|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commission'S Analysis of ADP CR3, Llc'S Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] |
Text
April 1, 2015 Andrew Mitchell, Director Technological Hazards Division Federal Emergency Management Agency 1800 South Bell Street Arlington, VA 20598-3025
SUBJECT:
EXEMPTION OF CRYSTAL RIVER NUCLEAR GENERATING STATION (UNIT 3) FROM OFF-SITE EMERGENCY PLANNING REQUIREMENTS
Dear Mr. Mitchell:
This is to notify you that on March 30, 2015, the U.S. Nuclear Regulatory Commission (NRC) granted an exemption to Duke Energy Florida, Inc. (DEF) from certain emergency planning requirements in Section 50.47, "Emergency plans," and Appendix E, "Emergency Planning and Preparedness for Production and Utilization Facilities," to Title 10 of the Code of Federal Regulations (10 CFR) Part 50, thereby allowing DEF to discontinue off-site radiological emergency planning activities and reduce the scope of its on-site emergency planning at the Crystal River Unit 3 Nuclear Generating Plant (CR-3). A copy of the NRC's safety evaluation (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15058A906) for the requested exemption is enclosed.
CR-3 is a decommissioning power reactor located at Red Level, Florida in Citrus County, about 5 miles south of Levy County. The site is 7.5 miles northwest of Crystal River, Florida and 90 miles north of St. Petersburg, Florida. CR-3 is situated on the Gulf of Mexico, within the Crystal River Energy Complex. The 10 CFR Part 50 license for CR-3 no longer authorizes operation of the reactor or emplacement or retention of fuel into the reactor vessel, as specified in 10 CFR 50.82(a)(2). DEF is authorized to possess and store spent nuclear fuel at the permanently shutdown and defueled CR-3 facility. Spent fuel is currently stored on-site at CR-3 in a spent fuel pool. The regulations that require each nuclear power reactor licensee to establish and maintain emergency plans and preparedness are set forth in 10 CFR 50.47, and Appendix E to 10 CFR Part 50. The regulations include standards for both on-site and off-site radiological emergency plans. However, when compared to an operating nuclear power plant, the regulations do not take into account the reduced risk of an off-site radiological release at a permanently shutdown and defueled power reactor. The NRC concluded that the emergency planning requirements for CR-3, as modified by the exemptions described in the enclosed safety evaluation, would provide: (1) an adequate basis for an acceptable state of emergency preparedness; and (2) in conjunction with arrangements made with off-site response agencies, reasonable assurance that adequate protective measures can and will be taken in the event of a radiological emergency at CR-3.
In light of the exemption granted to DEF, the NRC no longer requires the Federal Emergency Management Agency (FEMA) to monitor, review, or report on off-site radiological emergency planning and preparedness activities at CR-3, in accordance with the memorandum of understanding between FEMA and the NRC as contained in Appendix A to 44 Part 353. Emergency planning and preparedness will be limited to on-site activities; notification of off-site authorities in event of an emergency classification; requiring only on-site exercises with the opportunity for off-site response organization participation; and only maintaining arrangements for off-site response organizations (i.e., law enforcement, fire and medical services) that may respond to on-site emergencies as identified in the licensee's permanently defueled emergency plan.
We request that FEMA notify the appropriate State and local governments that the off-site radiological emergency plans, required by 44 CFR 350, will no longer be required for the CR-3 site due to the permanent shut down and defueled condition of the facility. Should you need more information or support in interfacing with State and local government officials on this manner, please contact Joseph Anderson of my staff at (301) 287-9300. Sincerely, /RA/ Robert J. Lewis, Director Division of Preparedness and Response Office of Nuclear Security and Incident Response
Enclosure:
Letter to Terry Hobbs - Crystal River Nuclear Plant - Exemptions from certain emergency planning requirements and related safety evaluation (TAC No. MF 2981) cc: T. Greten, FEMA V. Quinn, FEMA A. Coons, FEMA
Pkg. ML15085A258 Letter: ML15085A241
Enclosure:
ML15058A906 OFFICE: TL:NSIR/DPR/ORLOB BC:NSIR/DPR/ORLOB D:NSIR/DPR NAME: MNorris JAnderson RLewis DATE: 03/27/15 03/27/15 03/27/15