IR 05000016-08-009, on 08/27/2008 & 08/28/2008, Enrico Fermi Unit 1, Routine Decommissioning Inspection Included Reviews of Facility Management and Control, and Radiological SafetyML082682136 |
Person / Time |
---|
Site: |
Fermi |
---|
Issue date: |
09/24/2008 |
---|
From: |
Lipa C A NRC/RGN-III/DNMS/DB |
---|
To: |
Plona J H Detroit Edison |
---|
References |
---|
IR-08-009 |
Download: ML082682136 (11) |
|
Similar Documents at Fermi |
---|
Category:Inspection Report
MONTHYEARIR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 IR 05000341/20220042023-06-22022 June 2023 Non-Concurrence on Fermi Power Plant, Unit 2 - Integrated Inspection Report 05000341/2022004 IR 05000341/20220102023-06-21021 June 2023 Reissue Fermi Power Plant, Unit 2, Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20234022023-05-0101 May 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000341/2023402 IR 05000341/20230112023-04-0606 April 2023 Triennial Fire Protection Inspection Report 05000341/2023011 IR 05000341/20234012023-03-17017 March 2023 Security Baseline Inspection Report 05000341/2023401 IR 05000341/20220062023-03-0101 March 2023 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2022006) ML23039A1552023-02-14014 February 2023 Integrated Inspection Report 05000341/2022004 IR 05000341/20224032023-02-13013 February 2023 Security Baseline Inspection Report 05000341/2022403 ML22313A1032022-11-0909 November 2022 Design Basis Assurance Inspection (Teams) Inspection Report 05000341/2022010 IR 05000341/20220032022-11-0808 November 2022 Integrated Inspection Report 05000341/2022003 IR 05000016/20220012022-11-0808 November 2022 NRC Inspection Report No. 05000016/2022001(DRSS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20224202022-11-0101 November 2022 Security Baseline Inspection Report 05000341/2022420 IR 05000341/20225012022-10-17017 October 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2022501 IR 05000341/20220052022-08-25025 August 2022 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2022005) IR 05000341/20220022022-08-0404 August 2022 Integrated Inspection Report 05000341/2022002 IR 05000341/20220012022-05-0909 May 2022 Integrated Inspection Report 05000341/2022001 IR 05000341/20224012022-03-21021 March 2022 Security Baseline Inspection Report 05000341/2022401 IR 05000341/20210062022-03-0202 March 2022 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2021006) IR 05000341/20210042022-02-0707 February 2022 Integrated Inspection Report 05000341/2021004 IR 05000341/20210132021-12-17017 December 2021 Temporary Instruction 2515/194 Inspection Report 05000341/2021013 IR 05000016/20210012021-12-13013 December 2021 Subject: NRC Inspection Report No. 050-00016/2021-001 (DNMS) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20214022021-12-0909 December 2021 Security Baseline Inspection Report 05000341/2021402 IR 05000341/20210122021-12-0707 December 2021 Biennial Problem Identification and Resolution Inspection Report 05000341/2021012 IR 05000341/20210032021-10-28028 October 2021 Integrated Inspection Report 05000341/2021003 IR 05000341/20215012021-10-21021 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2021501 IR 05000341/20214032021-09-0808 September 2021 Material Control and Accounting Program Inspection Report 05000341/2021403 IR 05000341/20210052021-09-0101 September 2021 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2021005) IR 05000341/20210112021-08-25025 August 2021 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000341/2021011 IR 05000341/20210022021-08-0606 August 2021 Integrated Inspection Report 05000341/2021002 IR 05000341/20213012021-07-13013 July 2021 NRC Initial License Examination Report 05000341/2021301 IR 05000341/20214012021-06-0707 June 2021 Security Baseline Inspection Report 05000341/2021401 IR 05000341/20210012021-05-0404 May 2021 Integrated Inspection Report 05000341/2021001 IR 05000341/20210102021-05-0303 May 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000341/2021010 IR 05000341/20203022021-03-18018 March 2021 NRC Initial License Examination Report 05000341/2020302 IR 05000341/20200062021-03-0404 March 2021 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2020006) IR 