MONTHYEARIR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 IR 05000315/20230062024-02-28028 February 2024 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2023006 and 05000316/2023006) ML23310A1152023-11-0606 November 2023 Notification of the NRC Baseline Inspection and Request for Information, Inspection Report 05000316/2024002 ML23242A1832023-08-30030 August 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report05000315/2023004 IR 05000315/20230052023-08-24024 August 2023 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2023005 and 05000316/2023005) IR 05000315/20234042023-05-11011 May 2023 D.C. Cook Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000315/2023404 and 05000316/2023404 ML23076A0212023-03-20020 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection; Inspection Report 05000315/2023011; 05000316/2023011 ML23066A1882023-03-0707 March 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Donald C. Cook Nuclear Plant IR 05000315/20220062023-03-0101 March 2023 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022006 and 05000316/2022006) IR 05000315/20220052022-08-24024 August 2022 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2022005 and 05000316/2022005) ML22130A1722022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20210062022-03-0202 March 2022 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021006 and 05000316/2021006) ML21309A3322021-11-0505 November 2021 Notification of Nrc Fire Protection Team Inspection Request for Information IR 05000315/20210052021-09-0101 September 2021 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2021005 and 05000316/2021005) ML21146A2862021-05-26026 May 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Donald C. Cook Nuclear Plant ML21068A3512021-03-0909 March 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2021002; 05000316/2021002 IR 05000315/20200062021-03-0404 March 2021 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020006 and 05000316/2020006) IR 05000315/20214012021-01-12012 January 2021 Information Request for the Cyber-Seruity Full Implementation Inspection, Notification to Perform Inspection 05000315/2021401; 05000316/2021401 IR 05000315/20200112020-09-17017 September 2020 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000315/2020011; 05000316/2020011 IR 05000315/20200052020-09-0101 September 2020 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2020005 and 05000316/2020005) ML20133J9722020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000315/20200202020-04-10010 April 2020 Units 1 and 2 - Information Request for NRC Triennial Evaluation of Changes, Tests, and Experiments (50.59) Baseline Inspection 05000315/2020020 and 05000316/2020020 IR 05000315/20190062020-03-0303 March 2020 Annual Assessment Letter for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019006 and 05000316/2019006) ML20016A3842020-01-16016 January 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000315/20204102019-11-19019 November 2019 Information Request for the Cyber Security Full Implementation Inspection, Notification to Perform Inspection 05000315/2020410; 05000316/2020410 IR 05000315/20190052019-08-28028 August 2019 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2019005 and 05000316/2019005) ML19192A1552019-07-11011 July 2019 Ltr. 07/11/19 Donald C. Cook Nuclear Power Plant, Unit 2 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019004; 05000316/2019004 (DRS-M.Holmberg) ML19128A3482019-05-0808 May 2019 Ltr. 05/08/19 Donald C. Cook Nuclear Power Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000315/2019012; 05000316/2019012 (DRS-A.Shaikh) ML19078A3732019-03-19019 March 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000315/20180062019-03-0404 March 2019 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018006 and 05000316/2018006) ML19037A3842019-02-0404 February 2019 Ltr. 02/04/19 Donald C. Cook Nuclear Power Plant, Unit 1 - Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000315/2019001; 05000316/2019001 (DRS-E.Fernandez) IR 05000315/20180052018-08-28028 August 2018 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2018005 and 05000316/2018005) IR 05000315/20170062018-03-0202 March 2018 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017006; 05000316/2017006) ML18058B6192018-02-27027 February 2018 Inspection Plan for Donald C. Cook, Unit 2, for Inservice Inspection Activities; Inspection Report 05000316/2018002 (DRS-L.Smith) IR 05000315/20170052017-08-28028 August 2017 Updated Inspection Plan for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2017005; 05000316/2017005) ML17076A3592017-03-17017 March 2017 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000315/2017002; 