities Rept for Facility.Transcript of Meeting Encl | |
ML20149M662 | 22 January 1997 | Forwards Copy of Notice That Appeared in 961219 Federal Register Re Public Meeting on post-shutdown Decommissioning Activities Rept for SNEC Facility & Agenda for Meeting | |
ML20133N400 | 21 January 1997 | Informs That NRC Planning to Hold Public Meeting on post- Shutdown Decommissioning Activities Rept for SNEC Facility in Sexton,Pa on 970128 | |
ML20133P938 | 21 January 1997 | Forwards Insp Rept 50-146/96-01 on 961119-21.No Violations Noted | |
ML20133E112 | 8 January 1997 | Informs That NRC Planning to Hold Public Meeting on post- Shutdown Decommissioning Activities Rept for SNEC Facility on 970128 | |
ML20134P335 | 25 November 1996 | Forwards TS Change Request 59,submitting Decommissioning TSs | |
ML20134L731 | 8 November 1996 | Submits site-specific Cost Estimate for Saxton Nuclear Experimental Corp Facility as Required by 10CFR50.82(a)(8)(ii) & Satisfies Commitment to Have an Approved Quality Assurance Plan,Per 10CFR71.101 |