ML18153A297

From kanterella
Jump to navigation Jump to search
Discusses part-length Control Rod Drive Mechanism Housing Leakage Re Preliminary Action Plan
ML18153A297
Person / Time
Site: Surry, North Anna  Dominion icon.png
Issue date: 04/14/1998
From: Ohanlon J
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
98-171A, NUDOCS 9804210298
Download: ML18153A297 (4)


Text

e e VIRGINIA ELECTRIC AND PowER COMPANY RICHMOND, VIRGINIA 23261 April 14, 1998 U.S. Nuclear Regulatory Commission Serial No. 98-171A Attention: Document Control Desk NLOS/ETS: R4 Washington, D. C. 20555 Docket Nos. 50-338/339 50-280/281 License Nos. NPF-4/7 DPR-32/37

Dear Sir:

VIRGINIA ELECTRIC AND POWER COMPANY NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 PART-LENGTH CONTROL ROD DRIVE MECHANISM HOUSING LEAKAGE PRELIMINARY ACTION PLAN Northern States Power Company recently identified a leak in a reactor vessel head penetration at Prairie Island Nuclear Station Unit 2. After further investigation of the leak, it was determined that the leak was at a dissimilar metal weld in a part-length control rod drive mechanism (CROM) housing. Virginia Electric and Power Company has been actively involved in the Westinghouse Owners Group (WOG) activities associated with the part-length CROM housing weld failure evaluation and proposed corrective actions. The WOG's technical assessment of the dissimilar weld issue and safety assessment were provided to the NRC in a WOG letter from Mr. R. A. Newton to Mr. F. J. Miraglia (Serial No. OG-98-037), dated March 6, 1998. The WOG investigation and safety assessment have reached the following conclusions:

- the Prairie Island flaw originated from weld fabrication and was not service induced, ~, -:.

- there was no evidence of additional flaw growth during service, v nineteen part-length CRDMs have been ultrasonically examined to date with only the Prairie Island flaw being identified,

- such weld fabrication flaws are extremely unlikely to be present based on fabrication inspection criteria, A.;,-/, I *r::1---

- for a failure to occur, a significant flaw not previously identified must exist and an 05,f l abnormal load would be required to cause the flaw to fail, *

- a part-length CROM housing failure is bounded by existing safety analyses, and

- continued plant operation will not result in an increase in risk.

9804210298 980414 PDR ADOCK 05000280 P POR

Consistent with WOG recommendations, we are providing the NRC with Virginia

  • Electric and Power Company's preliminary action plan to address the part-length CROM housing dissimilar metal weld issue at both North Anna and Surry Power Stations.

Considering the current outage schedules and the industry experience gained to date on this issue, Virginia Electric and Power Company plans to take the following actions.

North Anna Unit 2 1998 Refueling Outage North Anna Unit 2 commenced a refueling outage on April 5, 1998. The current plans are to remove and cap four of the five part-length CROM housings during the refueling.

The fifth part-length CROM housing contains the reactor head vent and will be replaced with a CROM housing that has been verified fully acceptable by having had the dissimilar metal weld ultrasonically (UT) inspected. The removal and replacement activity is contingent on the availability of a qualified vendor and materials. Also, if engineering or nuclear safety concerns (e.g., design or analysis) are identified that would prevent the completion of the modification, we may revise our current action plan for Unit 2. Any change from the current action plan will be communicated to the NRC.

North Anna Unit 1 and Surry Units 1 and 2 1998/1999 Refueling Outages Until the next refueling outage for each unit, currently scheduled to begin September 13, 1998 for North Anna Unit 1, October 19, 1998 for Surry Unit 1, and April 12, 1999 for SPS Unit 2, we will be actively involved in the WOG activities associated with investigation and disposition of the CROM housing dissimilar metal weld issue. Based on the status of the WOG investigation and the industry experience subsequently gained, action plans will be developed for implementation during the next refueling outage for each unit. These action plans will be communicated to the NRC prior to the upcoming outages.

Note that, during a recently completed Surry Unit 1 maintenance outage, a "best effort" visual inspection of the visually accessible, peripheral portions of the head and penetration area was completed. The inspection did not reveal any evidence of leakage. These results were communicated to the NRC in a March 30, 1998 letter (Serial No.98-171).

Heightened Awareness to Reactor Coolant System Leakage Until a comprehensive corrective action plan (e.g., qualified inspection, replacement, or evaluation and disposition based on industry experience) can be completed, Reactor Coolant System (RCS) leakage monitoring awareness has been heightened at both North Anna and Surry. Heightened RCS leakage monitoring awareness has been accomplished through required reading by the Operations staff at both stations. The required reading identified the Prairie Island leakage event and noted that relevant parameters must be closely monitored.

In addition to these actions to heighten awareness, the following actions are already in

  • place at each station to facilitate sensitivity to RCS leakage monitoring:
  • A daily evaluation of primary system leakage is performed for each unit.
  • If an increasing trend exists in containment parameters associated with Reactor Coolant System leakage, a containment entry is made in accordance with procedure to check for visible leakage in a number of areas, including the reactor cavity/head area.

Should you have questions or require additional information, please contact us.

Very truly yours, James P. O'Hanlon Senior Vice President - Nuclear Commitments made in this letter:

1. North Anna Unit 2 - The current plans are to remove and cap four of the five part-length CROM housings during the refueling. The fifth part-length CROM housing contains the reactor head vent and will be replaced with a CROM housing that has been verified fully acceptable by having had the dissimilar metal weld ultrasonically (UT) inspected. Any change in the action plan will be communicated to the NRC.
2. Action plans will be developed for implementation during the refueling outage for each unit (North Anna Unit 1 and Surry Units 1 and 2). The action plans will be communicated to the NRC prior to the upcoming outages.

cc: United States Nuclear Regulatory Commission Region II Atlanta Federal Center 61 Forsyth Street, SW Suite 23T85 Atlanta, Georgia 30303 Mr. M. J. Morgan NRC Senior Resident Inspector North Anna Power Station Mr. R. A. Musser NRC Senior Resident Inspector Surry Power Station