2CAN029407, Submits 1993 Annual Rept of Steam Generator Tube Isis,Per TS 4.4.5.5.b & 6.9.1.5.b

From kanterella
(Redirected from ML20064H202)
Jump to navigation Jump to search
Submits 1993 Annual Rept of Steam Generator Tube Isis,Per TS 4.4.5.5.b & 6.9.1.5.b
ML20064H202
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 02/23/1994
From: Mims D
ENTERGY OPERATIONS, INC.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
2CAN029407, 2CAN29407, NUDOCS 9403170201
Download: ML20064H202 (2)


Text

.* = EntaU e#i rev oa=<=iioa=. ia=-

Operations-Lw a- %m=

w smam ma L-.__.-_.___..___ _ - . _ _ _ _ _ _ _

February 23,1994 2CAN029407 U. S. Nuclear Regulatory Commission Document Control Desk Mail Station PI-137 Washington, DC 20555 jl

Subject:

Arkansas Nuclear One - Unit 2 Docket No. 50-368 License No. NPF-6 1993 Annual Report Of Steam Generator Tube Inservice Inspections Gentlemen:

The Arkansas Nuclear One, Unit 2 (ANO-2) Technical Specifications 4.4.5.5.b and 6.9.1.5.b require that complete results of all ANO-2 steam generator tube inservice inspections (ISI)  !

performed during the report period be submitted to the NRC on an annual basis. Except for the inspection of two tubes which were not examined during the last refueling outage conducted in 1992 (2R9), no inservice inspections of the steam generators were conducted in 1993. Ilowever, a non-ISI inspection of the steam generator tubes was conducted during our 1993 planned outage (2P93-1). Results of this non-ISI inspection were voluntarily transmitted by letter dated June 17,1993 (2CAN069302).

ANO-2 Technical Specification Amendment 143, dated February 23,1993 (2CNA029302), ,

added a note to Table 4.4-2 of the Technical Specifications granting a one time exemption to the C-3 inspection requirements for the 2R9 inspection of "B" steam generator tubes 38-66 and 37-67 for the period of November 27,1992, through May 30,1993. Inspection of these two tubes was not completed as part of the 100% C-3 sample inspection performed during 2R9 (see Entergy Operations letter dated November 27,1992 (2CANI19205)). The inservice inspection of these tubes was completed in conjunction with the non-ISI examinations conducted during 2P93-1. No indications were identified in these tubes as a result of this inspection.

This submittal completes the reporting requirements of ANO-2 Technical Specifications 4.4.5.5.b and 6.9.1.5.b for 1993. Should you have any questions regarding this issue, please contact me.

170037 l 94031702o1 940223 I I

()I

[DR ADOCK 05000369 h / I PDR i (l>t

U; S. NRC

"",* February 23,1994

.'+ 2CAN029407 Page .2 Very truly yours, bajWC Wld Dwight C. h1ims Director, Licensing DChif,1jd cc: Afr. Leonard J. Callan Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Rc adent Inspector Arkansas Nuclear One - ANO-1 & 2 Number 1, Nuclear Plant Road Russellville, AR 72801 Nfr. George Kalman NRR Project hianager Region IV/ANO-1 U. S. Nuclear Regulatory Commission NRR hfall Stop 13 H _3 J One White Flint North 11555 Rockville Pike Rockville, h1D 20852 Mr. Thomas W. Alexion i NRR Project hianager, Region IV/ANO-2 ,

U. S. Nuclear Regulatory Commission l NRR h1all Stop 13-11-3 1

One White Flint North 11555 Rockville Pike Rockville, AfD 20852 l

\

)

l 1

l 1