05000316/2017002 (Lnr) IR 05000315/20160062017-03-0101 March 2017 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016006; 05000316/2016006) IR 05000315/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2016005; 05000316/2016005) ML16211A0322016-07-28028 July 2016 Request for Inforamtion for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000316/2016010 IR 05000315/20150062016-03-0202 March 2016 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2(Report 05000315/2015006 and 05000316/2015006) ML16013A1832016-01-12012 January 2016 Notification of NRC Inspection and Request for Information (Jen) IR 05000315/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 (Report 05000315/2015005; 05000316/2015005) IR 05000315/20140012015-03-0404 March 2015 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2014001 and 05000316/2014001) ML14317A5892014-11-13013 November 2014 Notification of NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection 05000315/2015002; 05000316/2015002 ML14245A2562014-09-0202 September 2014 Mid-Cycle Assessment Letter for Donald C. Cook Nuclear Power Plant, Units 1 and 2 IR 05000316/20130012014-03-0404 March 2014 Annual Assessment Letter for Donald C. Cook Nuclear Power Plant, Unit 1 and 2 (Report 05000351/2013001; 05000316/2013001) ML14024A4762014-01-23023 January 2014 Information Request for a NRC Post-Approval Site Inspection for License Renewal 05000315-14-007 ML13246A2272013-09-0303 September 2013 2013 Donald C. Cook Mid-Cycle Letter Combined IR 05000315/20120012013-03-0404 March 2013 Annual Assessment Letter for D.C. Cook Nuclear Power Plant, Units 1 and 2, (Report 05000315/2012001 and 05000316/2012001) 2024-08-21
[Table view] Category:Letter
MONTHYEAR05000316/LER-2024-004, AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications2024-11-11011 November 2024 AB Emergency Diesel Generator Inoperable for Longer than Allowed by Technical Specifications IR 05000315/20240032024-10-31031 October 2024 Integrated Inspection Report 05000315/2024003 05000316/2024003 07200072/2024001 and Exercise of Enforcement Discretion AEP-NRC-2024-77, U2C28 Steam Generator Tube Inspection Report2024-10-21021 October 2024 U2C28 Steam Generator Tube Inspection Report AEP-NRC-2024-80, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2024-10-15015 October 2024 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-79, Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask2024-09-26026 September 2024 Unit 2, Independent Spent Fuel Storage Installation - Registration of Dry Spent Storage Cask AEP-NRC-2024-78, Reply to a Notice of Violation: EA-24-0472024-09-23023 September 2024 Reply to a Notice of Violation: EA-24-047 05000316/LER-2024-002-01, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-09-12012 September 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak IR 05000315/20244022024-09-10010 September 2024 Security Baseline Inspection Report 05000315/2024402 and 05000316/2024402, Independent Spent Fuel Storage Installation Security Inspection Report 07200072/2024401 AEP-NRC-2024-69, Core Operating Limits Report2024-09-0909 September 2024 Core Operating Limits Report IR 05000315/20243012024-09-0505 September 2024 NRC Initial License Examination Report 05000315/2024301 and 05000316/2024301 ML24225A0022024-09-0303 September 2024 Issuance of Amendment Nos. 363 and 344 Revising Technical Specifications Section 3.8.1, AC Sources-Operating, for a One-Time Extension of a Completion Time IR 05000315/20240112024-08-30030 August 2024 NRC Inspection Report 05000315/2024011 and 05000316/2024011 and Notice of Violation AEP-NRC-2024-76, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-08-28028 August 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-51, Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes2024-08-28028 August 2024 Annual Report of Loss-Of-Coolant Accident Evaluation Model Changes 05000316/LER-2024-003, Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage2024-08-22022 August 2024 Plant Shutdown Required by Technical Specifications Due to Reactor Coolant System Identified Leakage IR 05000315/20240052024-08-21021 August 2024 Updated Inspection Plan for Donald C. Cook Nuclear Plant, Units 1 and 2 (Report 05000315/2024005 and 05000316/2024005) AEP-NRC-2024-61, Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request2024-08-15015 August 2024 Unit 2 - Response to Request for Additional Information for Neutron Flux Instrumentation License Amendment Request ML24221A2702024-08-0808 August 2024 Unit 2 Independent Spent Fuel Storage Installation - Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-62, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-08-0707 August 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask ML24256A1482024-08-0202 August 2024 2024 Post Examination Submittal Letter AEP-NRC-2024-47, Form OAR-1, Owners Activity Report2024-07-30030 July 2024 Form OAR-1, Owners Activity Report ML24183A0162024-07-25025 July 2024 Review of Reactor Vessel Material Surveillance Program Capsule W Technical Report ML24169A2142024-07-25025 July 2024 Issuance of Amendment No. 362 Regarding Change to Technical Specification 3.4.12, Low Temperature Overpressure Protection System IR 05000315/20240022024-07-24024 July 2024 Integrated Inspection Report 05000315/2024002 and 05000316/2024002 ML24197A1262024-07-15015 July 2024 Unit 2 - Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 05000316/LER-2024-002, Manual Reactor Trip Following Rapid Downpower for Steam Leak2024-07-15015 July 2024 Manual Reactor Trip Following Rapid Downpower for Steam Leak ML24191A0692024-07-0909 July 2024 Operator Licensing Examination Approval - Donald C. Cook Nuclear Power Plant, July 2024 AEP-NRC-2024-56, Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask2024-07-0808 July 2024 Unit 2, Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Storage Cask AEP-NRC-2024-48, Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-07-0202 July 2024 Response to Request for Additional Information (RAI) for License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating ML24176A1012024-06-21021 June 2024 57143-EN 57143 - Paragon Energy Solutions - Update 1 (Final) - 10CFR Part 21 Final Notification: P21-05242024-FN, Rev. 0 AEP-NRC-2024-45, Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring2024-06-13013 June 2024 Report Per Technical Specification 5.6.6 for Inoperability of Post Accident Monitoring Neutron Flux Monitoring ML24163A0132024-06-12012 June 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000315/2024012 and 05000316/2024012 ML24159A2522024-05-30030 May 2024 10 CFR 50.71(e) Update and Related Site Change Reports AEP-NRC-2024-23, Core Operating Limits Report2024-05-23023 May 2024 Core Operating Limits Report ML24141A2162024-05-20020 May 2024 —Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000316/LER-2024-001, Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip2024-05-20020 May 2024 Reactor Trip Due to Main Turbine Trip from a High-High Thrust Bearing Position Trip AEP-NRC-2024-40, Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-05-16016 May 2024 Unit 2 - Supplement to License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating AEP-NRC-2024-41, Annual Radiological Environmental Operating Report2024-05-15015 May 2024 Annual Radiological Environmental Operating Report IR 05000315/20240012024-05-14014 May 2024 Integrated Inspection Report 05000315/2024001 and 05000316/2024001 IR 05000315/20244012024-05-14014 May 2024 – Security Baseline Inspection Report 05000315/2024401 and 05000316/2024401 AEP-NRC-2024-26, Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 492024-05-14014 May 2024 Transmittal of Donald C. Cook Nuclear Plant, Emergency Plan Revision 49 AEP-NRC-2024-07, Unit 2 - Transmittal of Report of Changes to the Emergency Plan2024-05-14014 May 2024 Unit 2 - Transmittal of Report of Changes to the Emergency Plan AEP-NRC-2024-24, Form OAR-1, Owners Activity Report2024-05-0707 May 2024 Form OAR-1, Owners Activity Report ML24115A2152024-05-0707 May 2024 LTR: CNP Non-Acceptance with Opportunity TS 3-8-1 ML24256A1472024-05-0606 May 2024 DC Cook 2024 NRC Examination Submittal Letter: Submittal ML24116A0002024-05-0202 May 2024 – Regulatory Audit in Support of Review of the Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors AEP-NRC-2024-35, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-04-30030 April 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations AEP-NRC-2024-28, 2023 Annual Radioactive Effluent Release Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report AEP-NRC-2024-31, Annual Report of Individual Monitoring2024-04-24024 April 2024 Annual Report of Individual Monitoring AEP-NRC-2024-02, Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating2024-04-0303 April 2024 Unit 2 License Amendment Request for One-Time Extension of Completion Time for Inoperable AC Source - Operating 2024-09-09
[Table view] |
See also: IR 05000315/2024012
Text
Q. Shane Lies
Senior VP and Chief Nuclear Officer
Indiana Michigan Power Company
Nuclear Generation Group
One Cook Place
Bridgman, MI 49106
SUBJECT:
DONALD C. COOK NUCLEAR PLANT - REQUEST FOR INFORMATION FOR
THE NRC AGE-RELATED DEGRADATION INSPECTION: INSPECTION
REPORT 05000315/2024012 and 05000316/2024012
Dear Q. Shane Lies:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
staff will conduct IP 71111.21N.04, Age-Related Degradation baseline inspection at Donald C.
