ML092600018
| ML092600018 | |
| Person / Time | |
|---|---|
| Site: | Kewaunee |
| Issue date: | 09/15/2009 |
| From: | Dominion Energy Kewaunee |
| To: | Office of Nuclear Reactor Regulation |
| Tam P | |
| Shared Package | |
| ML092600030 | List: |
| References | |
| TAC MC4691 | |
| Download: ML092600018 (51) | |
Text
GSI-191 RESOLUTION FOR KEWAUNEE POWER STATION 1
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- KEWAUNEE TELECONFERENCE PARTICIPANTS:
DOMINION:
JACK DILLICH, DIRECTOR NUCLEAR ENGINEERING MICHAEL L. MILLER, MANAGER NUCLEAR DESIGN ENGINEERING SCOTT PUTMAN, PROJECT MANAGER LORI CHRISTENSEN, MECHANICAL DESIGN ENGINEERING TOM BREENE, LICENSING TOM BREENE, LICENSING JACK GADZALA, LICENSING PERFORMANCE CONTRACTING, INC. (PCI)
JIM BLEIGH, ENGINEERED SYSTEMS MANAGER CHRIS KUDLA, CONSULTANT ALDEN RESEARCH LABORATORIES, INC. (ARL)
STU CAIN, PRESIDENT ATOMIC ENERGY OF CANADA LIMITED (AECL)
DAVID GUZONAS, PRINCIPAL SCIENTIST DAVID RHODES, PRINCIPAL ENGINEER 2
KEWAUNEE POWER STATION - GSI-191 RESOLUTION TODAYS PRESENTATIONS WILL COVER MATERIAL WE INTEND TO PROVIDE IN OUR RAI RESPONSE THE FINAL RAI RESPONSE WILL BE PREPARED, REVIEWED AND APPROVED IN ACCORDANCE WITH OUR CORRESPONDENCE PROCESS 3
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- REPLACEMENT STRAINER
- DESIGNED BY PCI
- TESTED BY PCI/AREVA/ARL 4
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- INSTALLED 2006 REFUELING OUTAGE
- STRAINER SURFACE AREA 768.7 FT2 5
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- ORIGINAL CONTAINMENT SUMP STRAINER MODULES
- 39 FT2 TOTAL SURFACE AREA (TWO MODULES COMBINED) 6
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- KEWAUNEE IS A SINGLE UNIT, 2-LOOP PWR
- 597 MWe
- NSSS BY WESTINGHOUSE
- KEWAUNEE DESIGN BASIS DEBRIS
- REFLECTIVE METAL INSULATION (RMI) ON RCS
- REFLECTIVE METAL INSULATION (RMI) ON RCS
- 40.3 FT3 TEMPMAT ON PRESSURIZER SURGE LINE PIPE SUPPORTS
- ENCASED IN STAINLESS STEEL RIVETED PANELS
- THIS DEBRIS SOURCE REPRESENTS 85% OF KEWAUNEES FIBROUS DEBRIS
- OTHER FIBER IS PIPE COVER (2.44 FT3), CABLE INSULATION, THERMOBESTOS FIBER AND LATENT FIBER
- PARTICULATE DEBRIS CONSISTS OF COATINGS, LATENT AND SMALL QUANTITY OF THERMOBESTOS 7
KEWAUNEE POWER STATION - GSI-191 RESOLUTION PRESSURIZER SURGE LINE (TEMPMAT)
TEMPMAT 8
NUKON
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- KEWAUNEE DESIGN BASIS
- DESIGN BASIS RECIRCULATION FLOW
- SINGLE TRAIN OPERATION
- 1990 GPM RHR PUMP FLOW (INCLUDES PUMP RECIRC FLOW)
- 1870 GPM THROUGH RECIRCULATION STRAINER
- RECIRCULATION STRAINER
- RECIRCULATION STRAINER
- 768.7 FT2 SURFACE AREA, 0.066 IN. PERFORATIONS
- LOW APPROACH VELOCITY 0.0056 FT/SEC @ 1920 GPM FLOW THROUGH STRAINER (1870 GPM + 50 GPM MARGIN ADDED)
- LOW APPROACH VELOCITY RESULTS IN MINIMAL TURBULENCE
- DEBRIS INTERCEPTORS INSTALLED TO PREVENT MATERIAL MOVING ALONG THE SUMP FLOOR FROM REACHING THE STRAINER 9
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- DEBRIS INTERCEPTORS 10
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
T (TIME) + 0 MIN.
START OF LOCA - START RCS INJECTION AND CONTAINMENT SPRAY T + 21 MIN.
RWST REACHES 37% SWITCHOVER LEVEL (MANUAL SWITCHOVER)
T+ 29 MIN.
RECIRCULATION BEGINS SUMP LEVEL 43.44 INCHES (MINIMUM) (40.5 IN. CONSERVATIVELY USED IN ANALYSES)
STRAINER SUBMERGED 6.19 INCHES (43.44 - 37.25 INCH STRAINER HEIGHT)
RCS INJECTION AND CONTAINMENT SPRAY CONTINUES T + 43 MIN.
RCS INJECTION FLOW ENDS, CONTAINMENT SPRAY ENDS SUMP LEVEL > 5.75 FT OF WATER LONG TERM RECIRCULATION CONTINUES (NO RECIRC SPRAY) 11
KEWAUNEE POWER STATION - GSI-191 RESOLUTION PARAMETER HEAD (FT)
COMMENT NPSH AVAILABLE 24.108 TOTAL WATER HEIGHT AT THE ONSET OF RECIRCULATION, MINUS PIPING FRICTION LOSSES [26.224 - 2.116];
USES 43.44 IN. SUMP LEVEL
AT MANUFACTURER-SPECIFIED DESIGN FLOW RATE 2000 GPM (BOUNDS DESIGN BASIS FLOW DURING RECIRCULATION)
NPSH MARGIN 16.108
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- OVERVIEW OF FLUME TESTING
2006 - STRAINER HEAD LOSS FLUME TESTS
2007 - FIBER TRANSPORT TESTS
2007 - FIBER TRANSPORT TESTS
2008 - STRAINER HEAD LOSS FLUME TESTS (LARGE SCALE FLUME) 13
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- 2006 TESTS
- ARL SMALL FLUME
- DESIGN BASIS DEBRIS LOAD
- POWDERED SODIUM ALUM SILICATE CHEM SURROGATE
- TESTED AT 2X DESIGN BASIS FLOW
- TESTED AT 2X DESIGN BASIS FLOW
- DEBRIS STIRRED IN FLUME AND OVERHEAD SPRAYS USED TO MINIMIZE SETTLING
- MAX HEAD LOSS WAS THIN BED TEST 3.79 FT OF WATER (CSHL +
DEBRIS BED LOSSES) AT 2 X DESIGN BASIS FLOW
- SIGNIFICANTLY BELOW 10 FT OF WATER ACCEPTANCE CRITERIA 14
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2006 TEST FLUME - MANUAL STIRRING 15
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- 2007 TESTS FIBER TRANSPORT TESTS ARL SMALL FLUME DEBRIS INTERCEPTOR (C8X18.75 CHANNEL) IN FLUME; 3/8 IN. GAP MODELED DEBRIS SCALED TO DEBRIS INTERCEPTOR LENGTH (9.6% OF TOTAL DEBRIS)
TESTED AT FLOW RATE EQUIV. TO CROSS SECTIONAL FLUID VELOCITY OVER SOUTH TESTED AT FLOW RATE EQUIV. TO CROSS SECTIONAL FLUID VELOCITY OVER SOUTH DEBRIS INTERCEPTOR, 0.113 FT/SEC TESTS RESULTED IN < 5% TRANSPORT OF FIBER DOWNSTREAM OF DEBRIS INTERCEPTOR NO THIN BED OCCURRED USING 12.2 FT2 STRAINER DEBRIS INTERCEPTORS IN COMBINATION WITH LOW SUMP POOL VELOCITIES AND LOW STRAINER APPROACH VELOCITY PROTECTS STRAINER FROM THIN BED 16
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2007 TEST FLUME - FIBER TRANSPORT TESTS 17 DEBRIS INTERCEPTOR FLUME INLET (UPSTREAM SIDE)
FLOW
KEWAUNEE POWER STATION - GSI-191 RESOLUTION TWO FLOW SIMULATIONS MODELED INITIAL START OF RECIRC WITH INJECTION AND RECIRC FLOW OUT THE RCS BREAK, INJECTION SPRAY, AND RECIRC SUMP FLOW LONG TERM RECIRCULATION - RCS BREAK FLOW EQUAL TO RECIRCULATION FLOW, NO SPRAY
- COMPUTATIONAL FLUID DYNAMICS (CFD) ANALYSIS MOST CONSERVATIVE SIMULATION (START OF RECIRC) USED WHEN DETERMINING DEBRIS SUBJECT TO TRANSPORT TOWARD THE STRAINER/DEBRIS INTERCEPTOR AREA PLANT CONDITION LASTS APPROX. 14 MINUTES FOR SIMPLICITY, BOTH MODELS USE 40.5 INCH SUMP WATER LEVEL MORE CONSERVATIVE THAN 43.44 IN. MIN. LEVEL AND LONG TERM SUMP LEVEL (> 5.75 FT) 18
KEWAUNEE POWER STATION - GSI-191 RESOLUTION N
19 STRAINER
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- SIMULATION AT START OF RECIRC (INJECTION & RECIRC IN PROGRESS) 20
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- SIMULATION DURING LONG TERM RECIRCULATION 21
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- 2008 STRAINER TESTS ARL LARGE SCALE FLUME ALL FINE AND SMALL DEBRIS SUBJECT TO TRANSPORT PLACED IN FLUME WCAP-16530-NP USED TO CREATE CHEMICAL SURROGATE (ALOOH)
DEBRIS INTERCEPTOR & 3/8 IN. GAP MODELED IN FLUME DEBRIS INTRODUCED FROM UPSTREAM DROP ZONE DEBRIS INTRODUCED FROM UPSTREAM DROP ZONE TOTAL HEAD LOSS (DEBRIS BED + CSHL) FOR DESIGN BASIS DEBRIS LOAD AT DESIGN BASIS FLOW RATE = 1.1 FT OF WATER TOTAL HEAD LOSS (DEBRIS BED + CSHL) FOR DESIGN BASIS DEBRIS LOAD PLUS ADDITIONAL FIBROUS, LATENT DEBRIS AND DOUBLE CHEMICAL DEBRIS CONCENTRATION FOR ADDED DEBRIS LOAD MARGIN = 3.28 FT OF WATER ALL TESTS SIGNIFICANTLY BELOW 10 FT OF WATER DESIGNATED BY KPS AS ACCEPTANCE CRITERIA 22
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2008 TESTS - LARGE SCALE FLUME TESTS 23
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- DESIGN BASIS CASE; WATER TEMP 105.8 F
- MAX HL 0.51036 + CSHL = 1.1034 FT WHEN TEMP-CORRECTED 24
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- DB CASE W/ADDL FIBER, LATENT AND 200% CHEMICALS
- WATER TEMP 116.1 F; MAX HL 1.6697 + CSHL = 3.286 FT WHEN TEMP. CORRECTED 25
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- CHEMICAL EFFECTS USING WCAP
- AREVA PREPARED A CHEMICAL PRECIPITATION ANALYSIS FOR KEWAUNEE USING WCAP-16530-NP
- PRECIPITATE IS SODIUM ALUMINUM SILICATE (NaAlSi308)
- DESIGN BASIS CASE CALCULATED 8.286 mg/L CONCENTRATION 26
KEWAUNEE POWER STATION - GSI-191 RESOLUTION CHEMICAL EFFECTS EVALUATION BY AECL
- Al RELEASE FROM SPRAYED ALUMINUM
- SHORT INJECTION SPRAY TIME (< ONE HOUR LBLOCA), NO RECIRCULATION SPRAY
- ICET TESTS SHOW VERY LITTLE Al RELEASE FOR SPRAY < 4 HOURS
- SPRAYED COUPONS IN TEST 1 (PH 10, NO TSP) GAINED A SMALL AMOUNT OF WEIGHT, SUBMERGED COUPONS LOST OVER 25%
- SEM IMAGES OF SPRAYED AL COUPONS SHOWED LITTLE CORROSION, WHILE SEM IMAGES OF SUBMERGED COUPONS SHOWED A THICK CRUST OF CORROSION IMAGES OF SUBMERGED COUPONS SHOWED A THICK CRUST OF CORROSION PRODUCTS
- OVER 90% OF AL RELEASED INTO SOLUTION FROM 3 SUBMERGED COUPONS
- LESS THAN 10% FROM FIBERGLASS AND THE 56 SPRAYED ALUMINUM COUPONS
- TOTAL WEIGHT LOSS = 0.15%, TWO ORDERS OF MAGNITUDE LESS THAN SUBMERGED COUPONS
- LACK OF MECHANISM FOR CORROSION PRODUCT TRANSPORT AFTER SPRAY CEASES
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- Precipitation zones for sodium aluminosilicates at 25oC and 0.89 M hydroxide
- No aluminosilicate species expected
-4.5
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0 log[Al] mol/kg no precipitation precipitation Kewaunee 28
- Maximum sump Al concentration:
- AECL calculation = 0.37 mg/L
- WCAP prediction = 0.82 mg/L
- Worst case Al concentration below experimentally measured Al solubility (Bahn et al. [2008])
- No Precipitation Expected
-5.0
-4.5
-5.0
-4.5
-4.0
-3.5
-3.0
-2.5
-2.0
-1.5
-1.0 log[Si] mol/kg 0.1 1
10 100 1000 6
6.5 7
7.5 8
8.5 9
9.5 10 pH
[Al] (mg/L)
AECL WCAP
KEWAUNEE POWER STATION - GSI-191 RESOLUTION PARAMETER HEAD (FT)
COMMENT NPSH AVAILABLE 24.108 TOTAL WATER HEIGHT AT THE ONSET OF RECIRCULATION, MINUS PIPING FRICTION LOSSES [26.224 - 2.116]
MAXIMUM 3.286 CLEAN STRAINER HEAD LOSS AND
- NET POSITIVE SUCTION HEAD (NPSH) MARGIN MAXIMUM MEASURED DEBRIS LADEN STRAINER HEAD LOSS
- 3.286 CLEAN STRAINER HEAD LOSS AND DEBRIS LADEN STRAINER HEAD LOSS COMBINED, TEMPERATURE-CORRECTED TO 65 DEG F NPSH REQUIRED 8
AT MANUFACTURER-SPECIFIED DESIGN FLOW RATE 2000 GPM (BOUNDS DESIGN BASIS FLOW DURING RECIRCULATION)
NPSH MARGIN 12.822 29
- MAXIMUM STRAINER HEAD LOSS (CSHL+DEBRIS BED HL) IS LIMITED TO 10 FT UNLESS STRUCTURAL REANALYSIS IS PERFORMED
KEWAUNEE POWER STATION - GSI-191 RESOLUTION
- ITEMS REMAINING FOR GSI-191 RESOLUTION
- REACTOR VESSEL CORE COOLING DOWNSTREAM EFFECTS
- REACTOR VESSEL DOWNSTREAM EFFECTS EVALUATIONS HAVE BEEN COMPLETED FOR KEWAUNEE USING WCAP-HAVE BEEN COMPLETED FOR KEWAUNEE USING WCAP-16406-P AND WCAP-16793-NP
- KEWAUNEE WILL REASSESS ITS EVALUATIONS UPON NRC ISSUANCE OF THE FINAL SAFETY EVALUATION FOR WCAP-16793-NP 30
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS A. BREAK SELECTION 1.A THREE ANALYZED BREAKS RESULTING IN WORST DEBRIS QUANTITY/COMBINATION 1.B ADDITIONAL BREAKS NOT ANALYZED AS WOULD NOT CHANGE DEBRIS SOURCE TERM DUE TO LARGE ZONES OF INFLUENCE 1.C RCS LOOP B CONTAINS PRESSURIZER 1.D RX VESSEL NOZZLE BREAK NOT A LIMITING BREAK 31
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS
- BREAK SELECTION o REFER TO SECOND KPS HANDOUT, PAGES 1 - 4 32
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS B. DEBRIS GENERATION / ZONE OF INFLUENCE 2.
USE OF 5.45D FOR THERMOBESTOS 3.
REPAIRS TO THERMOBESTOS & FIBERGLASS INSULATIONS 4.
VERIFY LATENT DEBRIS IS FINES 5.
TEMPMAT FINES 6.
FIBER EROSION OVER MISSION TIME 6.
FIBER EROSION OVER MISSION TIME 33
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS C. DEBRIS CHARACTERISTICS 7.A THERMOBESTOS AS 100% FINES 7.B FIBERGLASS PIPE COVER SIZE DISTRIBUTION 34
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS D. LATENT DEBRIS
- 8. LATENT DEBRIS SAMPLING METHODOLOGY 35
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS E. DEBRIS TRANSPORT 9.
DEBRIS INTERCEPTOR TESTS 10.A FIBERGLASS EROSION TESTS 10.B MINIMUM TUMBLING VELOCITY & DEBRIS SETTLING 10.C DURATION OF EROSION TESTS 10.C DURATION OF EROSION TESTS
- 11. EROSION OF THERMOBESTOS - SEE QUESTION B.6
- 12. EROSION OF DEBRIS IN TEST FLUME
- 13. CFD IDENTIFICATION 13.A HOW DEBRIS INTERCEPTORS MODELED IN INPUT DECK 13.B LOCATIONS OF DRAINAGE 36
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2007 FIBER TRANSPORT TESTS
- 33% FIBROUS DEBRIS, 0.113 FT/SEC OVER DI (TEST 3B)
FLOW 37
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2007 FIBER TRANSPORT TESTS
- 33% FIBROUS DEBRIS, 0.113 FT/SEC OVER DI (TEST 3B) 38
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2007 FIBER TRANSPORT TESTS
- 100% FIBROUS DEBRIS; 0.113 FT/SEC OVER DI (TEST 1B)
FLOW DEBRIS INTERCEPTOR 39 FLOW
KEWAUNEE POWER STATION - GSI-191 RESOLUTION 2007 FIBER TRANSPORT TESTS
- 100% FIBROUS DEBRIS; 0.113 FT/SEC OVER DI (TEST 1B) 40
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS
- RAI E.9.j, E.13.a - e, E.15 AND E.16 o REFER TO SEPARATE HANDOUT BY ARL 41
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS E. DEBRIS TRANSPORT 13.C SIZE OF COMPUTATIONAL DOMAIN 13.D MAIN PHYSICAL MODELS 13.E BOUNDING SIMULATIONS
- 14. SETTLING ON UPPER ELEVATIONS
- 14. SETTLING ON UPPER ELEVATIONS
- 15. CONTOUR PLOTS OF VELOCITY AND TURBULENCE
- 16. DISTANCE OF DEBRIS ADDED IN TEST FLUME
- 17. DEBRIS FLOATATION 42
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS F. HEAD LOSS AND VORTEXING
- 18. CLEAN STRAINER HEAD LOSS METHODOLOGY 19.A MEASURED HEAD LOSS AND CSHL 19.B HEAD LOSS TEMPERATURE CORRECTION 19.C HED LOSS TEST METHODOLOGY 19.C HED LOSS TEST METHODOLOGY 19.C.I DEBRIS INTRODUCTION 19.C.II DEBRIS ADDITIONS AT < 100% FLOW RATE 19.C.III DEBRIS PREPARATION AND SURROGATE SIZE 19.C.IV DEBRIS CHARACTERISTICS FOR SURROGATES 19.C.V PROCEDURE STEPS 19.C.VI DESCRIPTION OF TEST FACILITY 19.C.VII DEBRIS INTRODUCTION TECHNIQUES 43