05000341/20200042021-02-10010 February 2021 Integrated Inspection Report 05000341/2020004 IR 05000016/20200012021-01-12012 January 2021 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2020001 (DNMS) IR 05000341/20204022020-11-12012 November 2020 Security Baseline Inspection Report 05000341/2020402 IR 05000341/20200102020-11-0505 November 2020 Confirmatory Action Letter Followup Inspection Report 05000341/2020010 and Closure IR 05000341/20200032020-11-0303 November 2020 Integrated Inspection Report 05000341/2020003 IR 05000341/20200122020-10-19019 October 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000341/2020012 IR 05000341/20204012020-10-13013 October 2020 Security Baseline Inspection Report 05000341/2020401 2024-02-05
[Table view] Category:Inspection Report Correspondence
MONTHYEARIR 05000341/20224012022-03-21021 March 2022 Security Baseline Inspection Report 05000341/2022401 IR 05000341/20214022021-12-0909 December 2021 Security Baseline Inspection Report 05000341/2021402 IR 05000341/20215012021-10-21021 October 2021 Emergency Preparedness Biennial Exercise Inspection Report 05000341/2021501 IR 05000341/20164062016-07-14014 July 2016 Cyber Security Problem and Identification Inspection Report 05000341/2016406 - Cover Letter Only IR 05000341/20155012016-02-0303 February 2016 NRC Emergency Preparedness Annual Inspection Report No. 05000341/2015501 IR 05000034/20104052010-02-17017 February 2010 Cover Letter for IR Fermi 2 Nuclear Power Station - NRC ISFSI Security Inspection Report 0500034/2010405(DNMS) ML0909103282009-04-0101 April 2009 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000341-09-004 IR 05000016/20080092008-09-24024 September 2008 IR 05000016-08-009, on 08/27/2008 & 08/28/2008, Enrico Fermi Unit 1, Routine Decommissioning Inspection Included Reviews of Facility Management and Control, and Radiological Safety IR 05000341/20075012008-02-14014 February 2008 IR 05000341-07-501, and IR 05000341-07-403, on 12/31/2007, for Fermi, Emergency Preparedness Annual and Security Annual Inspection Report IR 05000341/20060122006-09-12012 September 2006 IR 05000341-06-012 Cover Letter IR 05000341/20020022002-03-0404 March 2002 IR 05000341/2002-002(DRP), Detroit Edison Company, Fermi 2 Nuclear Power Station, on 12/30/2001- 02/15/2002. No Violations Issued IR 05000341/20010172002-01-16016 January 2002 IR 05000341/2001-017(DRP), Detroit Edison Company, Fermi 2 Nuclear Power Station, Inspection on 11/17-12/29/2001 Re Maintenance Risk Assessments and Emergent Work Evaluation. Two Noncited Violations 2022-03-21
[Table view] |
Inspection Report - Fermi - 2008009 |
---|
|
|
Text
September 24, 2008
Mr. Joseph Plona Site Vice President Nuclear Generation The Detroit Edison Company 6400 North Dixie Highway Newport, MI 48166
SUBJECT: NRC INSPECTION REPORT 050-00016/08-09(DNMS)
- ENRICO FERMI UNIT 1
Dear Mr. Plona:
On August 28, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the Enrico Fermi Unit 1 facility. The purpose of the inspection was to determine whether decommissioning activities were conducted safely and in accordance with NRC requirements in the areas of facility management and control, and radiological safety. At the conclusion of the inspection on August 28, 2008, the NRC inspector discussed the findings with members of your staff. The inspection consisted of an examination of activities at the facility as they relate to safety and compliance with the Commission's rules and regulations. Areas examined during the inspection are identified in the enclosed report. Within these areas, the inspection consisted of a selective examination of procedures and representative records, field observations of activities in progress, and interviews with personnel. Based on the results of this inspection, the NRC did not identify any violations. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). The NRC's document system is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html. We will gladly discuss any questions you have concerning this inspection.
Sincerely,/RA/ Christine Lipa, Chief Decommissioning Branch Docket No. 050000016 License No. DPR-9
Enclosure:
Inspection Report 050-00016/2008-009(DNMS)
cc w/encl: