© Dominion 2006 Regulatory Meeting Internal Flooding Risk Reduction Activities November 30, 2006

© 2006

© Dominion 2006 Dominion

Introduction Leslie Hartz Site Vice President

© Dominion 2006

© 2003 Dominion 3

AGENDA Introduction Leslie Hartz - Site VP Background Lori Armstrong - Director Engineering PRA History Tom Hook - Supv. PRA Modifications Lori Armstrong - Director Engineering Conclusion Leslie Hartz - Site VP

© Dominion 2006

© 2003 Dominion 4

Internal Flooding Background Lori Armstrong Director Engineering

© Dominion 2006

© 2003 Dominion 5

Background

Since 2004 numerous modifications installed reduce risk from Internal Flooding

  • Spring 2005 - Turbine Building Flooding Barrier installation
  • Fall 2005 - Safeguards Alley Level Alarms
  • 2006 - Procedure changes and outage maintenance

© Dominion 2006

© 2003 Dominion 6

Additional Flood Barriers

© Dominion 2006

© 2003 Dominion 7

© Dominion 2006

© 2003 Dominion Barrier to Safeguards Alley 8

Barrier between Turbine Building and

© 2003 Dominion the far end of Safeguards Alley 9

© 2003 Dominion Level Switch Circulating Pump Trip 10

Safeguards Alley Flood Level Indication Level switches and alarms for:

A AFW pump room B AFW pump room DG A room DG B room Bus 51/52 room Bus 61/62 room TD AFW pump room Cardox room

© Dominion 2006

© 2003 Dominion 11

Pre-modification Circulating Water Outlet Expansion Joints

© 2003 Dominion 12

Post-modification Circulating Water Outlet Expansion Joint

© 2003 Dominion 13

Risk Profile and Safety Improvements Tom Hook Supervisor PRA

© Dominion 2006

© 2003 Dominion 14

Flood Risk Contribution as of 12/2004 CDF = 7.2E-04/yr (internal events plus flooding) 95% of total CDF from flooding sequences Dominant CDF Contributors 4.0E-04 3.0E-04 2.0E-04 1.0E-04 0.0E+00 Auxiliary Turbine Safeguards Internal Building Building Alley Flooding Initiating Flooding Flooding Events

© Dominion 2006

© 2003 Dominion 15

PRA Modifications Completed in 2005 Incorporated plant modifications

  • Installed flood barriers between Turbine Building and Safeguards Alley
  • Installed flood sensors and alarms in Safeguards Alley
  • Installed circulating water pump trip on high turbine building level
  • Reduced CDF by 4.1E-4/yr Model improvements
  • Upgraded flooding models for Auxiliary Bldg and Safeguards Alley to address WOG peer review comments

© Dominion 2006

© 2003 Dominion 16

Flood Risk Contribution as of 12/2005 CDF = 3.1E-04/yr (internal events plus flooding) 92% of total CDF from flooding sequences Dominant CDF Contributors 4.0E-04 3.0E-04 2.0E-04 1.0E-04 0.0E+00 Auxiliary Turbine Safeguards Internal Building Building Alley Flooding Initiating Flooding Flooding Events

© Dominion 2006

© 2003 Dominion 17

PRA Modifications Completed in 2006 Incorporated procedure changes

  • Included new operator actions to address loss of battery room, AFW pump room or safeguards bus ventilation during safeguards flooding
  • Reduced CDF by 1.3E-4/yr

© Dominion 2006

© 2003 Dominion 18

Flooding Risk Contribution - Current CDF = 1.8E-04/yr (internal events plus flooding) 82% of total CDF from flooding sequences Dominant CDF Contributors 4.0E-04 3.0E-04 2.0E-04 1.0E-04 0.0E+00 Auxiliary Turbine Safeguards Internal Building Building Alley Flooding Initiating Flooding Flooding Events