Cook Nuclear Plant, Units 1 and 2, beginning October 21, 2024. The inspection will be
conducted in accordance with IP 71111.21N.04, dated December 15, 2023.
The schedule for the inspection is as follows:
- Information gathering visit - week of July 15, 2024
- On-site inspection - weeks of October 21, 2024, and November 4, 2024
The purpose of the information gathering visit is to become familiar with the station
maintenance, surveillance, testing, inspection, and condition monitoring programs, become
familiar with plant layout, support identification of structures, systems, and components (SSCs)
that will be reviewed during the inspection, and, as necessary, obtain plant-specific site access
training and badging for unescorted site access. An initial list of documents that the team will
review during the information gathering visit is listed in enclosure 1.
For SSCs that the inspection team plans to review, an initial list of the documents the team
plans to review during the conduct of the inspection are listed in enclosure 2. The team leader
will contact you with identified SSCs. Also, personnel should be available at the site during the
inspection who are knowledgeable regarding maintenance, surveillance, testing, inspection, and
condition monitoring programs.
The lead inspector for this inspection is Kevin Barclay. We understand that our regulatory
contact for this inspection is Matthew Hoholek of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at
630-829-9885 or via email at Kevin.Barclay@nrc.gov.
June 12, 2024
Q. Lies
2
This letter contains voluntary information collections that are subject to the Paperwork
Reduction Act of 1995 (44 U.S.C. 3501 et seq.). The Office of Management and Budget (OMB)
approved these information collections (approval number 3150-0011). The burden to the public
for these information collections is estimated to average 42 hours4.861111e-4 days <br />0.0117 hours <br />6.944444e-5 weeks <br />1.5981e-5 months <br /> per response. Send
comments regarding this information collection to the FOIA, Library and Information Collection
Branch, Office of the Chief Information Officer, Mail Stop: T6-A10M, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, or by email to Infocollects.Resource@nrc.gov, and
to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0011)
OMB, Washington, DC 20503.
In accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of
this letter, its enclosures, and your response (if any) will be available electronically for public
inspection in the NRCs Public Document Room or from the Publicly Available Records System
(PARS) component of NRC's Agencywide Document Access and Management System
(ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-
rm/adams.html (the Public Electronic Reading Room).
Sincerely,
Kevin Barclay, Senior Reactor Inspector
Engineering Branch 1
Division of Operating Reactor Safety
Docket Nos. 05000315 and 05000316
License Nos. DPR-58 and DPR-74
Enclosure:
1. Requested Information to Support
Age-Related Degradation Sample
Selection
2. Requested Information to Support
Age-Related Degradation Inspection
cc: Distribution via LISTSERV
Signed by Barclay, Kevin
on 06/12/24
Q. Lies
3
Letter to Q. Shane Lies from Kevin Barclay dated June 12, 2024.
SUBJECT:
DONALD C. COOK NUCLEAR PLANT - REQUEST FOR INFORMATION FOR
THE NRC AGE-RELATED DEGRADATION INSPECTION: INSPECTION
REPORT 05000315/2024012 and 05000316/2024012
DISTRIBUTION:
Michelle Simmons
RidsNrrDorlLpl3
RidsNrrPMDCCook Resource
RidsNrrDroIrib Resource
Jack Giessner
Mohammed Shuaibi
Diana Betancourt-Roldan
Allan Barker
David Curtis
Karla Stoedter
R3-DORS
ADAMS Accession Number: ML24163A013
Publicly Available
Non-Publicly Available
Sensitive
Non-Sensitive
OFFICE
RIII
NAME
KBarclay:gmp
DATE
06/12/2024
OFFICIAL RECORD COPY
Enclosure 1
Enclosure 1 - Requested Information to Support Age-Related Degradation Sample
Selection
The documents and information requested below should generally be made available to the
inspection team for the teams use both on-site and off-site during the information gathering
visit. Electronic format is the preferred media. If electronic media is made available via an
internet based remote document management system, then the remote document access
should allow inspectors to download, save, and print the documents in the NRCs regional
office. Electronic media on compact disc or paper records (hard copy) are acceptable. At the
end of the inspection, the documents in the teams possession should not be retained.
