Monticello - License Amendment Request for Areva Extended Flow Window Supplement to Respond to NRC Staff Questions
ML15022A165
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 01/09/2015
From: Fili K D
Northern States Power Co, Xcel Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML15022A162 List:
References
L-MT-14-103, TAC MF5002
Download: ML15022A165 (3)


Text

ENCLOSURES 1, 3,4, 5 CONTAIN PROPRIETARY INFORMATION WITHHOLD FROM PUBLIC DISCLOSURE IN ACCORDANCE WITH 10 CFR 2.390 XcelEnergy Monticello Nuclear Generating Plant 2807 W County Rd 75 Monticello, MN 55362 January 9, 2015 L-MT-14-103 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Monticello Nuclear Generating Plant Docket 50-263 Renewed License No. DPR-22 License Amendment Request for AREVA Extended Flow Window Supplement to Respond to NRC Staff Questions (TAC No. MF5002)

References:

1) Letter from Karen D. Fili (NSPM), to Document Control Desk (NRC),"License Amendment Request for AREVA Extended Flow Window," L-MT-14-044, dated October 3, 2014. (ADAMS Accession No.ML14283A125)
2) Email T. Beltz (NRC) to G. Adams (NSPM), "Monticello Nuclear Generating Plant -Acceptance Review (Opportunity to Supplement) re: AREVA Extended Flow Window License Amendment Request (TAC No. MF5002)," dated December 10, 2014.In Reference 1, Northern States Power Company, a Minnesota corporation (NSPM), doing business as Xcel Energy, requested approval of an amendment to the Monticello Nuclear Generating Plant (MNGP) Renewed Operating License (OL) and Technical Specifications (TS). The proposed change would revise TS and would approve certain analytical methods that together would support operation in the expanded power-flow operating domain described as the Extended Flow Window (EFW). The purpose of the requested amendment is to transition from the General Electric methodology called Maximum Extended Load Line Limit Analysis Plus (MELLLA+)

to-the AREVA methodology called EFW.In Reference 2, NRC Staff identified further information that was required to support their acceptance review. The correspondence stated that the submitted LAR could be supplemented to provide the required information.

The purpose of this supplement is to provide the required information.

The general approach to this supplement was discussed with NRC Staff in a telephone conference on December 2, 2014.I)A_(

Document Control Desk Page 2 Enclosure 1 provides AREVA Report ANP-3376P, Revision 0, which provides reply to the questions posed in Reference

2. Enclosure 1 is proprietary to AREVA.Enclosure 2 provides the non-proprietary AREVA Report ANP-3376NP, Revision 0.The nonproprietary report is being provided based on the NRC's expectation that the submitter of the proprietary information should provide, if.possible, a nonproprietary version of the document with brackets showing where the proprietary information has been deleted.Enclosure 3 provides AREVA FS1 -0008928, FSQA-07-AISHA User and Programmer's Manual for BWR Transient Analysis Including Large Oscillations, Revision 2.0. This manual is proprietary in its entirety.Enclosure 4 provides AREVA FS1-0008916, FSQA-07-SINANO User's and Programmer's Manual, Revision 2.0. This manual is proprietary in its entirety.Enclosure 5 provides AREVA Report EMF-2279(P), Revision 0, STAIF: A Computer Program for BWR Stability in the Frequency Domain -Theory Manual, dated September 2001. This manual is proprietary in its entirety.Enclosure 6 provides affidavits executed to support withholding Enclosures 1, 3, 4, and 5 from public disclosure.

These Enclosures contain proprietary information as defined by 10 CFR 2.390. The affidavit sets forth the basis on which the information may be withheld from public disclosure by the NRC and addresses with specificity the considerations listed in 10 CFR 2.390(b)(4).

Accordingly, NSPM respectfully requests that the AREVA proprietary information in Enclosures 1, 3, 4, and 5 be withheld from public disclosure in accordance with 10 CFR 2.390(a)4, as authorized by 10 CFR 9.17(a)4.Correspondence with respect to the copyright or proprietary aspects of the AREVA information in Enclosure 4 or the supporting AREVA affidavits in Enclosure 6 should be addressed to Mr. Alan Meginnis, Manager- Product Licensing, AREVA Inc., 2101 Horn Rapids Road, Richland, Washington 99354.The information offered herein does not affect the conclusions of the Significant Hazards Consideration and the Environmental Consideration evaluations provided in the Reference 1 LAR.In accordance with 10 CFR 50.91(b), a copy of this application supplement is being provided to the designated Minnesota Official without enclosures.

If there are any questions or if additional information is needed, please contact Glenn Adams at 612-330-6777.

Document Control Desk Page 3 Summary of Commitments This letter makes no new commitments and no revisions to existing commitments.

I declare under penalty of perjury that the foregoing is true and correct.Executed on: January 9, 2015 Kar4- D. Fili Site Vice-President Monticello Nuclear Generating Plant Northern States Power Company-Minnesota Enclosures (6)cc: Administrator, Region III, USNRC Project Manager, Monticello Nuclear Generating Plant, USNRC Resident Inspector, Monticello Nuclear Generating Plant, USNRC Minnesota Department of Commerce (w/o enclosures)