© Dominion 2006

© 2003 Dominion 19

Current Dominant CDF Initiators 4.0E-05 3.0E-05 2.0E-05 1.0E-05 0.0E+00 SW A Fl ood SW B Spr ay RWST f l ood SW B Spr ay SW B Fl ood SW B Spr ay Tr ansi ent Loss of Steam Loss of i n Aux Bl dg on Tr ai n A i n Aux Bl dg i n Aux Bl dg i n Aux Bl dg on Tr ai n A wi th MFW Component Gener ator Of f si te 480V Swgr Basement EDG/ 4kV Avai l abl e Cool i ng Tube Power Swgr Ruptur e Note: SW pipe is seismically qualified.

© Dominion 2006

© 2003 Dominion 20

Near Term Risk Reduction Actions z Install watertight door between Auxiliary Building and Safeguards Alley z Install flood level alarms in Auxiliary Building z Relocate risk significant bottom row breakers 15206 and 16206 on 480V buses to spare higher locations z Install spray shields around service water piping in Safeguards Alley to protect 480V and 4kV switchgear from spray

© Dominion 2006

© 2003 Dominion 21

Plant Risk After Proposed Modifications CDF = 6.2E-05/yr 50% of total CDF from flooding sequences Dominant CDF Contributors 4.0E-04 3.0E-04 2.0E-04 1.0E-04 0.0E+00 Auxiliary Turbine Safeguards Internal Building Building Alley Flooding Initiating Flooding Flooding Events

© Dominion 2006

© 2003 Dominion 22

Impact of Modifications on Dominant CDF Initiators 4.0E-05 Current Post-Modification 3.0E-05 2.0E-05 1.0E-05 0.0E+00 SW A Flood in SW B Spray RWST f lood SW B Spray SW B Flood in SW B Spray Transient Loss of St eam Loss of Aux Bldg on Train A in Aux Bldg in Aux Bldg Aux Bldg on Train A wit h MFW Component Generat or Of f sit e 480V Swgr Basement EDG/ 4kV Available Cooling Tube Power Swgr Rupt ure Note: SW pipe is seismically qualified.

© Dominion 2006

© 2003 Dominion 23

Internal Events Risk Profile since 2004 Core Damage Frequency 1.0E-03 1.0E-04 1.0E-05 12/2004 12/2005 Current 5/2008 Date

© Dominion 2006

© 2003 Dominion 24

Summary Dominion committed to reduce internal flooding risk at Kewaunee z With proposed modifications, CDF will be reduced by 91% to 6.2E-5/yr z Internal flood contribution after proposed modifications will be 50% of internal events CDF

© Dominion 2006

© 2003 Dominion 25

Modifications Lori Armstrong Director Engineering

© Dominion 2006

© 2003 Dominion 26

Installation of Watertight Door Scope:

  • Installation of a watertight door between Aux Building and Safeguards Alley Proposed Schedule:
  • Door installation during next refueling outage

© Dominion 2006

© 2003 Dominion 27

Installation of Aux Building Water Level Alarms Scope:

  • Addition of Auxiliary Building water level alarms Proposed Schedule:
  • Installation of level indication 2Q07

© Dominion 2006

© 2003 Dominion 28

Raise breakers on 480V buses 52 and 62 Scope:

  • Relocate risk significant Class 1E breakers 15206, 16206 from bottom row to higher spare locations Proposed Schedule:
  • 4Q07

© Dominion 2006

© 2003 Dominion 29

Install Spray Shields on SW piping Scope:

  • Install spray shields around service water piping in Safeguards Alley Proposed Schedule:
  • 1Q08

© Dominion 2006

© 2003 Dominion 30

Summary Dominion continues to reduce internal flooding risk at Kewaunee

  • With proposed modifications, CDF will be reduced by 91% since 2004 Dominion will continue to evaluate CDF reductions at Kewaunee

© Dominion 2006

© 2003 Dominion 31

Questions