IR 05000413/2018004
ML19023A532 | |
Person / Time | |
---|---|
Site: | Catawba |
Issue date: | 01/23/2019 |
From: | Frank Ehrhardt NRC/RGN-II/DRP/RPB1 |
To: | Simril T Duke Energy Corp |
Geanette D | |
References | |
IR 2018004 | |
Download: ML19023A532 (13) | |
Text
ary 23, 2019
SUBJECT:
CATAWBA NUCLEAR STATION - NRC INTEGRATED INSPECTION REPORT 05000413/2018004 AND 05000414/2018004
Dear Mr. Simril:
On December 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Catawba Nuclear Station, Units 1 and 2. On January 15, 2019, the NRC inspectors discussed the results of this inspection with you and other members of your staff.
The results of this inspection are documented in the enclosed report.
NRC inspectors did not identify any findings or violations of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Frank J. Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos.: 50-413, 50-414 License Nos.: NPF-35, NPF-52
Enclosure:
IR 05000413/2018004 and 05000414/2018004
Inspection Report
Docket Number(s): 50-413, 50-414 License Number(s): NPF-35, NPF-52 Report Number(s): 05000413/2018004 and 05000414/2018004 Enterprise Identifier: I-2018-004-0039 Licensee: Duke Energy Carolinas, LLC Facility: Catawba Nuclear Station, Units 1 and 2 Location: York, SC Inspection Dates: October 1, 2018 to December 31, 2018 Inspectors: J. Austin, Senior Resident Inspector C. Scott, Resident Inspector A. Butcavage, Reactor Inspector M. Meeks, Senior Operations Engineer R. Williams, Senior Reactor Inspector Approved By: Frank J. Ehrhardt, Chief Reactor Projects Branch 1 Division of Reactor Projects Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring licensees performance by conducting a quarterly baseline inspection at Catawba, Units 1 and 2 in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors.
Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. No findings were identified during this inspection period.
PLANT STATUS
Unit 1 operated at or near 100 percent rated thermal power (RTP) through November 16. On November 17, the unit commenced refueling outage 1RFO24 and returned to 100 percent RTP on December 14.
Unit 2 operated at or near 100 percent RTP for the entire inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515 Appendix D, Plant Status and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection Seasonal Extreme Weather
The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures, expecting snow and freezing rain on December 9, 2018.
71111.04 - Equipment Alignment Partial Walkdown
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) standby shutdown facility (SSF) ventilation system on October 25, 2018
- (2) Unit 1 and Unit 2 service water structure on November 13, 2018
- (3) station blackout bus work on December 9, 2018
Complete Walkdown (1 Sample)
The inspectors evaluated system configurations during a complete walkdown of the diesel generator sump pump system on December 26, 2018.
71111.05AQ - Fire Protection Annual/Quarterly Quarterly Inspection
The inspectors evaluated fire protection program implementation in the following selected areas:
- (1) Unit 1 B emergency diesel generator, Fire Area 26 on November 6, 2018
- (2) Unit 2 B emergency diesel generator, Fire Area 28 on November 7, 2018
- (3) standby shutdown facility elevation 612, Fire Area SSF on November 13, 2018
- (4) Unit 1 reactor building elevation 565 lower containment, Fire Area RB1 on November 30, 2018
- (5) Unit 1 turbine building elevation 568, Fire Area TB1 on December 26, 2018
Annual Inspection (1 Sample)
The inspectors evaluated fire brigade performance on October 5, 2018.
71111.06 - Flood Protection Measures Internal Flooding
The inspectors evaluated internal flooding mitigation protections in the Unit 1 and Unit 2 turbine buildings on October 11, 2018.
71111.08 - Inservice Inspection Activities
The inspectors evaluated pressurized water reactor non-destructive testing by reviewing the following examinations from November 26, 2018 to November 30, 2018:
- (1) Ultrasonic Examination (UT)a) UT of 1SM-4B-A, 34 pipe-to-elbow weld, ASME Class 2 (observed)b) UT of 1SM28-3, 34 elbow-to-pipe weld, ASME Class 2 (observed)
- (2) Liquid Penetrant Examination (PT)a) PT of SA5-2, 4 pipe valve weld, ASME Class 2 (reviewed) - This review included a pressure boundary welding activity
- (3) Visual Examination (VE)a) VE of 1RPV-HEAD-SURFACE, reactor pressure vessel upper head; ASME Code Class 1 (reviewed)
- (4) Radiographic Examination (RT)a) RT of SA5-2, 4 pipe valve weld, ASME Class 2 (reviewed) - This review included a pressure boundary welding activity
- (5) Eddy Current Examination (ET)a) Steam Generator B - ET for tubes R10C91, R97C70, R93C116, R111C72, R119C72, ASME Class 1 (observed)b) Steam Generator C - ET for tubes R24C5, R25C5, R25C4, R43C12, R46C7, ASME Class 1 (observed)
- (6) Visual Examination (VT-1)a) VT-1 of 1SGB-MW-Y1-X2, Steam Generator Manway Nuts; ASME Code Class 1 (observed)b) VT-1 of 1SGB-MW-X2-Y2, Steam Generator Manway Nuts; ASME Code Class 1 (observed)c) VT-1 of 1SGC-MW-X1-Y1, Steam Generator Manway Nuts; ASME Code Class 1 (observed)d) VT-1 of 1SGC-MW-X1-Y2, Steam Generator Manway Nuts; ASME Code Class 1 (observed)
The inspectors evaluated the licensees boric acid corrosion control program performance.
71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification
The inspectors observed and evaluated a reactor operator simulator evaluation on October 4, 2018. The scenario consisted of a component cooling pump failure, loss of feedwater, and a faulted steam generator.
Operator Exams (1 Sample)
The inspectors reviewed and evaluated requalification examination results during the week of December 17, 2018.
Operator Performance (1 Sample)
The inspectors observed operator performance during the Unit 1 reactor startup on December 11, 2018.
71111.13 - Maintenance Risk Assessments and Emergent Work Control
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
- (1) Protected equipment plan with the 1B auxiliary feedwater pump out of service for pre-planned maintenance on November 1, 2018
- (2) Yellow Risk condition for Unit 1 while at reduced inventory during refueling outage 1RFO24 to remove reactor vessel head on November 21, 2018
- (3) Yellow Risk condition for Unit 1 to remove steam generator nozzle dams on December 3, 2018
- (4) Green Risk condition for Unit 1 while reactor start-up was in progress on December 8, 2018
71111.15 - Operability Determinations and Functionality Assessments
The inspectors evaluated the following operability determinations and functionality assessments:
- (1) Condition Report (CR) 2230546, Unit 1 Standby make up pump suction damper on October 16, 2018
- (2) CR 2240817, Technical basis for standby shutdown facility without heating and ventilation on November 1, 2018
- (3) CR 2247778, Unit 1 C steam generator PORV SV-7 inoperable during mode change to Mode 4 on December 8, 2018
- (4) CR 2247892, 1A Motor generator breaker tripped on December 10, 2018
- (5) CR 2249561, Investigate 1 delta cold leg accumulator inleakage on December 19, 2018
71111.19 - Post Maintenance Testing
The inspectors evaluated the following post maintenance tests:
- (1) Work Request (WR) 20126420, Functional testing following repair of 1EMF-74, D SG N-16 leakage monitor on November 15, 2018
- (2) PT/1/A/4350/002 A, Diesel operability test following 1A diesel governor modification on November 26, 2018
- (3) TN/1/A/108756/01E, Post modification testing of 120 VAC power panelboard 1ERPA, following replacement on November 28, 2018
- (4) PT/0/A/4400/002 A, Nuclear service water train A performance test following 1A service water pump replacement on November 29, 2018
- (5) PT/1/A/4200/007 A, Centrifugal charging pump 1A test following mechanical seal rebuild on November 30, 2018
- (6) Work Order (WO) 20189225, Functional verification following overheating of flex link connection adapter plates in main generator bushing box on December 16, 2018
71111.20 - Refueling and Other Outage Activities
The inspectors evaluated refueling outage 1RFO24 activities from November 16, 2018 to December 12, 2018.
71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests: Routine
- (1) PT/0/A/4200/086, Ice bed analysis periodic test on November 24, 2018
Reactor Coolant System Leak Detection (1 Sample)
- (1) PT/2/A/4150/001 D, Reactor coolant leakage calculation on December 12, 2018
Containment Isolation Valve (1 Sample)
- (1) PT/1/A/4200/001 I, As Found Containment Isolation Valve Leak Rate Test, on November 27, 2018
71114.06 - Drill Evaluation Drill/Training Evolution
The inspectors evaluated a simulator based licensed operator requalification training evolution on November 1, 2018.
The inspectors observed emergency response organization focus area training on November 6,
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below for the period from October 2017 through September 2018.
- (1) unplanned scrams per 7000 critical hours
- (2) reactor coolant leakage
- (3) safety system functional failure
71152 - Problem Identification and Resolution Semiannual Trend Review
The inspectors reviewed the licensees corrective action program for trends that might be indicative of a more significant safety issue.
Annual Follow-up of Selected Issues (1 Sample)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) CR 2242621, 1B emergency diesel generator unstable voltage during testing
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
The inspectors confirmed that proprietary information was controlled to protect from public disclosure.
- On January 15, 2019, the inspector presented the quarterly resident inspector inspection results to Mr. Tom Simril, and other members of the licensee staff.
LIST OF
DOCUMENTS REVIEWED
71111.04 - Equipment Alignment
CR 2245787, SSF-AHS-1 damage
CR 2238064, Capability of WN sump pumps
CR 2238070, WN and NS/ND sump pumps added to the IST program
71111.05AQ - Fire Protection Annual/Quarterly
RP/0/B/5000/029, Fire Brigade Response
71111.08 - Inservice Inspection Activities
Procedures
03-6016219, Field Procedure for In-Situ Pressure Testing RSG Tubes Using the Triplex Pump,
Rev. 012
03-9289742, Secondary Side Visual Inspection Plan and Procedure for Duke Energy, Catawba
1, EOC24, Rev. 0
54-ISI-400-022, Non-Destructive Examination Procedure, Multi-Frequency Eddy Current
Examination of Tubing, 6/27/17
AD-EG-PWR-1611, Boric Acid Corrosion Control Program - Implementation, Rev. 2
AD-MN-ALL-0006, Fluid Leak Management, Rev. 1
NDE-NE-ALL-4101, Liquid Penetrant Examination, Rev. 1
NDE-NE-ALL-6102, Utilization of PDI-UT-2 Generic Procedure for the Ultrasonic Examination of
Austenitic Pipe Welds, Rev. 2
NDE-NE-ALL-6111, Utilization of PDI-UT-1, Generic Procedure for the Ultrasonic Examination
of Ferritic Pipe Welds, Rev. 1
NDE-NE-ALL-7101, VT-1 Visual Examination, Rev. 0
NDE-NE-ALL-7202, Visual Examination of PWR Reactor Pressure Vessel Upper Head
Penetrations, Rev. 3
PD-EG-PWR-1611, Boric Acid Corrosion Control Program, Rev. 1
Calculations
CNC-1201.01-00-0009, Appendix F, Catawba 1EOC21 Steam Generator Condition Monitoring
and Operational Assessment (CMOA), 7/31/14
CNC-1201.01-00-0022, Determination of Periodic Inspection Requirements for the Reactor
Vessel Head and Reactor Vessel Head Inspection Documentation, Rev. 27
Drawings
7693E001, B&W Canada, Duke Power Company, Steam Generator Arrangement, Right Hand
Vessel, Rev. 7
7693E002, B&W Canada, Duke Power Company, Steam Generator Arrangement, Left Hand
Vessel, Rev. 3
CN-1680-182, Catawba Nuclear Station, Steam Generator Tube Repair and Plugging Listing,
Steam Generator 1A,1B,1C and 1D, Rev. 2
Other Documents
03-1246524, Instructions for Plug Visual Inspection Level III, Enclosure 1, Plug Inspection
Report, S/G-1D Cold Leg, 11/26/18
03-1246524, Instructions for Plug Visual Inspection Level III, Rev. 14
Areva, Certificate of Calibration, Eddy Current Tester MIZ-80, S/N 042, Expiration Date 7/19/19
Areva, Certificate of Conformance, Data Package No. 23-5061192-02, 4/22/05
Areva, Certificate of Personnel Qualification (ET), ID Code B3720, Level-III-QDA, Expires
8/17/21
ASME Boiler & Pressure Vessel Code, 2007 w/2008 Addenda, July 1, 2008
BWXT, Catawba Unit-1 Foreign Object Assessment, 12/4/18
Catawba 1R24, Steam Generator Degradation Assessment, Rev.0, 11/8/18
Catawba C1R24, Independent Quality Data Analyst (IQDA) Log, Sparky Data Observation,
11/23/2018
Catawba Unit-1, Model CFR 80 Tri-Pitch Steam Generators, Secondary Side Integrity Plan,
Rev. 1
Catawba Unit-1, Primary to Secondary Leak-rate, 5 minute Average Trend Plot, 2/1/18 through
11/1/18
Catawba Unit-1, SG1A, SG1B, SG1C and SG1D, Narrow Range Level Trend Plots, 2/1/18
through 11/1/18
Certificate of Method Qualification for Examiners:
- M. Freeman, 465817, 268757,
430648, 288663
C-ISISG-0169.030.0040, Duke Energy, Fourth Interval Steam Generator Tube In-service
Inspection Plan, Catawba Nuclear Station, Units 1&2, Rev. 0
CS-CP-CNS-0020, Catawba Nuclear Station Primary to Secondary Leak Rate Monitoring
Program, Rev. 1
Duke Energy, Catawba, Calibration Group SG1BHCAL00037, IQDA Equipment Used, Data
Display, 11/29/18
Duke Energy, Catawba, Calibration Group SG1CHCAL000011, QDA Equipment Used, Data
Display, 11/26/18
Duke Energy, Certificate of Method Qualification (ET), ID Code 224860, Level-III-N, Expires
7/11/21
Duke Energy, Eddy Current Guidelines for Duke Energy CFR80 Steam Generators, 11/7/18
Duke Energy, Visual Acuity Record, ID Code 224860, Expires 5/15/19
ETSS-11956.3, Performance Demonstration Database, X-Probe Array, Rev. 2
ETSS-11956.4, Performance Demonstration Database, X-Probe Array, Rev. 2
ETSS-2, Examination Technique Specification Sheet, Catawba C1R24, Rev. 0
ETSS-96004.3, Performance Demonstration Database, Bobbin Coil, Rev. 13
Framatome, Certificate of Visual Examination, ID Code B3720 Expires 6/13/19
More Tech, Certificate of Personnel Qualification (ET), ID Code M2655, Level-III, QDA, Expires
8/29/23
More Tech, Certificate of Visual Examination, ID Code M2655, Expires 8/30/19
NDE Report No. WE170294
NDE-NE-CFR-0112, Duke Energy CFR80 Steam Generator Site Technique Validation for
Catawba Nuclear Station, Unit-1 and McGuire Nuclear Station Units-1 & 2, Rev 2
Procedure Qualification Record: L-102E Rev. 0, L-104 Rev. 3, L-133 Rev. 1, L-146D Rev. 0
Radiographic Examination Report No. DEC1_SA5-1_2017-03-24
SF-040115,Rev.1, B&W Ltd. Canada, Operability Statement for B&W RSGs/ROTSGs Without
Documented NB-3000 Analysis of Tube to Tubesheet Welds, 4/14/15
SGMP-IL-15-01, Steam Generator ASME Code Pressure Boundary-Tubesheet Weld or Tube-to
Tubesheet Friction Joint, 7/9/15
UT Calibration/Examination Report No.: UT-18-99, UT-18-100
Visual Examination for Boric Acid Detection Report No. VT-18-212
Visual Examination of Pressure Retaining Bolting (VT-1) Report No.: VT-18-231, VT-18-232,
VT-18-233, VT-18-234
Weld Doc No. 170373
Weld Procedure Specification Technical Sheet: GTSM01010-01, Rev. 8
ZETEC, Certificate of Conformance, Eddy Current Probe, S/N 756440, 9/29/18
ZETEC, Certificate of Conformance, Eddy Current Probe, S/N 760981, 11/16/18
Condition Reports
AR 01898451, Fatigue Analysis of Replacement Steam Generator Tube to Tube Sheet Welds
AR 02123708, Engineering to perform boric acid corrosion evaluation
AR 02124726, (NRC Identified) Evaluate Enhancement to SGME Procedures (PD-EG-PWR-
1801, AD-EG-PWR-1814 and AD-EG-PWR-1815) for improved clarity in how Vendor
Condition Monitoring and Operational Assessments (CMOAs) and Degradation Assessments
(DAs), are Retained as Site Calculations
AR 02127992, Boric acid corrosion control evaluation
AR 02130581, Boric acid corrosion control evaluation 1-NS-VA-5
AR 02161998, Perform BACC evaluation - 1-NV-VA-313
AR 02189442, Perform BACC evaluation 1NM-27 pipe cap leak
AR 02190836, 1-NV-VA-A087 - BACC evaluation IAW AD-EG-PWR-1611
AR 02246790, C1R24 SG Condition Monitoring and Reports
Work Orders (WO)/Work Requests (WR)
WR 20127584
WR 20127586
71111.11 - Licensed Operator Requalification Program and Licensed Operator
Performance
CPE 1801 License Operator Requalification
71111.19 - Post Maintenance Testing
IP/1/A/3450/003, 1ERPA, B, C, D Low Voltage Relay Checkout Procedure, Rev.10
EC 108756, Replace 1ERPA Panel Board
71111.20 - Refueling and Other Outage Activities
CNJITT10-N, Unit 1/2/ EOC Shutdown to Mode 5 JITT
OP/1/A/6100/002, Controlling Procedure for Unit Shutdown, Rev. 193
C1R24 Risk Plans
71111.22 - Surveillance Testing
CR 2246695, Ice Condenser- light ice baskets
11