IR 05000413/2021011

From kanterella
Jump to navigation Jump to search
NRC Fire Protection Team Inspection Report 05000413/2021011 and 05000414/2021011
ML21113A149
Person / Time
Site: Catawba  
Issue date: 04/23/2021
From: Scott Shaeffer
Division of Reactor Safety II
To: Simril R
Duke Energy Carolinas
References
IR 2021011
Download: ML21113A149 (9)


Text

April 23, 2021

SUBJECT:

CATAWBA NUCLEAR STATION - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000413/2021011 AND 05000414/2021011

Dear Mr. Simril:

On March 12, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Catawba Nuclear Station and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Scott M. Shaeffer, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos. 05000413 and 05000414 License Nos. NPF-35 and NPF-52

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000413 and 05000414

License Numbers:

NPF-35 and NPF-52

Report Numbers:

05000413/2021011 and 05000414/2021011

Enterprise Identifier: I-2021-011-0036

Licensee:

Duke Energy

Facility:

Catawba Nuclear Station

Location:

South Carolina

Inspection Dates:

February 22, 2021 to March 12, 2021

Inspectors:

P. Braaten, Senior Reactor Inspector

E. Coffman, Reactor Inspector

L. Jones, Senior Reactor Inspector

M. Singletary, Reactor Inspector

Approved By:

Scott M. Shaeffer, Chief

Engineering Branch 2

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Catawba Nuclear Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21N.05 - Fire Protection Team Inspection (FPTI)

Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)===

The inspectors verified that the following systems credited in the approved fire protection program could perform their licensing basis function:

(1)a. Review deficiencies or open fire protection impairments for the selected system, including any temporary modifications, operator workarounds, or compensatory measures.

b. Verify that operator actions can be accomplished as assumed in the licensees FHA, or as assumed in the licensees fire probabilistic risk assessment (FPRA)analysis and SSA.

c. Review repetitive or similar maintenance work requests which could be an indicator of a design deficiency and could affect the ability of the components to perform their functions, when needed.

d. Ensure that post maintenance and/or surveillance activities are performed as scheduled.

e. Perform a walkdown inspection to identify equipment alignment discrepancies.

Inspect for deficient conditions such as corrosion, missing fasteners, cracks, and degraded insulation.

f. Ensure the selected SSCs that are subject to aging management review (AMR)pursuant to 10 CFR Part 54 are being managed for aging (e.g., loss of material, cracking, reduction of heat transfer) in accordance with appropriate aging management programs. Verify that the licensees aging management program activities (such as, Fuel Oil Analysis or Selective Leaching Aging Management Program) associated with FP equipment are being implemented.

g. If a review of operating experience issues will be completed for the selected inspection sample, verify that the licensee adequately reviewed and dispositioned the operating experience in accordance with their processes.

The team selected the following SSCs as samples:

  • Automatic Sprinkler System in room (2)
  • Unit 2 Component Cooling Water System (KC Pumps)

(3)

  • Unit 2 Battery

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the following fire protection program administrative controls were implemented in accordance with the current licensing basis:

(1)

  • Fire Brigade Training Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors reviewed the following changes to ensure that they did not constitute an adverse effect on the ability to safely shutdown post-fire and to verify that fire protection program documents and procedures affected by the changes were updated.

(1)

  • Engineering Change (EC)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On March 12, 2021, the inspectors presented the triennial fire protection inspection results to Robert T. Simril and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection Procedure

Type

Designation

Description or Title

Revision or Date

71111.21N.05

Calculations

71111.21N.05

CNC-1223.04-00-0119

CNS Units 1 and 2

RCPs NFPA-805 Loss

of Seal Cooling Analysis

Rev. 0

CNC-1223.49-02-0018

Fire Protection Piping

Friction Losses

Rev. 0

CNC-1435.00-00-0080

NFPA 13 Code

Conformance Review

for KC Pump Sprinkler

System

Rev. 0

CNS-1599.RF-00-0001

Fire Protection System

(RF/RY) Design Basis

Specification

Rev. 026

Corrective Action

Documents 71111.21N.05

2364078

Site Fire Protection

Engineers to Review IN 20-04

01/06/2021

Corrective Action

Documents Resulting

from Inspection

71111.21N.05

AR 02372737

NRC FP Insp - Calc

date reference has

editorial error

03/04/2021

AR 02373641

EC Reference Revised

03/10/2021

AR 02373895

NRC FP Insp.

Observation from NRC

Insp Team

03/12/2021

Drawings 71111.21N.05

CN-1705 Series

25V DC VITAL

INSTRUMENTATION

AND CONTROL

POWER SYSTEM

(EPL)

- 17

CN-2702-05.02

One Line Diagram

Essential and Blackout

Auxiliary Power

Systems 4.16KV/600V

06/11/2015

CNEE-0111-01.32-02

Elementary Diagram

MCC SMXG COMPT

F05C

SSF

PZR HTR GRP

Rev. 9

CNEE-0211-01.32.02

Elementary Diagram

MCC SMXG COMPT

RO5B SSF PZR HTR

GRP

Rev. 6

CNM-2206.09-0003.001

Unit 2 Component

Cooling Pump

Autosprinkler System S

Plans and Details

Rev. 014

Engineering Evaluations

71111.21N.05

Circuit Analysis Report

1ILE-SSSPZRHTRD

Circuit Analysis Report

CNC -1381.05-00-0251

Units 1 and 2 NFPA 805

Circuit Breaker and

Fuse Coordination

Study

Rev. 33

CNC-1435.00-00-0044

Fire Protection Nuclear

Safety Capability

Assessment

Rev. 003

CNC-1435.00-00-0067

NFPA 805 Transition -

Fire Risk Evaluation

(FRE)

Rev. 004

Miscellaneous

71111.21N.05

600V MCC Load list

600V MCC Load list

CNS-1465.00-00-0006

Fire Protection Design

Bases Document

Rev. 28

CNWT-1752-03.17

Wire Tabulation

09/24/2020

DUKE-QAPD-001

Topical Report - Quality

Assurance Program

Description Operating

Fleet

Rev. 46

PRR-02307136

Revision Summary (and

basis) for

ABG/0/5500/045

Rev. 004

Procedures 71111.21N.05

AP-0-A-5500-020

Loss of Nuclear Service

Water

Rev. 049

AP-0-A-5500-045

Plant Fire

Rev. 017

AP-1-A-5500-017

Loss of Control Room

Rev. 061

CNC-1435.00-00-0068

NFPA 805 Transition

Recovery Action

Feasibility Review

Rev. 003

OP-0-B-6100-013

Standby Shutdown

Facility Operations

Rev. 057

PT-0-A-4400-001-J

Spray Valve Sprinkler

System Functional Test

Rev. 030

PT-0-A-4700-061

Time Critical Actions /

Time Sensitive Actions

Rev. 009

Radiation Surveys

71111.21N.05

IP/0/A/3850/023

Molded Case Circuit

Breaker Inspection and

Testing Procedure

Rev. 134

Work Orders

71111.21N.05

Work Order 20170423

2NV - Cal Standby

Makeup Discharge

05/30/2018

Work Order Package

20189513 01

Calibration Pressurizer

Instrumentation

2/01/2018