Point Beach/Kewaunee Meeting Summary Slides, Nuclear Management Companys Reactor Pressure Vessel Head Replacement Project
ML031990332
Person / Time
Site: Kewaunee, Point Beach  NextEra Energy icon.png
Issue date: 07/03/2003
From:
Nuclear Management Co
To:
NRC/RGN-III
References
Download: ML031990332 (40)


Text

1 Nuclear Management Companys Reactor Pressure Vessel Head Replacement Project July 2003 United States Nuclear Regulatory Commission Region III

2 Agenda

 Project Organization

 Project Status

 Fabrication

 Quality Oversight

 Installation

 Summary

3 Purpose Communicate to NRC Region III the scope and schedule of the NMC Reactor Pressure Vessel Head Replacement Project.

4 Objectives

 Identify required NRC regulatory activities

 Establish periodic updates to the NRC

5 Project Organization

6 Organization

 Multi-site capital project for NMC

 Common fabrication organization

 Site specific installation organization

Background

7 Project Organization Mike Wadley Sr. VP Support Programs Ron Kuhn Project Manager Point Beach RVHR Tim Olson Project Manager Kewaunee RVHR Chuck Tomes Fleet Engineering Lead RVHR Steve Forsha Oversight Lead RVHR Project Management Japan Lewis McKenzie Hank Hoelscher Fleet Project Manager Leo Ganser Manager Supplier Assessment John Paul Cowan CNO Mano Nazar Sr VP Dave Jantosik Director Nuclear Oversight Gary Van Middlesworth VP Nuclear Assessment Programs Project Oversight Review Panel Dave Jantosik Mike Wadley Mano Nazar Tom Coutu Site VP Kewaunee Fred Cayia Site VP Point Beach Organization

8 Project Status

9 Contractors

 Westinghouse is prime contractor providing new replacement reactor pressure vessel (RPV) heads

 Mitsubishi Heavy Industries (MHI), Kobe Japan, subcontracted to design and fabricate RPV heads Project Status

10 Scope

 Kewaunee - New RPV head and CRDM

 No Head Assembly Upgrade Package (HAUP)

 Point Beach - New RPV heads and CRDMs

 HAUP

 Control Rod Drive Mechanism (CRDM) coil stacks

 Thermocouple cables

 Rod Position Indicator (RPI) and CRDM cables Project Status

11 Scope (continued)

 New heads and CRDMs will be made and fabricated in Japan under Mitsubishi Heavy Industries quality program

 HAUP will be fabricated in Pittsburgh under Westinghouses quality program Project Status

12 Details of RPV Head Scope



Single Piece Forging



Electro-Slag Welded Strip cladding



Alloy 600 Prohibited



Use alloy 690 tubing versus alloy 600 tubing



Use alloy 690 weld material versus alloy 600 weld material



Use narrow J-groove weld bevel



One piece L-106A CRDMs (one butt weld on latch mechanism)



Eliminate vent on each CRDM



Eliminate all seal welds



Eliminate spare and part length penetrations



Vent and Reactor Vessel Level Indication System Taps



Core Exit Thermocouple Nozzle Assembly (CETNA)

Project Status

13 Details of Scope (continued)

Plant specific differences

 Kewaunee has eliminated plutonium recycle ports and part length penetrations

 Kewaunee will have four capped spare penetrations on the new RPV head Project Status

14 Project Schedule - Kewaunee

 Reactor Vessel Head Forging Complete

 Fabrication CRDM Head Adapter & Housing 12/13/03

 Shrink Fitting of the head penetration tubing 12/15/03

 Hydro Test 05/01/04

 Site Delivery 09/01/04

 Outage 09/25/04 Project Status

15 Project Schedule - Point Beach

 Reactor Vessel Forging 8/23/03 1/15/04

 Fabrication CRDM Head Adapter & Housing 4/10/04 9/25/04

 Shrink Fitting of the head penetration tubing 4/15/04 9/30/04

 Hydro Test 9/15/04 2/20/05

 Site Delivery 2/01/05 7/01/05

 Outage 4/02/05 10/08/05 Unit 2 Unit 1 Project Status

16 Fabrication

17 Overall Responsibilities RPV Head and CRDMs

 Design Specification - Westinghouse

 Material Procurement - Mitsubishi Heavy Industries

 Design Review - Westinghouse

 Technical and Quality Oversight - NMC Fabrication

18 Overall Responsibilities (continued)

RPV Head and CRDMs

 Mitsubishi Heavy Industries

 Fabrication

 Certified Design Report

 Stamping

 Preservice Inspection

 Packaging and Shipping

 Installation - Westinghouse Fabrication

19 Overall Responsibilities (continued)

Head Assembly Upgrade Package

 Fabrication-Westinghouse

 Design-Westinghouse

 Installation-Westinghouse

 Technical and Quality Oversight - NMC Fabrication

20 Design Responsibilities

 NMC - Scope and Technical Specification

 Westinghouse (Original Equipment Manufacturer) - Design Specification

 Mitsubishi Heavy Industries

 Certified Design Report

 ASME NPT Stamp Fabrication

21 Fabrication Status Kewaunee

 Long Lead Time Items Delivered

 Forging - Japan Steel Works

 CRDM Alloy 690 Penetrations - Sumitomo

 Design Specifications Issued

 CRDM Stainless Steel Pressure Boundary - Hitachi

 Fabrication in progress

 Cladding

 Latch housing & rod travel housing machining

 Latch arm machining Fabrication

22 Fabrication Status Point Beach - Unit 2

 Long Lead Time Items Ordered

 Forging - Japan Steel Works

 CRDM Alloy 690 Penetrations - Sumitomo

 Design Specifications Issued Fabrication

23 Sub Vendor Fabrication Locations

 Mitsubishi Heavy Industries

 Futami Plant - Reactor Vessel Head

 Kobe Shipyard & Machinery Works - CRDMs Fabrication

24 Sub Vendor Fabrication Locations (continued)

 Sub Vendor Facilities

 Japan Steel Works - Forging

 Sumitomo - CRDM Alloy 690 Penetrations tubing

 Hitachi - Stainless Steel CRDM Pressure Boundary Components

 Kanaski Steel - Lifting Lugs

 Kobe Steel LTD. - Weld Material

 Nippon Welding Rod - Alloy 690 Weld Material

25 MHI Japan Steel Works Hitachi Sumitomo Fabrication Kawasaki NIPPON

26 Licensing Requirements

 Planned to be done pursuant to 10CFR 50.59

 Additional NRC reviews or prior approvals not expected Fabrication

27 Applicable ASME Codes and Standards ASME Boiler and Pressure Vessel Code

 Section II,Section III, Section V,Section XI ASME 1998 Edition thru 2000 Addendum

 Section IX, Latest Edition Code cases

 ASME Code Case 2142-1, Ni-Cr-Fe (UNS N06052), November 25, 1992

 ASME Code Case 2143-1, Ni-Cr-Fe (UNS W86152), November 25, 1992 Fabrication

28 Applicable ASME Codes and Standards (continued)

 NRC Issued Flaw Evaluation Criteria for Examination of CRDM Tubing and J-groove Welds

 US NRC Regulatory Guide 1.28, Rev 3 - Quality Assurance Program Requirements

 US NRC Regulatory Guide 1.31, Rev 3 - Control of Ferrite Content in Stainless Steel Metal

 US NRC Regulatory Guide 1.43, May 1973 - Control of Stainless Steel Weld Cladding of Low Alloy Steel and Components

 US NRC Regulatory Guide 1.50, May 1973 - Control of Preheat Temperature for Welding of Low Alloy Steel Fabrication

29 Non Destructive Testing

 Section XI, ASME 1998 Edition thru 2000 Addendum

 Section III, ASME 1998 Edition thru 2000 Addendum

 Additional NDE Requirements Imposed By NMC

 NRC Developed Acceptance Criteria Used for Preservice Examination of Alloy 690 Tubing and J-groove Welds

 Capability of Examining the Alloy 690 Tubing and J-groove Welds To Be Verified With NDE & Repair Mockups Fabrication

30 Quality Oversight

31 Quality Oversight



NMC Project Oversight Plan



Establishes the program oversight and responsibilities for the project Supplier qualification Stop Work Authority Inspections Nonconformances Personnel Qualification Reporting

32 Oversight Plan

 Establishes an Oversight Review Panel

 Purpose to provide an integrated review of the project oversight

 Panel consists of:

  • Director of Nuclear Oversight
  • Senior Vice President of Support Programs
  • One additional Vice President

 Panel meets biannually or as conditions require Quality Oversight

33 Resident Oversight Personnel

 Resident Oversight Personnel for NMC and Westinghouse

 Monitor work activities

 Verify critical attributes at witness and hold points

 Follow-up on corrective actions

 Resident inspector is bilingual Japanese national Quality Oversight

34 Communication and Issue Resolution Form (CIRF)

 Project Specific Process

 Documents and communicates issues found by NMC, Westinghouse and MHI

 Reviewed each day in Kobe by NMC, Westinghouse and MHI Project Managers for cause determination, corrective action and resolution.

 Quality issues tracked via MHI/W QA Programs.

Other issues tracked via project letter, as needed.

Quality Oversight

35 Installation

36 Installation

 Westinghouse/ Mitsubishi Heavy Industries to arrange transportation of the new heads

 Replacement RPV heads fit through equipment hatches at Point Beach and Kewaunee - No Integrated Leak Rate Testing required

 Both sites will require interference removal

37 Installation Overview (continued)

 Westinghouse to supervise old RPV head removal and new RPV head installation

 NMC provide tools, craft labor and oversight

 Head removal and reinstallation performed per standard outage requirements

38 Installation Overview (continued)

 Westinghouse provides the Department of Transportation (DOT) shipping container for old RPV heads and CRDMs

 NMC will select a disposal contractor for old RPV heads

39 Summary

40 Summary

 Technical/quality oversight is in place

 Fabrication of RPV heads is underway

 Installation planning is just starting