ML090910328
| ML090910328 | |
| Person / Time | |
|---|---|
| Site: | Fermi |
| Issue date: | 04/01/2009 |
| From: | Ann Marie Stone NRC/RGN-III/DRS/EB2 |
| To: | Jennifer Davis Detroit Edison |
| References | |
| IR-09-004 IR-09-004 | |
| Download: ML090910328 (8) | |
See also: IR 05000341/2009004
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE ROAD, SUITE 210
LISLE, IL 60532-4352
April 1, 2009
Mr. Jack M. Davis
Senior Vice President and
Chief Nuclear Officer
Detroit Edison Company
Fermi 2 - 210 NOC
6400 North Dixie Highway
Newport, MI 48166
SUBJECT:
FERMI POWER PLANT, UNIT 2 - NOTIFICATION OF AN NRC TRIENNIAL
HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR
INFORMATION INSPECTION REPORT 05000341/2009004
Dear Mr. Davis:
On July 6, 2009, the NRC will begin the onsite portion of the Triennial Heat Sink Performance
Inspection at your Fermi Power Plant, Unit 2. This inspection will be performed in accordance
with NRC baseline inspection procedure (IP) 71111.07.
In order to minimize the impact that the inspection has on the site and to ensure a productive
inspection, we have enclosed a request for documents needed for the inspection. The
documents have been divided into three groups.
The first group lists information necessary for our initial inspection scoping activities.
This information should be available to the lead inspector no later than May 22, 2009. By
May 29, 2009, the inspector will communicate the initial selected set of approximately 2-3
risk significant heat exchangers.
The second group of documents requested is those items needed to support our in-office
preparation activities. This set of documents, including the calculations associated with
the selected heat exchangers, should be available at the Regional Office no later than
June 19, 2009. This information should be separated for each selected component,
especially if provided electronically (e.g., folder with component name that includes
calculations, condition reports, maintenance history, etc.). During the in-office preparation
activities, the inspector may identify additional information needed to support the
inspection.
The last group includes the additional information above as well as plant specific reference
material. This information should be available onsite to the inspector on July 6, 2009. It is
also requested that corrective action documents and/or questions developed during the
inspection be provided to the inspector as the documents are generated.
J. Davis
-2-
The lead inspector for this inspection is Gerard ODwyer. If there are questions about the
material requested, or the inspection, please call Gerard ODwyer at (630) 829-9624. Please
send the information to the following e-mail address: Gerard.ODwyer@nrc.gov. A hard-copy
with the required information is also an acceptable option.
It is important that these documents be as complete as possible, in order to minimize the
number of documents requested during the preparation week or during the onsite inspection.
All requested documents are to be for the time period from the onsite inspection period back to
the last Heat Sink Performance Inspection. If no activities were accomplished in that time
period, then the request applies to the last applicable document in the previous time period.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be available electronically for public inspection in the NRC Public Document
Room or from the Publicly Available Records (PARS) component of NRC's document system
(ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
Sincerely,
/RA by C. E. A. Tilton Acting For/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-341
License No. NPF-43
Enclosure:
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT
REQUEST
cc w/encl:
J. Plona, Vice President,
Nuclear Generation
K. Hlavaty, Plant Manager
R. Gaston, Manager, Nuclear Licensing
D. Pettinari, Legal Department
Michigan Department of Environmental Quality
G. Williams, Director, Monroe County
Emergency Management Division
Supervisor - Electric Operators
T. Strong, State Liaison Officer
Wayne County Emergency Management Division
J. Davis
-2-
The lead inspector for this inspection is Gerard.ODwyer. If there are questions about the material
requested, or the inspection, please call Gerard ODwyer at (630) 829-9624. Please send the
information to the following e-mail address: Gerard.ODwyer@nrc.gov. A hard-copy with the required
information is also an acceptable option.
It is important that these documents be as complete as possible, in order to minimize the number of
documents requested during the preparation week or during the onsite inspection. All requested
documents are to be for the time period from the onsite inspection period back to the last Heat Sink
Performance Inspection. If no activities were accomplished in that time period, then the request applies
to the last applicable document in the previous time period.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure
will be available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from
the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA by C. E. A. Tilton Acting For/
Ann Marie Stone, Chief
Engineering Branch 2
Division of Reactor Safety
Docket No. 50-341
License No. NPF-43
Enclosure:
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
cc w/encl:
J. Plona, Vice President,
Nuclear Generation
K. Hlavaty, Plant Manager
R. Gaston, Manager, Nuclear Licensing
D. Pettinari, Legal Department
Michigan Department of Environmental Quality
G. Williams, Director, Monroe County
Emergency Management Division
Supervisor - Electric Operators
T. Strong, State Liaison Officer
Wayne County Emergency Management Division
DOCUMENT NAME: G:\\DRS\\Work in Progress\\Ltr. 040109 FERM HS 2009-004 RFI.doc
9 Publicly Available
9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive
To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy
OFFICE RIII
RIII
NAME
CTilton for GODwyer:ls
CTilton for AMStone
DATE
04/01/09
04/01/09
OFFICIAL RECORD COPY
Letter to Mr. Jack M. Davis from Ms. Ann Marie Stone dated April 1, 2009.