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS F. HEAD LOSS AND VORTEXING 19.C.VIII THIN BED INCREMENTAL FIBER 19.C.IX DEBRIS BY EACH DEBRIS ADDITION 19.C.X SCALING FACTORS 19.C.XI FLOW RATES 19.C.XI FLOW RATES 19.C.XII DENSITY-CORRECTED SURROGATES 19.C.XIII STIRRING 19.C.XIV DEBRIS THAT SETTLED 19.C.XV AGGLOMERATION OF DEBRIS
- 20. VORTEX EVALUATION CONDITIONS, ASSUMPTIONS
- 21. VOIDING EVALUATION
- 22. FLASHING
- 23. HEAD LOSS PLOTS 44
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS F. HEAD LOSS AND VORTEXING
- 24. VENTED STRAINER
- 25. TEST TERMINATION
- 26. HEAD LOSS EXTRAPOLATION TO MISSION TIME
- 27. SCHEMATIC OF TEST FLUME
- 27. SCHEMATIC OF TEST FLUME
- 28. DEBRIS INTERCEPTOR DESIGN IN PLANT AND FLUME 45
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS G. NET POSITIVE SUCTION HEAD (NPSH)
- 29. BASIS FOR DESIGN FLOW RATES
- 31. SUCTION LINE FRICTION LOSSES
- 33. HOT LEG INJECTION (NOT USED), UPI AND COLD LEG INJECTION BOUNDED BY NPSH CALC
- 34. HOLD UP VOLUMES IN CONTAINMENT
- 35. MANUAL OPERATION OF TWO TRAINS RHR IN RECIRC MODE 46
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS H. STRUCTURAL ANALYSES
- 36. DESIGN CODE
- 37. DESIGN MARGINS
- 38. NO IMPINGEMENT ON STRAINER MODULES
- 39. DEBRIS INTERCEPTOR STRUCTURAL ADEQUACY
- 39. DEBRIS INTERCEPTOR STRUCTURAL ADEQUACY 47
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS I.
UPSTREAM EFFECTS 40.
REFUELING CAVITY DRAIN LINE 48
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS J.
DOWNSTREAM EFFECTS / IN-VESSEL
- 41. FINAL RESPONSE WITHIN 90 DAYS OF SER ISSUANCE 49
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS K. CHEMICAL EFFECTS
- 42. NO PLANT-SPECIFIC REFINEMENTS TO WCAP-16530-NP BASE MODEL
- 43. MIN/MAX PH 50
KEWAUNEE POWER STATION - GSI-191 RESOLUTION RAI QUESTIONS L. LICENSING BASIS
- 44. STRAINER SURVEILLANCE REQUIREMENTS NO CURRENT TECHNICAL SPECIFICATIONS TRANSITION TO IMPROVED TS WILL REQUIRE INSPECTION FOR DEBRIS, STRUCTURAL DISTRESS, ABNORMAL CORROSION CONTAINMENT INSPECTION PROCEDURES ALREADY IMPLEMENT THE NEW CONTAINMENT INSPECTION PROCEDURES ALREADY IMPLEMENT THE NEW INSPECTION REQUIREMENTS 51