ML053190338

From kanterella
Jump to navigation Jump to search
Notice of Meeting with Dominion, Kewaunee Flooding Regulatory Conference Slides
ML053190338
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 11/08/2005
From:
Dominion
To:
Office of Nuclear Reactor Regulation
References
EA-05-176
Download: ML053190338 (27)


Text

© Dominion 2005 Regulatory Conference Safety Related Equipment Susceptibility To Internal Flooding November 8, 2005

© 2003

© Dominion 2005 Dominion

Introduction Mike Gaffney Site Vice President

© Dominion 2005

© 2003 Dominion 3

AGENDA Introduction Mike Gaffney - Site VP Background Tom Webb - Director S&L Analysis Tom Hook - Supv. PRA Corrective Actions Kyle Hoops - Site Director Conclusion Mike Gaffney - Site VP

© Dominion 2005

© 2003 Dominion 4

Background

Tom Webb Station Director Nuclear Safety and Licensing

© Dominion 2005

© 2003 Dominion 5

NRC Finding The design of KPS did not ensure the AFW Pumps, EDGs, 480V and 4kV Safeguards Buses would be protected from random or seismically induced failures of non-class I systems in the Turbine Building

© Dominion 2005

© 2003 Dominion 6

Internal Flood Design Requirements USAR Appendix B.5 - Protection of Class I Items Class I items are protected against damage from: a) Rupture of a pipe or tank resulting in serious flooding or excessive steam release to the extent that the Class I function is impaired.

Systems, structures, and components designated Class I are so designed that there is no loss of function in the event of a Design Basis Earthquake (DBE) and all environmental factors (Ref.: USAR 1.3.1)

© Dominion 2005

© 2003 Dominion 7

Flood Areas

© Dominion 2005

© 2003 Dominion 8

Analysis Tom Hook Supervisor PRA

© Dominion 2005

© 2003 Dominion 9

Internal Flood Risk Assessment Topics z Initiating Events Summary z Analysis Methods z Failure Assumptions z Mitigation Assumptions z Risk Results

© Dominion 2005

© 2003 Dominion 10

Flood Initiating Events Random pipe breaks Condenser expansion joint breaks Steam line break with fire water sprinkler actuation Feedwater line break with fire water sprinkler actuation Seismic induced pipe breaks Tornado induced pipe breaks Turbine induced pipe breaks

© Dominion 2005

© 2003 Dominion 11

Resolution of NRC Issues with Prior Draft Analysis Credit for operator action to isolate firewater flow which required access through flooded Safeguards Alley compartments Credit for operator detection and isolation of the breaks in the assume timeframes Credit for connecting battery charger to TSC diesel Critical flood height uncertainty High energy line break initiating event frequency based on flow accelerated corrosion program

© Dominion 2005

© 2003 Dominion 12

Analysis Methods Surveyor measurements of flood area floor elevations Dynamic flood level analysis using GOTHIC Equipment survivability evaluations in flooded conditions Dynamic motor-driven auxiliary feedwater pump room heatup upon loss of ventilation Simulator scenario exercises Review of operator training materials 480V breakers tested in flooded conditions Developed seismic fragilities for flood sources Constructed event trees and fault trees for scenarios

© Dominion 2005

© 2003 Dominion 13

Flood Initiating Event Assumptions Offsite power available unless event causes loss (e.g., flood level exceeds 18, seismic, or tornado)

No credit taken for equipment in Turbine Building z Non-safety related buses z Feedwater and condensate z Sump pumps z Auxiliaries for reserve auxiliary transformer

© Dominion 2005

© 2003 Dominion 14

Flood Initiating Event Assumptions - Break Frequencies Plant specific analysis using EPRI reports z High energy line breaks z Random pipe breaks z Condenser expansion joint breaks z Seismic breaks

© Dominion 2005

© 2003 Dominion 15

Flood Failure Assumptions Critical flood heights in each compartment z Train A/B 480V switchgear (buses 51, 52, 61, 62)

- @ 2.75 flood level trips bottom row of breakers

- @ 4 flood level control power lost

- @ 11 flood level bus stabs covered and bus failed z Train A/B 4kV switchgear (buses 5 and 6 located in respective EDG rooms)

- @ 4 flood level control power connections covered and breaker failed (applies to Train A, only applies to Train B room after 6 curb removal)

- @ 18 flood level bus stabs covered and bus failed

© Dominion 2005

© 2003 Dominion 16

Flood Failure Assumptions (cont.)