SUBJECT:
FERMI POWER PLANT, UNIT 2 - NOTIFICATION OF AN NRC TRIENNIAL
HEAT SINK PERFORMANCE INSPECTION AND REQUEST FOR
INFORMATION INSPECTION REPORT 05000341/2009-004
DISTRIBUTION:
RidsNrrDorlLpl3-1
RidsNrrPMFermi2 Resource
RidsNrrDirsIrib Resource
Mark Satorius
Kenneth Obrien
DRPIII
DRSIII
Patricia Buckley
ROPreports Resource
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Enclosure
1
Inspection Report: 05000341/2009004
Inspection Dates:
July 6 - 10, 2009
Inspection Procedure:
IP 71111.07, Heat Sink Performance
Lead Inspector:
Gerard ODwyer, Lead Inspector
(630) 829-9864
Gerard.ODwyer@nrc.gov
I.
Information Requested By May 22, 2009
1. List of the Generic Letter (GL) 89-13, Service Water System Problems Affecting
Safety-Related Equipment, heat exchangers in order of risk significance.
2. Copy of heat exchanger performance trending data tracked for each GL 89-13 heat
exchanger.
3. List of corrective action program documents (with a short description) associated
with GL 89-13 heat exchangers, heat sinks, silting, corrosion, fouling, or heat
exchanger testing, for the previous two years or since the last heat sink performance
inspection.
4. Copy of any self-assessment done on any of GL 89-13 heat exchangers.
5. System health report(s) and maintenance rule system notebooks for all the GL 89-13
heat exchangers.
II.
Information Requested By June 19, 2009
1. For the specific heat exchangers selected:
a. Copies of the two most recent completed tests and evaluation of data confirming
thermal performance for those heat exchangers which are performance tested.
b. Copy of system description and design basis document for the heat exchangers
(as applicable).
c. Copy of any operability determinations or other documentation of degradation
associated with the heat exchangers or the systems that support the operation
for the selected heat exchangers.
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Enclosure
2
d. Copy of the Updated Final Safety Analysis Report (UFSAR) sections applicable
for each heat exchanger.
e. Provide a list of calculations with a description which currently apply to each heat
exchanger.
2. A schedule of all inspections, cleanings, maintenance, or testing of any plant heat
exchanger to be done during the onsite portion of the inspection.
3. Copies of procedures developed to implement the recommendations of GL 89-13,
e.g., the GL 89-13 Heat Exchanger Program description.
4. Pages from the UFSAR for the GL 89-13 Heat Exchanger Program.
5. Maximum cooling water system inlet temperature limit that still allows full licensed
power operation of the nuclear reactor. Please provide the document that states this
limit (e.g., UFSAR or Technical Requirements Manual (TRM)) and the operating
procedure that ensures this limit is not exceeded.
III.
Information Requested to be Available on First Day of Inspection, July 6, 2009
1. For the specific heat exchangers selected:
a. Copy of the design specification and heat exchanger data sheets for each heat
exchanger.
b. Copy of the vendor manuals including component drawings for each heat
exchanger.
c. Copy of the calculation which establishes the limiting (maximum) design basis
heat load which is required to be removed by each of these heat exchangers.
d. Copy of the calculation which correlates surveillance testing results from these
heat exchangers with design basis heat removal capability (e.g., basis for
surveillance test acceptance criteria).
e. Copy of the calculations or documents which evaluate the potential for water
hammer or excessive tube vibration in the heat exchanger or associated piping.
f. List of engineering-related Operator Workarounds/Temporary Modifications for
these heat exchangers since the last Heat Sink Performance Inspection.
g. Documentation and procedures that identify the types, accuracy, and location of
any special instrumentation used for the two most recently completed thermal
performance tests for the heat exchangers (e.g., high accuracy ultrasonic flow
instruments or temperature instruments). Include calibration records for the
instruments used during these tests.
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Enclosure
3
h. Copies of those documents that describe the methods taken to control water
chemistry in the heat exchangers.
i.
Copies of the documents that verify the structural integrity of the heat exchanger,
e.g., eddy current summary sheets, ultrasonic testing results, and visual
inspection results.
j.
The cleaning and inspection maintenance schedule for each heat exchanger for
the next 5 years.
k. Copy of the document describing the inspection results for the last two clean and
inspection activities completed on each heat exchanger.
l.
Copy of the document which identifies the current number of tubes in service for
each heat exchanger and the supporting calculation which establishes the
maximum number of tubes which can be plugged in each heat exchanger.
m. Copy of the document establishing the repair criteria (plugging limit) for degraded
tubes which are identified in each heat exchanger.
n. Information regarding any alarms which monitor on-line performance.
2. For the ultimate heat sink (UHS):
a. Maintenance or inspection records of inaccessible below-water portions of the
UHS system including results of underwater diving inspections and assessments
of sediment intrusion and/or removal of sediment.
b. Inspections and/or maintenance related to preventing macrofouling (silt, dead
mussel shells, debris, etc.) and aquatic life such as fish, algae, grass, or kelp.
c. Inspections and/or maintenance related to preventing biotic fouling.
d. Copies of chemistry procedures and surveillances that monitor for pH, calcium
hardness, etc.
e. Copies of any design changes performed on the system.
f. Copies of procedures for a loss of UHS.
3. For the service water system:
a. Copies of any design changes performed on the system.
b. Copies of procedures for a loss of service water system.
TRIENNIAL HEAT SINK PERFORMANCE INSPECTION DOCUMENT REQUEST
Enclosure
4
c. Copies of inspections and/or maintenance related to macrofouling (silt, dead
mussel shells, debris, etc.) and aquatic life such as fish, algae, grass, or kelp.
d. Copies of inspections and/or maintenance related to preventing biotic fouling.
e. Copies of chemistry procedures and surveillances that monitor for pH, calcium
hardness, etc.
f. Analysis of safety-related service water weak-strong pump interactions.
If the information requested above will not be available, please contact Inspector ODwyer as
soon as possible at (630) 829-9624 or email Gerard.ODwyer@nrc.gov.