This document request is based on typical documents that a generic plant might have. As
such, this document request is not meant to imply that any specific plant is required to have
all of the listed documents. In addition, your plant-specific document titles may vary from the
document titles listed below.
The following information is requested by July 12, 2024, or sooner, to facilitate the
sample selections.
Documents requested, if available:
1.
List of 50.65 (a)(1) SSCs from the past 5 years
2.
List of maintenance rule functional failures (including preventable) from the past 5 years
3.
Most recent evaluation of maintenance effectiveness required per 10 CFR 50.65(a)(3)
4.
Maintenance rule scoping and performance criteria document
5.
List of preventative maintenance deferrals and preventative maintenance change
requests in the last 5 years
6.
Equipment reliability characterization and preventative maintenance program procedures
7.
List of 10 CFR Part 21 Reports applicable to the site from the past 5 years
8.
Site specific corrective actions associated with component failures, or tagged with
aging, age-related, wear, accelerated wear, abnormal wear, accelerated
degradation, abnormal degradation, corrosion, degradation, etc.
9.
List of technical specification operability determinations from the past 5 years
10. List of risk-significant long-lived passive SSCs (for licensees in the period of extended
operation (PEO)
11. Aging management programs (AMPs) and any plant-specific or industry operating
experience reviews that have been used to update aging management activities
(for licensees in the period of extended operation)
12. List of top 100 most risk-significant structures and components. If possible, designate
the component as active or passive in the risk ranking
2
13. List of RISC-1, RISC-2, and RISC-3 SSCs (for licensees that implement
10 CFR 50.69)
14. Safety significant functions identified during the RISC categorization process, and
alternative treatment requirements (for licensees that implement 10 CFR 50.69)
15. Last feedback and process adjustment required per 10 CFR 50.69(e)(1) (for license
that implement 10 CFR 50.69)
16. Site specific probabilistic risk assessment (PRA) identifying risk-significant functions
17. Technical specifications and technical requirements manual, including applicable bases
documents
18. List of systems (system numbers/designators and corresponding names)
Enclosure 2
Enclosure 2: Requested Information to Support Age-Related Degradation Inspection
The team lead will identify samples (i.e., structures and components) after the information
gathering visit. The documents and information requested below should generally be made
electronically available to the inspection team for the team's use both on-site and off-site. At the
end of the inspection, the documents in the team's possession should not be retained.
This document request is based on typical documents that a generic plant might have. As such,
this document request is not meant to imply that any specific plant is required to have all the
listed documents. In addition, your plant-specific document titles may vary from the document
titles listed below. We also request that the information provided be sorted by the list below for
each sample.
The following information is requested by October 4, 2024, or sooner, to facilitate the
inspection.
1.
List of corrective action documents for the last 10 years
2.
Maintenance, surveillance, testing, inspection, and condition monitoring testing
requirements, acceptance criteria, and periodicities
3.
Bases documents associated with maintenance, surveillance, testing, inspection, and
condition monitoring testing requirements, acceptance criteria, and periodicities
4.
Last 2 years of maintenance, surveillance, testing, inspection, and condition monitoring
testing results; for periodicities greater than 2 years, the last two test results
5.
Self-imposed and vendor recommendations
6.
If available
a)
Equipment reliability category/characterization (e.g., non-critical,
run-to-maintenance, etc.)
b)
Preventative maintenance templates for the maintenance strategy
c)
System design basis documents and the specific updated final safety analysis
report section that describes the function
d)
Piping and instrumentation drawings (P&IDs) and electrical one-line drawings
e)
Control circuit drawings
f)
Design/procurement specifications
g)
List of applicable modifications for the component
If you have questions regarding the information requested, please contact the lead inspector.