Critical flood heights in each compartment (cont.)

z Turbine-driven AFW pump

- @ 9 flood level auxiliary lube oil pump fails

- @ 18 flood level pump fails z Motor-driven AFW pumps

- @ 9 flood level auxiliary lube oil pump fails

- @ 13 flood level pump fails z Instrument air compressors

- @ 11 flood level compressor fails z Emergency diesel generators and dedicated shutdown panel

- Equipment above 6, however 4kV buses fail @ 6 flood level

© Dominion 2005

© 2003 Dominion 17

Flood Mitigation Assumptions Operator action times z Based on simulator exercise, table top exercises, and training

- Isolation of circulating water and service water breaks

- Isolation of firewater sprinklers and deluge valves

- Establish alternate battery room cooling

- Transfer inverter to alternate power supply

- Establish long term power supply to DC chargers Impact of flood on local operator actions z No credit for operator passing through flooded safeguards areas to perform flood isolation actions in high energy line break events Equipment operation z Operation in flooded environment based on documented engineering assessments and testing

© Dominion 2005

© 2003 Dominion 18

Resolution of NRC Issues with Prior Draft Analysis Credit for operator action to isolate firewater flow which required access through flooded Safeguards Alley compartments z No longer credited in high energy line break events Credit for operator detection and isolation of the breaks in the assumed timeframes z Operator actions were time validated in simulator exercises performed, human error evaluations revised to be more conservative Credit for connecting battery charger to TSC diesel z Human error evaluations revised to be more conservative Critical flood height uncertainty z Performed definitive 480V breaker test (all 3 breakers performed same),

surveyor measurements of room elevations High energy line break initiating event frequency based on flow accelerated corrosion program z Performed updated plant specific evaluation based on new EPRI report on pipe break frequencies

© Dominion 2005

© 2003 Dominion 19

Internal Flood Risk Results Flood Scenario Total CDP (per yr)

Random circulating water inlet expansion joint break 2.8E-5 Random circulating water outlet expansion joint break 4.3E-6 Random service water system break with equivalent diameter greater 1.2E-6 than four inches Random fire water line with equivalent diameter greater than four inches 2.3E-6 Random feedwater or condensate high-energy line break that actuates 8.7E-6 all turbine building fire sprinklers Random feedwater or condensate high-energy line break that actuates 6.1E-7 100 turbine building fire sprinklers Random main steam high-energy line break that actuates all turbine 7.0E-6 building fire sprinklers Random main steam high-energy line break that actuates 100 turbine 4.2E-7 building fire sprinklers Tornado induced break of circulating water lines, firewater lines, service Negligible water lines, and condensate storage tanks Turbine missile induced break of circulating water lines, firewater lines, Negligible service water lines, and condensate storage tanks Seismic induced break of circulating water lines, firewater lines, service 6.6E-6 water lines, and condensate storage Total 5.9E-5

© Dominion 2005

© 2003 Dominion 20

Internal Flood Risk Results (cont.)

Large early release probability (LERP) z No short term impact on Containment integrity assuming Containment initially intact z Likelihood of intact Containment capable of causing large release less than 10%

z CDP impact dominates risk, LERP at least factor of 10 below CDP

© Dominion 2005

© 2003 Dominion 21

Sensitivity Analyses Sensitivity Case Total CDP Percent (per year) Change Best-Estimate Baseline 5.9E-5 n/a HEPs for operator actions with less than 30 min time 6.5E-5 +09%

window increased by 100%

HEPs for operator actions with less than 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> time 8.2E-5 +39%

window increased by 100%

HEPs for unproceduralized operator actions increased by 7.1E-5 +21%

100%

High energy (main steam & feedwater) line break 7.6E-5 +28%

frequencies increased by 100%

Circulating water expansion joint break frequencies 7.7E-5 +31%

increased by 100%

Random pipe break frequencies increased by 100% 7.7E-5 +31%

© Dominion 2005

© 2003 Dominion 22

Summary Overall delta core damage risk is 5.9E-05 per year (yellow)

Large, early release risk not a factor in overall SDP color Additional conservatisms not quantified:

z No credit for operators taking actions in Safeguards Alley to isolate floods following high energy line break events z Additional mitigation from primary system feed & bleed cooling not credited z Opening Safeguards Alley doors would hasten isolation of firewater pumps and eliminate need for local operator action to isolate flood z Impact of operators tripping feedwater pumps before emptying hotwell not credited Consideration of uncertainties does not impact overall risk characterization

© Dominion 2005

© 2003 Dominion 23

Corrective Actions Kyle Hoops Site Director

© Dominion 2005

© 2003 Dominion 24

Corrective Actions z Organizational z Modifications

- Barriers

- Check Valves

- Circulating Water Pump Trip

© Dominion 2005

© 2003 Dominion 25

Conclusion Mike Gaffney Site Vice President

© Dominion 2005

© 2003 Dominion 26

Conclusions Flooding Overall Delta Core Damage Risk 5.9E-05 per year (Yellow)

Modifications Resolved Turbine Building Flooding Issues

© Dominion 2005

© 2003 Dominion 27